Professional Documents
Culture Documents
Tax Remedies Summary
Tax Remedies Summary
Tax Remedies Summary
1977
Quantitative Meaningful
Raw Data Analysis Information
I. Rationale in using quantitative techniques
1 . Quantitative analysis is
a. Logical approach to decision making
b. Rational approach to decision making
c. Scientific approach to decision making
d. All of the above
Answer :d
Also known as Management Science, Decision Science, Operations Research. Was
pioneered by Frederick W. Taylor , a military researcher in the 1900.
2 . The first step in quantitative analysis
a. Defining a problem
b. Developing a model
c. Acquiring input data
d. Developing a solution
Answer :a
Other steps in order:
1. Testing the solution.
2. Analyzing the result.
3. Implementing the result.
The Quantitative Analysis Approach
Defining the Problem
Developing a Model
Developing a Solution
s = 10 f = 1,000 v=5
Number of spring sets sold = X
Profits = sX – f – vX
0 = sX – f – vX, or 0 = (s – v)X – f
Fixed cost
BEP = (Selling price per unit) – (Variable cost per unit)
3 . An input such as variable cost per unit and fixed costs for a model is an example of
a(an)
a. Decision variable
b. parameter
c. algorithm
d. Stochastic variable
Answer :b
4 . A deterministic model is one in which
a. There is some uncertainty about the parameters used in the model
b. There is a measurable outcome
c. There is complete certainty about the parameters used in the model
d. Outcome is known
Answer :c
An example of deterministic model is costs reduction if we reduce operating costs by 20%
then the value is known for certain.
Probabilistic model – is the model with chance or risks. An example would be if we market a
new product there is a 60% chance that the market wil be favorable and 40% chance
5 . Algorithm means
a. Based from Algebra
b. Was named after the mathematician Algo
c. Series of steps or procedures to be repeated
d. All of the above
Answer :d
6 . An analysis to determine how a solution would change if there are changes in the model
or input data is called
a. Sensitivity or postoptimality analysis
b. Schematic analysis
c. Iconic analysis
d. All of the above
Answer :a
BEP = FC/CMU =P300,000/P60= 5,000 Units, what happens to BEP if fixed costs doubles.
P600,000/P60=10,000 Units, all things being equal BEP wil increase if fixed costs increase.
I . Decision theory And Decision Making Under Certainty, Risk and Uncertainty
7 . Decision theory is
a. An analytical and systematic approach to decision making.
b. A non-mathematical analysis of decision making
c. Is the study of historical decision
d. None of the above
Answer :a
8 . A good decision should be
a. Based on logic
b. Considers all available data
c. Considers all possible alternatives
d. All of the above
Answer :d
9 . What is the second step in decision theory
a. Define the problem
b. List possible alternatives
c. Identify possible outcomes or state of nature
d. List profit or payoff of each combination of alternatives or oucomes
Answer :b
Other steps in order:
1. Select one of the mathematical decision theory models.
2. Apply the model and make your decision.
10 . Is a type of decision making environment
a. Decision making under certainty
b. Decision making under risk
c. Decision making under uncertainty
d. All of the above
Answer :d
Decision making under certainty
If you win the lotto and invest at a 6% government security then you are certain
that the return will be 6% of your investment.
Decision making under risk
If you win the lotto and go to the casino and play blackjack with all your
winnings there is a 50% chance of doubling the earnings and a 50% risk of
loosing all the earnings. Here there are two possible outcomes and their
probabilities are known.
Decision making under uncertainty
Deciding to embark on a new business endeavor without any feasibility studies.
11 . Expected monetary value is defined. as
a. The expected value or mean value
b. The long run average value that would result if the decision is
repeated a large number of times
c. Sum of the possible payoffs of the alternative, each weighted by that
payoff occuring
d. All of the above
12 . Mr. Chubby Lito is considering putting a photocopying shop near a university. He
has the option to open a small shop, medium shop or no shop at all. The market
for the shop can be good, average or bad and the probabilities are .20 for good
market, .50 for average and .30 for bad market. The profit and loss for each option
are shown in the table below. What action will you recommend?
Answer :b
State of Nature Good Average Bad Total
EMV - Small shop
Payoff 75,000 25,000 (40,000)
Probability 20% 50% 30%
Expected Monetary Value 15,000 12,500 (12,000) 15,500
Answer :a
Maximax is an optimistic decision approach which selects the
highest or maximum value.
