Professional Documents
Culture Documents
CPPA
CPPA
3 CPPA
CPPA
1. Background
Restructuring of Power Sector
5 CPPA
Major Objectives of Corporatization
1. Move towards competitive power market by
eliminating government’s monopoly
2. Manage an efficient, stable and economical power
system through transparent operations.
3. Attract foreign investment in the power generation by
providing equal opportunities to IPPs
4. Make power sector profitable for all stakeholders
6 CPPA
Components of NTDC
Central Power
System
Purchase
Operator
National Agency (CPPA)
Transmission
and Dispatch
Company Contracts
Transmission (NTDC) Registrar &
Network Power
Operator Exchange
Administrator
7 CPPA
Important Milestones
Expected in
Autonomous functioning of CPPA
near future
8 CPPA
CPPA
2. CPPA An Overview
Important Facts
1. CPPA was created by Government of Pakistan
under Restructuring of Power Sector in 1992.
2. Working as an agent of NTDC, CPPA is mandated
to buy each unit of generated electricity for DISCOs.
3. It is a seller of electrical energy to whole sale
purchasers i.e. DISCOs and Bulk Power Consumers
including KESC.
4. CPPA is an entity with Zero Asset and Zero Liability;
it manages its business through wheeling charges.
10 CPPA
Existing Organizational Structure
Managing Director
Staff Officer
Technical
Chief Operating Officer/
General Manager
Manager Tech Manager Tech Manager IT Manager Manager HR&A Manager L&CA
(3) (2) (2) (4) (1) (1)
D.M (5) D.M (4) D.M (4) D.M (7) D.M (2)
A.M (5) A.M (4) A.M (4) A.M (13) A.M (2)
12 CPPA
Mission
We undertake to procure each
unit of electricity produced by
different sources and to sell it to
DISCOs and bulk consumers for
easing out the prevailing scarce
supply of electricity to the
consumers.
13 CPPA
Strategic Goal
CPPA to be acknowledged as a
trusted, professional and efficient
agency owing to its internationally
accepted working procedures, non-
discriminatory and transparent
business operations, and excellent
performance standards.
14
14 CPPA
Central Power Purchasing Agency
Objectives
1. Ensure verification of invoices from generators
(IPPs, GENCOs and WAPDA Hydel plants)
2. Execute settlement functions
(Billing to DISCOs and bulk consumers including
KESC under NEPRA determined mechanism)
3. Monitor functioning of different role players
(Generators, NTDC and Purchasers);
suggest changes in the SOPs
15 CPPA
Core Responsibility
16 CPPA
CPPA
3. A Snapshot of
Major Functions
CPPA’s Functions
1. Manage CDPs network for collection of energy data
2. Monitor functioning of meters installed at CDPs with
grid users (GENCOs, IPPs and DISCOs)
3. Undertake corrective measures for metering systems
errors
4. Establish Operating Committees, Metering Committees
and Interconnection Committees for IPPs
5. Reconcile and process energy data received from
Metering Committees (NTDC, IPPs and DISCOs)
6. Monitor compliance with respective PPA
18 CPPA
CPPA’s Functions (Continued)
7. Negotiate and enter into Energy Purchase Agreements
with RE Power Project Sponsors
8. Monitor compliance on the EPAs by both parties
9. Setup teams to witness generators’ Commissioning
Tests and Annual Dependable Capacity Tests
10.Process and execute necessary amendments to PPAs
11.Co-ordinate with Planning Power for technical studies
12.Participate in NEPRA public hearings
13.Co-ordinate with various NTDC departments for
arrangement of interconnection facilities
20 CPPA
I would put my money on the sun & wind energy.
What a source of power!... Thomas Edison
CPPA
4. Up to Date Progress
on Wind Power Projects
Status of Wind Power Projects
1. 27 IPPs with 1,898 MW of Wind Energy are on the way.
