Professional Documents
Culture Documents
Smed - Single Minute Exchange of Moulds
Smed - Single Minute Exchange of Moulds
Smed - Single Minute Exchange of Moulds
Welcome and
Introductions
1
Four Major Factors in
Production Flow
Transform
Looking at these
Inspect/Rework factors, we can
create a definition
Transport of waste.
Store
2
What Is Lead Time?
To the FG’s
Order Total Lead Time distribution
release
system
Trans- Change- Loss WIP Storage Transport, Finished
forma- over Time Handling Goods,
tion Delivery
3
Definition: Value-Adding
4
Definition: Non-Value-Adding
5
How Much Is Value-Adding?
Choose one of your products (unit or small
batch)
Estimate manufacturing lead time for
processing the product
Identify and list each
conversion/transformation operation in the
process and the time taken to transform one
unit (or batch)
Calculation of value-adding ratio (percent):
Total time for value-adding operations
x 100 = ____% (Value-adding ratio)
Total manufacturing lead time
6
Process or Flow Time
Non-Value- 5%
Adding 95% Value-
Activities Adding
7
Non-Value-Adding Activity
“7 Deadly Wastes”
Value-Adding (5%) Defects
Inspection
Waiting
Storage/
Inventory
Rework / “re-”
Equipment
Over / Under
Downtime
Early / Late Production
8
A Large Inventory Hides Most
Production Problems
11
Quick Changeover:
The Key to Lead Time Reduction
Less adjustment less error less rework
Smaller runs fewer defects and scrap
Machine and scheduling flexibility reduces
the need for all types of inventory
Less inventory less space less carrying
cost
Less waste reduced lead time
12
Overall Equipment
Effectiveness (OEE)
14
Definition: Changeover Time
15
Document the Changeover:
Eight Steps
16
Step Three: Observe and
Record the Process
17
CHANGEOVER STUDY - OBSERVATION SHEET
Sequence Changeover Elapse Elemental INDIVIDUAL ELEMENTAL TIMES
Number Element Time Time 20 40 60 80 100 120 140 160 180 200 220
10
11
12
13
TOTAL TIME
18
Observe and Record
the Process
CHANGEOVER STUDY - OBSERVATION SHEET
Sequence Changeover Elapse Elemental INDIVIDUAL ELEMENTAL TIMES
Number Element Time Time 20 40 60 80 100 120 140 160 180 200 220
1 Get tools
Remove nuts &
2 washers
3 Remove platen
Return old platen
4 & get new one
Install new
5
platen
6 Install nuts &
washers
7 Connect heater
TOTAL TIME
19
Step Three: Observe and
Record the Process
20
Record Elapsed Time
CHANGEOVER STUDY - OBSERVATION SHEET
Sequence Changeover Elapse Elemental INDIVIDUAL ELEMENTAL TIMES
Number Element Time Time 20 40 60 80 100 120 140 160 180 200 220
22
Visually Document the Facts
Use yellow fact cards
Write one fact per card
Use full thoughts and Hose clamps are
phrases stiff and awkward
Be concrete & specific to fasten. Raja A.
5/29
Make cards legible
Sign and date cards
23
Now Let’s Face the Facts!
Observations
Questions
If elements have already been
documented, don’t rewrite
them.
What else is happening
beyond listed elements?
What other information might
be useful?
