Professional Documents
Culture Documents
Project Management
Project Management
Chapter 3
Project Management
OBJECTIVES
Project Management
Defined
Activity 1
Activity 2
Activity 3
Activity 4
Activity 5
Activity 6
Time Horizontal
HorizontalAxis:
Axis:Always
AlwaysTime
Time
©The McGraw-Hill Companies, Inc., 2004
6
Pure Project
Defined
A pure project is where a self-contained team
works full-time on the project
Structuring Projects Pure Project:
Advantages
• The project manager has full authority
over the project
• Team members report to one boss
• Shortened communication lines
• Team pride, motivation, and
commitment are high
©The McGraw-Hill Companies, Inc., 2004
7
Functional Project
Defined
A functional project is housed within a
functional division
President
Research and
Engineering Manufacturing
Development
Example,
Example, Project
Project “B”
“B” is
is in
in the
the functional
functional
area
area of
of Research
Research and
and Development.
Development.
©The McGraw-Hill Companies, Inc., 2004
9
Structuring Projects
Functional Project: Advantages
• A team member can work on several
projects
• Technical expertise is maintained within
the functional area
• The functional area is a “home” after the
project is completed
• Critical mass of specialized knowledge
Structuring Projects
Functional Project: Disadvantages
Structuring Projects:
Matrix Project Organization Structure
President
Research and
Engineering Manufacturing Marketing
Development
Manager
Project A
Manager
Project B
Manager
Project C
©The McGraw-Hill Companies, Inc., 2004
12
Structuring Projects
Matrix: Advantages
• Pinpointed responsibility
Structuring Projects
Matrix: Disadvantages
1 Project 1 Project 2
Network-Planning Models
• A project is made up of a sequence of
activities that form a network representing a
project
• The path taking longest time through this
network of activities is called the “critical
path”
• The critical path provides a wide range of
scheduling information useful in managing a
project
• Critical Path Method (CPM) helps to identify
the critical path(s) in the project networks
• 1. Activity Identification
• 2. Activity Sequencing and Network
Construction
• 3. Determine the critical path
– From the critical path all of the project and
activity timing information can be obtained
A None 2
B A 1
C B 1
D C 2
E C 5
F D,E 5
D(2)
G F 1
E(5)
Example 1:
Determine late Hint:
Hint:Start
Startwith
withLF=15
LF=15or or
the
thetotal
totaltime
timeof
ofthe
theproject
project
starts and late finish ES=4 and
andgo
gobackward
backwardininthe
the
times EF=6 network
networkfrom
fromGGto
toA.
A.
LS=4
LF=9
©The McGraw-Hill Companies, Inc., 2004
24
LS=4
LF=9 Duration = 15 weeks
©The McGraw-Hill Companies, Inc., 2004
25
Immediate
Task Predecesors Optimistic Most Likely Pessimistic
A None 3 6 15
B None 2 4 14
C A 6 12 30
D A 2 5 8
E C 5 11 17
F D 3 6 15
G B 3 9 27
H E,F 1 4 7
I G,H 4 19 28
Opt.
Opt. Time
Time ++ 4(Most
4(MostLikely
LikelyTime)
Time) ++ Pess.
Pess. Time
Time
Expected
ExpectedTime
Time == 66
©The McGraw-Hill Companies, Inc., 2004
27
Opt.
Opt. Time
Time ++ 4(Most
4(MostLikely
LikelyTime)
Time) ++ Pess.
Pess. Time
Time
Expected
ExpectedTime
Time == 66
©The McGraw-Hill Companies, Inc., 2004
28
Opt.
Opt. Time
Time ++ 4(Most
4(MostLikely
LikelyTime)
Time) ++ Pess.
Pess. Time
Time
Expected
ExpectedTime
Time == 66
©The McGraw-Hill Companies, Inc., 2004
29
Example 2. Network
Duration = 54 Days
C(14) E(11)
A(7) H(4)
D(5) F(7)
I(18)
B G(11)
(5.333)
p(t < D)
D=53
t
TE = 54
DD -- TTEE
ZZ ==
cpcp
22
Pessim.
Pessim. -- Optim.
Optim.)22
Activity variance, = 22
(
Activity variance, = ( )
66
path.)
©The McGraw-Hill Companies, Inc., 2004
32
p(t < D)
t
TE = 54
D=53
D
D -- TTEE 53 53--54
54
ZZ == == == -.156
-.156
cpcp
22 41
41
p(Z
p(Z<< -.156)
-.156) == .438,
.438, or
or 43.8
43.8 %
% (NORMSDIST(-.156)
(NORMSDIST(-.156)
There
There isis aa 43.8%
43.8% probability
probability that
that this
this project
project will
will be
be
completed
completed in in less
less than
than 53
53 weeks.
weeks.
©The McGraw-Hill Companies, Inc., 2004
33
•• What
What isis the
the probability
probability that
that the
the project
project
duration
duration will
will exceed
exceed 56
56 weeks?
weeks?
p(t < D)
t
TE = 54
D=56
D
D -- TTEE 56 56--54
54
ZZ == =
22 =
== .312
.312
cp
cp
41
41
p(Z
p(Z >> .312)
.312) == .378,
.378, or
or 37.8
37.8 %
% (1-NORMSDIST(.312))
(1-NORMSDIST(.312))
©The McGraw-Hill Companies, Inc., 2004
35
Time-Cost Models
CPM Assumptions/Limitations
• Project activities can be identified as entities (There
is a clear beginning and ending point for each
activity.)
• Project activity sequence relationships can be
specified and networked
• Project control should focus on the critical path
• The activity times follow the beta distribution, with
the variance of the project assumed to equal the sum
of the variances along the critical path
• Project control should focus on the critical path
End of Chapter 3