23 CPPA 23
NEPRA Determined Tariff for WPPs
Capacity Tariff Commercial
# IPP Name
(MW) (US$ C/kWh) Opr. Date
24 CPPA
NEPRA Determined Tariff for WPPs
Capacity Tariff Commercial
# IPP Name
(MW) (US$ C/kWh) Opr. Date
9 Metro Wind Power Ltd. 50.0 14.5236 -
25 CPPA
EPAs Signed for Wind Power Projects
Sr. Gross Expected
No. Project Name Location
Capacity COD
1. Fauji Fertilizer Company Energy Limited Jhimpir 49.5 MW May 2013
26 CPPA
Summarized Status of All WPPS
Inter-
Capacity Individual Expected
Sponsor Name Status of WPP Connection
Addition Capacity COD
availability
Fauji Fertilizer Company 50 Commissioned Commissioned Available
27 CPPA
Summarized Status of All WPPS
Inter-
Capacity Individual Expected
Sponsor Name Status of WPP Connection
Addition Capacity COD
Availability
Dawood 50 Negotiating EPA with CPPA/NTDC Jul-16 Dec-15
Wind Eagle -II 50 CPPA consented for Upfront Tariff Jul-16 Dec-15
28 CPPA
Grid Reinforcements for WPPs
• 220/132 kV Jhimir Substation of
750 MVA
• 220/132 kV Gharo Substation of
500 MVA
• Addition of 450 MVA Transformer
at Jamshoro 500/220 kV
• 155 km of 220 kV Transmission
Lines
• 192 km of 132 kV Transmission
Lines
Total Cost Estimate = Rs. 14,542 M
29 CPPA
CPPA
5. Status of Solar Power
Projects in Pakistan
Phase 1: Quaid-e-Azam Solar Park
1000 MW Power Evacuation Plan from Quaid-e-Azam Solar Park
31 CPPA
Phase 2: Quaid-e-Azam Solar Park
1000 MW Power Evacuation Plan from Quaid-e-Azam Solar Park
32 CPPA
Phase 3: Quaid-e-Azam Solar Park
1000 MW Power Evacuation Plan from Quaid-e-Azam Solar Park
5 Buksh Energy (Pvt) Ltd. Lodhran 10.0 MEPCO Tariff Granted by NEPRA
6 Safe Solar Power (Pvt) Ltd. Punjab 10.0 MEPCO Tariff Granted by NEPRA
7 Access Solar Power (Pvt) Ltd. Pind D.Khan 10.0 IESCO Tariff Granted by NEPRA
8 Roshan Power (Pvt) Ltd. Kasur 10.0 LESCO Under Process at PPDB
10 Sanjwal Solar Power (Pvt) Ltd Sanwajwal 5.04 IESCO Tariff Granted by NEPRA
11 Engro Powergen Qadirpur Ltd. Deharki 0.36 SEPCO Applied for Gen. Licence
12 Pakistan Engineering Council Islamabad 0.356 IESCO Applied for Gen. Licence
34 CPPA
CPPA
4. Some of Our
Business Processes
Flow of Revenue Cycle
36 CPPA
IPPs’ Invoices Verification Process
Verification of Monthly Energy
Purchase Price (EPP) Invoices
37 CPPA
GENCOs & WAPDA Hydel Invoicing
40 CPPA
Resource Potential of Wind Power
• The Pakistan Wind Map was developed by National
Renewable Energy Laboratory (NREL), USA in
collaboration with USAID.
41 CPPA 41
Resource Potential of Wind Power
42 CPPA
Target for Wind Power Development
• Keeping in view the huge potential and the
anticipated future energy needs, the GOP has
set a target of at least 5% of the total national
power generation capacity to be generated
through wind power.
• Study is being conducted by NTDC to ascertain
the share of renewable energy which can be
reliably connected to national grid.
43
43
CPPA
Incentives for Wind Power Development
GoP offers following incentives for setting up Wind Power Projects:
• Wind Risk (risk of variability of wind speed)
• Guaranteed Electricity Purchase
• Grid provision is the responsibility of the purchaser
• Protection against political risk
• Attractive Tariff (Cost plus 17% ROE), indexed to inflation and
exchange rate variation (Rupee / Dollar)
• Euro / Dollar Parity allowed
• Carbon Credits available
• No Import Duties on Equipment
• Repatriation of Equity along with dividends freely allowed
• Permission to issue corporate registered bonds
44 CPPA
CPPA
6. Roadmap to the Future
Plan Should be Realistic
46 CPPA
Join the Less Travelled Path
Not
EXCUSES My
Job
47 CPPA
Importance of Contemplated Roles
48 CPPA
Changing the Lens & Perceptions
49 CPPA
CPPA Performance Expectations
• Maintain absolute clarity of purpose
• Own your actions and then expect from people to do so
• Respect others while maintaining self respect
• Have complete faith in Allah Almighty with NO doubt
• Be brave to own your mistakes and flop ideas
• Reassess before delivering your ideas and thoughts
• Manage your resources well – first of all humans
• Acknowledge others’ performance specially the juniors
• Negate negative ideas, approaches and decisions
• Exhibit highest level of commitment with your goal
• Aim to stay at top and keep excelling – nothing less
50 CPPA
The Way Forward
1. Manage effective communication channel
2. Adopt true Corporatized Culture (Vision, Mission,
Goals, Objectives, Strategic Plan, Action Plan)
3. Capitalize on the outcome of each intervention
4. Proactively prepare for the change
5. Ensure close interaction among team members
6. Need to erase old practices and understandings.
7. All plans to be ambitious yet realistic.
8. No less than cutting edge performance
9. Value and strive for team efforts
51 CPPA
Objectives As Autonomous Entity
1. Maintain highest level of transparency
2. Ensure effective accountability
3. Exhibit non-discrimination among generators &
customers
4. Achieve highest efficiency through corporate culture
5. Build industry standard capacity to manage business
6. Prepare and execute business plan
7. Mitigate cash shortfall risks
8. Monitor functioning of different role players
9. Develop formalized business standards & procedures
52 CPPA
CPPA
Your questions would certainly
add value to
our approach, operations and
performance
Your Questions Would Add Value to
Our Approach, Tactics & Contribution.
Cost Estimate
Phase-I Cost: Rs.54
milliont
55 CPPA
Phase 2 Interconnection Scheme
Cost Estimate
Phase-II Cost: Rs.702
milliont
56 CPPA
Phase 3 Interconnection Scheme
Cost Estimate
Phase-III Cost: Rs.3,303
million
57 CPPA