24
Step Four: Create a Bar Chart
CHANGEOVER STUDY - OBSERVATION SHEET
Sequence Changeover Elapse Elemental INDIVIDUAL ELEMENTAL TIMES
Number Element Time Time 20 40 60 80 100 120 140 160 180 200 220
Date
26
Step Five:
Define the Current Situation
Changeover Times
632
Target vs. Actual
6/7 Dates
27
Step Six:
Set Up a Changeover Chart
MACHINE/CHANGEOVER PROCESS:
Elements
Get Remove Remove Return Replace Replace Install Return Make Return Wait Make
Tools nuts & platen old & Platte nuts & heater old stock Adj’s tools for first
Elements washers get new washers get new heater pc. TOTAL
Time 43” 53” 23” 44” 17” 51” 12” 32” 34” 33” 06” 47” 392”
Tools
located
away from
Facts
station
Additional
Details
Internal
External
Set up a Quick
Converting
Internal to
Changeover Chart
External
Ideas to and post the facts
Streamline
Internals
Ideas to
Streamline
Externals
New
Standard
Procedure
28
Operation: BUST-A-GUT PRESS #1
Return
4’ 32”
5’ 06”
5’ 39”
32”
34”
33”
Step Seven : Make
a statement about
tools for the
Wait
12 06”
platen to 5’ 45”
13 heat
Make the
first 6’ 32” 47”
good piece
Team Members:
Rich
Ray
Mike
29
Document the
Changeover Process
Observe and record changeover process
Define the situation
Set up a QCO Chart and post facts
Visually display your findings
Establish a target and write a statement
Prepare and post a QCO Chart
30
Section Three:
Step-by-Step Improvement
Time-Consuming Setup Activities
32
Step-by-Step Improvement
33
Reducing Changeover Time:
A Step-by-Step Process
8. Develop new SOP
7. Test/practice new ideas
6. Select ideas to test/adopt
5. Streamline external activities
4. Streamline internal activities
34
Reducing Changeover Time:
Step 1
8. Develop new SOP
7. Test/practice new ideas
6. Select ideas to test/adopt
5. Streamline external activities
4. Streamline internal activities
3. Shift internal activities to external
2. Analyze changeover activities
35
Internal & External Activities
Internal External
Activities that must be Activities that can
performed while the be performed while
machine is shut down the machine is
or idle. running or producing.
Removing/attaching Getting stock or
dies, tools, fixtures, tools
guides, rails, etc. Die staging
Replacing/adjusting Cleanup &
same paperwork
Separate Internal and
External Elements
Operation: BUST-A-GUT PRESS #1 MACHINE/CHANGEOVER PROCESS:
Remove Return Replace Return
nuts & Remove old & Replace nuts & Install old stock Make Return Wait for Make
Current Situation Statement: Elements
Get
Tools washers platen get new Platte washers heater get new Adj’s tools heater first pc. TOTAL
2 Remove nuts
284”
and washers 285 235
3
4
Remove
platen
Store platen
330
445
45
115
Internal 53” 23” 44” 17” 51” 12” 34” 06” 47”
Install new
5 platen 535 90
Changeover Times
6
7
Replace nuts
and washers
Plug in heater
765
795
230
30
632 Target vs. Actual External 43” 32” 33” 108”
8 Get new cards 845 50
9
10
Adjust
Return tools
1050
1100
205
50
Converting
11 Heat up
Make first
1285 185 Internal to
12 good piece 1320 35 320
300 sec.
13 Time External
Target Date
Ideas to
Streamline
6/7 6/14
Dates 8/30 Internals
Target Statement: Team: Ideas to
Streamline
To get to a 300 Rich Externals
second changeover Ray New
by 8/30 Mike Standard
Procedure
37
Reducing Changeover Time:
Step 2
8. Develop new SOP
7. Test/practice new ideas
6. Select ideas to test/adopt
VIDEO
5. Streamline external activities
4. Streamline internal activities
3. Shift internal activities to external
2. Analyze changeover activities
38
Ask Why
39
Example of “5 Why” Analysis
Why? Answer Remedy
Why is there oil on the Oil leaks from Overhaul leaking part
floor? cylinder rod when
activated
Why did oil leak? The O-ring was cut Replace the O-ring
Why was the O-ring The rod was flawed Repair the flaw
cut?