Decision Table for 13 to 18
State of Nature
Strategy Favorable Market Unfavorable Market Average
1 10,000 (8,000) 1,000
2 8,000 (4,000) 2,000
3 - - -
10,000+(8,000)/2 8,000+(4,000)/2
14 Dough and Ghull are two friends who wants to put up a
. business that will provide word processing services to students
who are doing their term paper and other academic
requirements. They have identified three strategies. Strategy 1,
involves purchasing expensive computer and laser printer
which could give them P10,000 net profit over the next two
years if the market is favorable. If however, the market is
unfavorable they can lose P8,000. Strategy 2 on the other hand
will require purchase of cheaper computer and printer which
could result to a P8,000 profit and P4,000 lose for the same
period. Finally, strategy 3 is to do nothing. Dough is a risk taker
while Ghull is risk averse. What strategy would Dough choose?
a. Strategy 1
b. Strategy 2
c. Strategy 3
d. Any strategy will do
Answer :b
Decision Table for 13 to 18
State of Nature
Strategy Favorable Market Unfavorable Market Average
1 10,000 (8,000) 1,000
2 8,000 (4,000) 2,000
3 - - -
10,000+(8,000)/2 8,000+(4,000)/2
19 An optimistic decision making which choose the alternative
. with the highest return
a. Maximax
b. Maximin
c. Equallly likely approach
d. Marginal analysis
Answer :a
20 An outcome or occurrence over which the decision maker has
. little or no control
a. State of nature
b. Opportunity loss or regret
c. Minimax regret
d. Expected value of perfect information
Answer :a
21 A graphical presentation of a decision is a
.
a. Decision tree
b. Decision matrix
c. Decision table
d. Decision graph
22 A decision node is represented by
.
a.
b.
c.
Answer :a
b. is a state of the nature node c. is a flowcharting symbol for
decision
23 Which of the following is a step in a decision tree
.
a. Define the problem
b. Structure or draw the decision tree
c. Assign probabilities to the states of nature
d. All of the above
Answer :d
Other steps in order:
1. Estimate payoffs for each possible combination of alternatives
and states of nature
2. Solve the problem by computing expected monetary values
(EMVs) for each state of nature node.
24 A group of CPA’s is considering constructing a firm. If the
. demand for accounting services is high (favorable market) the
accountants will realize a profit of P100,000. If the market will be
unfavorable they could lose P40,000. in the absence of market
data, the accountants guess is that there is a 50-50 chance of
the success of the firm. What should the CPA’s do? What is the
Expected Value With Perfect Information? What is the Expected
Value Of Perfect Information? If an Economic Reasearch Firm
approached the CPA’s and charge them P50,000 to provide
them with accurate data as to the favorableness of the market
towards accounting services what should the CPA’s do?
Payoff
Favorable 50% 100,000
30,000
Construct firm
Unfavorable 50%
-40,000
Do nothing
P0
EVPI 20,000
Consultancy Fee 50,000
Excess of Cost Over Benefit - Reject -30,000
25 . The pay off table of two mutual funds for investment are shown below:
Requirement:
a. Draw the decision tree
b. Which fund is better?
c. What amount of peso return of Fund A in a good economy be to make
an investor indifferent to both funds?
Payoff
Good 20% P10,000
Poor 50%
(P5,000)
Poor 50% P0
EMV Fund A = (.20)(P10,000)+(.30)(P2,000)+(.50)(-P5,000) = P100
Answer :a
Utility- The overall value or worth of a particular outcome
Utility Theory- A theory that allows decision makers to incorporate
their risk preference and other factors iin their decision
Utility Curve- A graph that shows that shows the relationship
between utility and monetary values
Utility Assessment- process of determining the utility of any
outcome
27 . In the past few years the traffic problem in Roel’s town have gotten worse.
Now Broad Street is congested about half of the time. The normal travel
time to work for Roel is only 15 minutes when Broad St. is used and there
are no congestions. With congestion it takes 40 minutes to get to work. If
Roel decides to take the expressway, it will 30 minutes regardless of the
traffic condition. Roel’s utility for travel time is 15 minutes=0.9, 30
minutes=0.7 and 40 minutes = . 20.
a. Which route will minimize Roel’s travel time?
