The document provides details for designing the base plate, foundation, and erection sequence for a column. It specifies dimensions and loads for the base plate and foundation. It also outlines 10 steps for erecting the structure, starting with checking anchor bolts, installing columns at a braced bay, and finishing with a final inspection. Safety is ensured by fully constructing bays before moving to subsequent elements.
The document provides details for designing the base plate, foundation, and erection sequence for a column. It specifies dimensions and loads for the base plate and foundation. It also outlines 10 steps for erecting the structure, starting with checking anchor bolts, installing columns at a braced bay, and finishing with a final inspection. Safety is ensured by fully constructing bays before moving to subsequent elements.
The document provides details for designing the base plate, foundation, and erection sequence for a column. It specifies dimensions and loads for the base plate and foundation. It also outlines 10 steps for erecting the structure, starting with checking anchor bolts, installing columns at a braced bay, and finishing with a final inspection. Safety is ensured by fully constructing bays before moving to subsequent elements.
• Dia of anchor bolts= 20mm • No of bolts= 4 • Grade of bolts= 8.8 • Minimum spacing of bolts 2.5d Column section Geometry Base Plate • Size of base plate 650x450 • Check for base pressure 4N/mm2<0.45fck • Check for minimum thickness of base plate • Ts=8mm Base Plate • Required thickness ’t’ governed by bending moment about the X-axis
• Tx=14mm • Thickness provided=25 mm Foundation Load from column Self wt of footing Wt of soil
• Vertical Load: 1100 kN
• SBC= 300 kN/m2 @ 1.5 m • Step -1: size of footing: • Area of footing required = 1100/300 = 3.67 m2 Area provided 3 m x 2 m pressure on isolated footing pmax = 185kN/m2 Foundation • Step 2: Two way shear • Punching shear force = Factored load – (Factored average pressure x punching area of footing) • Thickness provided= 500 mm • Pedestal 750x550mm • Punching shear stress=0.389N/mm2
• Allowable shear stress=1.3 /mm2
• Step 3: Design for flexure • Provided 16 dia bar @ 140mm c/c Foundation • Step 4: Check for One-Way Shear • At a distance of ‘d’ from the face of of the pedestal • Nominal shear stress = Vu/(Bxd) = 0.275 N/mm2< 0.37 N/mm2 (table 19)
• Pedestal reinforcement 0.15%
ERECTION SEQUENCE
• Erection sequence should be
formed so as to establish a stable unit as quickly as possible and to attach the subsequent element
• Step 1: Anchor Bolt Checking
:Foundation levels are checked
• Step 2: Install Columns at
Braced Bay ERECTION SEQUENCE • Step3: Install other side columns
• Step 4: Install the 1st rafter
1st rafter that should be selected should be from the braced bay. • First rafter member is assembled on the ground and then lifted to the lifting position.
• Step5: Install the second rafter,
not releasing the crane until the purlins are installed and fly bracings are attached ERECTION SEQUENCE
• Step 6: Finish 100% of the braced bay
• Step 7: Alignment and Tightening of Braced Bay
• Step 8: Install the first end frame
• Step 9: Install all remaining columns, rafters and roof