Why was the rod Chips flew and Prevent flying chips
flawed? adhered to the rod
Dirt in the oil Drain the oil and
abrades the rod clean the inside
Why did dirt abrade the There are holes and Totally close the
rod? gaps on the upper holes and gaps
plate of the tank
40
Reducing Changeover Time:
Step 3
8. Develop new SOP
7. Test/practice new ideas
41
Reducing Changeover Time:
Steps 4 and 5
8. Develop new SOP
7. Test/practice new ideas
6. Select ideas to test/adopt
5. Streamline external activities
4. Streamline internal activities
42
Why We Streamline Externals
43
Time to Make Improvements
Brainstorm ideas
Record and then test ideas
Design implementation plan
Establish new procedures
Implement new changeover process
44
Reducing Changeover Time:
Step 6
8. Develop new SOP
7. Test/practice new ideas
6. Select ideas to test/adopt
5. Streamline external activities
4. Streamline internal activities
3. Shift internal activities to external
2. Analyze changeover activities
45
Document Ideas
46
Visually Document New Ideas
Operation: BUST-A-GUT PRESS #1 MACHINE/CHANGEOVER PROCESS:
Remove Return Replace Return old
Current Situation Statement: Elements
Get
Tools
nuts &
washers
Remove
platen
old & get
new
Replace
Platte
nuts &
washers
Install
heater
stock get
new
Make
Adj’s
Return
tools
Wait for
heater
Make
first pc. TOTAL
2 Remove nuts
and washers 285 235
Remove
3
4
platen
Store platen
330
445 115
45
Changeover Times
Internal 53” 23” 44” 17” 51” 12” 34” 06” 47” 284”
5 Install new
platen 535 90
6
Replace nuts 632 Target vs. Actual
7
and washers
Plug in heater
765
795
230
30
External 43” 32” 33” 108”
8 Get new cards 845 50
9 Adjust 1050 205
10
11
Return tools 1100 50 Converting
Heat up 1285 185
12
13
Make first
good piece 1320 35 320
300 sec. Internal to
Time
External
Target Date
Ideas to
Streamline
6/7 6/14 8/30
Dates Internals
48
Implementation Tips
49
Reducing Changeover Time:
Step 8
8. Develop new SOP
7. Test/practice new ideas
6. Select ideas to test/adopt
5. Streamline external activities
4. Streamline internal activities
3. Shift internal activities to external
2. Analyze changeover activities
50
Test and Standardize
New Procedures
Operation: BUST-A-GUT PRESS #1 MACHINE/CHANGEOVER PROCESS:
Remove Return Replace Return old
Get Remove Replace Install Make Return Wait for Make
nuts & old & get nuts & stock get TOTAL
Current Situation Statement: Elements Tools
washers
platen
new
Platte
washers
heater
new
Adj’s tools heater first pc.
2 Remove nuts
and washers 285 235
Internal
Remove
3
53” 23” 44” 17” 51” 12” 34” 06” 47” 284”
platen 330 45
4 Store platen 445 115
5 Install new
platen 535 90
Changeover Times
Replace nuts 632 Target vs. Actual
6
7
and washers
Plug in heater
765
795
230
30
External 43” 32” 33” 108”
8 Get new cards 845 50
10
Adjust
Return tools
1050
1100
205
50
Converting
11
12
Heat up
Make first
good piece
1285
1320
185
35 320
Internal to
300 sec.
Time
External
13
TOTAL TIME 1320
Target Date
Ideas to
Streamline Document new
6/7 6/14
Dates
8/30
Internals
procedures
Target Statement: Team: Ideas to
Streamline (elements)
To get to a 300 Rich Externals
second changeover Ray
by 8/30 New
Mike Standard
Procedure
Document new
standard times 51
Bustagut Rules
Do not remove studs.
Must be able to demonstrate ideas. Use
anything in this room (be creative).
Must have downward force on platen.
Must use the Bustagut press (think).
Must make a good diamond and then a
good circle and in that sequence.
First good yellow circle must be inspected.