Broadstreet 27.5 minnutes = (40x.50)+(15X.5)
b. Which route will maximize Roel’s utility?
Expressway = .70
Broadstreet = .55 = (.20)(.50)+(.90)(.50)
c. When it comes to travel time, is Roel a risk seeker or a risk
avoider?Risk Avoider
Decision Tree Example
p = 0.50 15 Mins
U(.90) = 0.50
(1 – p) = 0.50 40 Mins
U(.20) = 0.50
30 Mins
Figure 3.8
U.(0.70) = p = 1.0
Answer :d
Utility Curve
Risk
Avoider
Utility
Risk
Seeker
Monetary Outcome
Figure 3.10
29 . Jacquie is planning to put up a grocery store either at the downtown or the
mall or the busy traffic circle. The following are the peso values she
calculated:
Answer :c
Maximize profit=P15X + P25Y
Subject to constraints=
3X + 6Y < 600 ( mat a)
6X + 4Y < 880 (mat b)
Use trial and error by computing the contribution margin for all
choices. The choice that give the highest CM without violating the 2
constraint is the answer.
A violates 2nd constraint:
6(148)+4(0)=888
B CM is only P2,500= 15(0)+25(100)
C CM is P2,800 = 15(120)+25(40)
D violates 1st constraint:
=840
Second alternative is to graph the constraint and get the feasible area
32 . The dean of Chubby University must plan the school’s course offerings for
the first semester. Student demands make it necessary to offer at least 30
undergraduate and 20 graduate courses in the term. Faculty contracts also
dictate that at least 60 courses be offered in total. Each undergraduate
course taught costs the college an average of P2,500 in faculty wages, and
each graduate course costs P3,000. How many undergraduate and
graduate courses should be taught in the first semester so that total
faculty salaries should be kept at a minimum?
33. Which of the following is not a property of all linear programming
problems?
ANSWER: c
ANSWER: c
A C F
Build Internal Construct Install Control
Components Collection Stack System
E H
Start Inspect Finish
Build Burner
and Test
B D G
Modify Roof Pour Concrete and Install Pollution
and Floor Install Frame Device
Figure 13.1
Activity Times
• In some situations, activity times are known with
certainty
• CPM assigns just one time estimate to each activity and
this is used to find the critical path
• In many projects there is uncertainty about activity times
• PERT employs a probability distribution based on three
time estimates for each activity
• A weighted average of these estimates is used for the
time estimate and this is used to determine the critical
path
Activity Times
• The time estimates in PERT are
Probability of 1 in 100
of a Occurring
Probability
Probability of 1 in 100
of b Occurring
Activity Time
Most Most Most
Optimistic Likely Pessimistic
Time Time Time
(a) (m) (b)
Figure 13.2
Activity Times
• To find the expected activity time (t), the beta distribution
weights the estimates as follows
a 4m b
t
6
Variance
6
Activity Times
• Time estimates (weeks) for General Foundry
EXPECTED
MOST TIME, VARIANC
ACTIVIT OPTIMISTIC PROBABL PESSIMISTI t = [(a + 4m + E,
Y ,a E, m C, b b)/6] [(b – a)/6]2
A 1 2 3 2 4/36
B 2 3 4 3 4/36
C 1 2 3 2 4/36
D 2 4 6 4 16/36
E 1 4 7 4 36/36
F 1 2 9 3 64/36
G 3 4 11 5 64/36
H 1 2 3 2 4/36
Table 13.2
25
How to Find the Critical Path
• We accept the expected completion time for each task
as the actual time for now
• The total of 25 weeks in Table 13.2 does not take into
account the obvious fact that some of the tasks could be
taking place at the same time
• To find out how long the project will take we perform the
critical path analysis for the network
• The critical path is the longest path through the network
How to Find the Critical Path
• General Foundry’s network with expected activity
times
A 2 C 2 F 3
E 4 H 2
Start Finish
B 3 D 4 G 5
Figure 13.3
How to Find the Critical Path
• To find the critical path, need to determine the following
quantities for each activity in the network
1. Earliest start time (ES): the earliest time an activity can
begin without violation of immediate predecessor
requirements
2. Earliest finish time (EF): the earliest time at which an
activity can end