52
New Standard Procedure
C h a n g e o v e r P ro c e d u re
P ro c e s s :_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ R e v is io n D a te : _ _ _ _ _ _ _ _
E x te r n a l E le m e n ts : D o n e p r io r to m a c h in e s h u t d o w n
Seq E la p s e d T a s k
. # Ta sk P e rs o n d o i n g ta s k T im e T im e
1
2
3
4
5
In te r n a l E le m e n ts : D o n e w h ile m a c h in e is s h u t d o w n
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
E x te r n a l E le m e n ts : D o n e a fte r th e fir s t g o o d p a r t
1
2
3
4
5 53
Items to be improved list
C h a n g e o v e r Im p ro v e m e n t L is t
P ro cess:________________________ D a te : _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Ta rg e t
# Ite m to b e im p ro ve d /P ro p o s e d Im p ro ve m e nt P e rs o n re s p o ns ib le D a te C o nfirm a tio n
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
54
Team Reports
15 - 20 minutes, team gets up for presentation
Effects Chart
Changeover Chart
5 Why Analysis Sheet
Improvements implemented, short term
(tomorrow) & long term (1-4 weeks)
New changeover standard operating
procedure: review estimated changeover time
Items to be improved
55
Items to have completed
MACHINE/CHANGEOVER PROCESS:
Operation: BUST-A-GUT PRESS #1
Remov Retu Replac Retur
Current Situation Statement: Elements Ge Remov Repla Insta Mak Retu Wait Mak TOT
e nuts rn e nuts n old
t e ce ll e rn for e AL
The changeover on Press #1 from Time & old & & stock 392”
To platen Platte heat Adj’ tools heat first
Effects Chart
diamonds to circles took 392 seconds
as done by Rich on July 24th at 10AM Additional
ols
Tools
located
away
washer
s
get
new
washer
s
er
get
new
s er pc.
from
using platen #1. Details station
DATA:
NCE
1
NO.
Changeover Study Observation Worksheet
SEQUE CHANGEO
VER
ELAP
SED
Collect tools
ELEMENT
ELEM
ENT
TIME50 TIME
20 40 60 INDIVIDUAL
50
ELEMENT TIME
80 100120140160180200220
Changeover
Remove nuts
Chart
2 and washers 285 235
3 Remove
330 Internal 284”
4
platen
Store platen445
45
115 53” 23” 44” 17” 51” 12” 34” 06” 47”
5 Install new
platen
Replace
535
nuts
90 Changeover Times
6 and washers 765 230
632 External 108”
7 Plug in heater
8 Get new cards
795 30 43” 32” 33”
845 50
9 Adjust 1050 205 Converting
Target Date
Ideas to
Streamline
6/7 6/14 Dates 8/30 Internals
Target Statement: Team: Ideas to
To get to a 300 Streamline
Rich Externals
second Ray
changeover by Mike New
8/30 Standard
Procedure
C h a n g e o v e r P ro c e d u re C h a n g e o v e r Im p ro v e m e n t L is t
P ro c e s s :_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ R e v is io n D a te : _ _ _ _ _ _ _ _ P ro c e s s :_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ D a te : _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
E x te r n a l E le m e n ts : D o n e p r io r to m a c h in e s h u t d o w n
T a rg e t
Seq E la p s e d Task # Ite m to b e i m p ro ve d /P ro p o s e d Im p ro ve m e n t P e rs o n re s p o n s i b le D a te C o n fi rm a ti o n
. # Task P e r s o n d o i n g ta s k T im e T im e
W h y -W h y A n a ly s is 1
2
3
1
4 3
5
4
In te r n a l E le m e n ts : D o n e w h ile m a c h in e is s h u t d o w n
5
1
2 6
W hy? A ns w e r R e m e dy 3
4 7
5
8
6
7
Example 12
13
14
15
Procedure 12
13 improved
14
16
17 15
18
19 16
20
17
21
22 18
23
24 19
25
26 20
27
21
28
29 22
E x te r n a l E le m e n ts : D o n e a fte r th e fir s t g o o d p a r t 23
1 24
2
3
4
5
25
26
56
Large Lot Loop
Not
Setup a
“Win-Win”
Takes a Situation
Long Time
Don’t Learn
Run Large
Better
Lots
Techniques
Don’t
Setup too
often
57
Quick Changeover Results
58
Plant Floor Application Exercise
Phases
Phase I: Observe changeover
Phase II: Record information on QCO Chart
TODAY
Phase III: Prepare to reduce changeover
time
Phase IV: Reduce changeover time
Phase V: Report on achievements
59
Section Four:
61
Opportunities for Improvement
80% Workplace Management
10% Equipment
62
Example: SCOTT MACHINE
Oxford
20
18
16
14 Reduced changeover time
12 Observ ed
10 1s t Le v e l
from 16.8 minutes to 9.5
8 Target minutes in one day.
6
4
2
0
63
What We Can Expect
Changeover Time
RUN RUN
1 Internal B
A
START -- Define Internal and External Elements
64
Wrap-up
65