3. Latest start time (LS): the latest time an activity can
begin without delaying the entire project
4. Latest finish time (LF): the latest time an activity can
end without delaying the entire project
How to Find the Critical Path
• In the nodes, the activity time and the early and late
start and finish times are represented in the following
manner
ACTIVITY t
ES EF
LS LF
A t=2
ES = 0 EF = 0 + 2 = 2
Start
B t=3
ES = 0 EF = 0 + 3 = 3
How to Find the Critical Path
• General Foundry’s ES and EF times
A 2 C 2 F 3
0 2 2 4 4 7
E 4 H 2
Start 4 8 13 15 Finish
B 3 D 4 G 5
0 3 3 7 8 13
Figure 13.4
How to Find the Critical Path
• Latest times are computed as
• For activity H
LS = LF – t = 15 – 2 = 13 weeks
How to Find the Critical Path
• General Foundry’s LS and LF times
A 2 C 2 F 3
0 2 2 4 4 7
0 2 2 4 10 13
E 4 H 2
Start 4 8 13 15 Finish
4 8 13 15
B 3 D 4 G 5
0 3 3 7 8 13
1 4 4 8 8 13
Figure 13.5
How to Find the Critical Path
• Once ES, LS, EF, and LF have been determined, it is a
simple matter to find the amount of slack time that each
activity has
A 2 C 2 F 3
0 2 2 4 4 7
0 2 2 4 10 13
E 4 H 2
Start 4 8 13 15 Finish
4 8 13 15
B 3 D 4 G 5
0 3 3 7 8 13
1 4 4 8 8 13
Figure 13.6
Probability of Project Completion
• The critical path analysis helped determine the
expected project completion time of 15 weeks
• But variation in activities on the critical path can affect
overall project completion, and this is a major
concern
• If the project is not complete in 16 weeks, the foundry
will have to close
• PERT uses the variance of critical path activities to
help determine the variance of the overall project
15 Weeks
(Expected Completion Time)
Figure 13.7
Probability of Project Completion
• The standard normal equation can be applied as
follows
Due date Expected date of completion
Z
T
16 weeks 15 weeks
0.57
1.76 weeks
Probability
(T ≤ 16 Weeks)
is 71.6%
15 16
Time
Weeks Weeks
Figure 13.8
What PERT Was Able to Provide
• PERT has been able to provide the project manager
with several valuable pieces of information
• The project’s expected completion date is 15 weeks
• There is a 71.6% chance that the equipment will be in
place within the 16-week deadline
• Five activities (A, C, E, G, H) are on the critical path
• Three activities (B, D, F) are not critical but have
some slack time built in
• A detailed schedule of activity starting and ending
dates has been made available
37. The project described by
ANSWER: b
A=6 B=2
C=8
38. Development of a new deluxe version of a particular software product is
being considered. The activities necessary for the completion of this are
listed in the table below.
C=3 F=2
V. Learning Curve
39 . A measure of increased efficiency
a. Learning curve
b. Learning rate
c. Continuous improvement
d. Value added activity
Answer :a
40. Chubby Manufacturing is making a new product. The expected labor time
for the first batch is 10 hours, and the expected learning rate is 80%.
Prepare a schedule that illustrates the learning curve.
(a) (b) (a) x (b)
Output Average Time Total Time
1 10(given) 10
2 8(10 x .80) 16 (8X2)
4 6.4(8 x .80) 25.6 (6.4X4)
8 5.12(6.4x .80) 40.96(5.12X8)
41 . Chubby Co. is bidding a contract to make eight batches of landing gear
assemblies for an aircraft co. Chubby’s engineers expects direct labor and
variable overhead for the first batch to be P80,000. Variable overhead is related to
direct labor. Chubby usually achieves an 80% learning rate.
a. Determine the expected average cost for direct labor and variable overhead
for the eight batches.
b. Determine the expected total cost for direct labor and variable overhead for
the eight batches.
a. and b. P40,960 and P327,680
b -.3219
Y = aX , Y = P80,000 x 8
Y = P40,960 rounded
1 2 3 4
(a) Average number of customers per 50 50 50 50
shift
(b) Average waiting time per customer 7 4 3 2
(minutes)
(c) Total waiting time per shift 350 200 150 100
(a x b)
(d) Estimated cost per minute of waiting $1 $1 $1 $1
(e) Value of lost time or waiting cost (c x $350 $200 $150 $100
d)
(f) Salary cost per shift $70 $140 $210 $280