Professional Documents
Culture Documents
3-Alcocer Cesin
3-Alcocer Cesin
3-Alcocer Cesin
1
1
Contract Types
– Cost Reimbursement:
• CNF, CPFF, CPIF, CPAW, Cost-Share
• T&M, LH
2
Cost -Type Contracts
Cost Risk: High >>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>> Low
Requirement
Definition Vague >>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>> Well Defined
3
CPFF / T&M Overview
4
Cost-Reimbursement
Contract Administration
5
T&M Contracts
8
Revisions to Cost-No Fee Contracts
Issues you must address:
9
Revisions to Cost-No Fee Contracts
Issues you must address, continued:
• Monitor invoices.
10
Revisions to Cost-Plus Type
Contracts
Issues you must address:
11
Revisions to Cost-Plus Type
Contracts
Issues you must address, continued:
– Completion
– Term Form
13
Cost-Reimbursement Scope
Approach: Completion vs. Term
Completion
• States a definite goal or target and specifying an
end product.
• Contractor must complete and deliver specified
end product (e.g., a final report of research
accomplishing the goal or target) within the
estimated cost, as a condition for payment of the
entire fixed fee.
• If work cannot be completed within estimated cost,
Government may require more effort without
increase in fee, provided Government increases
the estimated cost.
• FAR 16.306(d)
14
Cost-Reimbursement Scope
Approach: Completion vs. Term
Term Form
• Obligates contractor to devote a specified level of effort
for a stated time period.
• If performance is considered satisfactory by
Government, fixed fee is payable at expiration of
agreed-upon period, upon contractor statement that
level of effort specified in contract has been expended
in performing the contract work.
• Renewal for further periods of performance is a new
acquisition that involves new cost and fee
arrangements.
• FAR 16.306(d) 15
Quarterly Cost Status Reports
SCOPE
SCHEDULE COST
19
Adding Scope, Schedule, Cost
Step One – Existing Scope:
• Get cost-to-date and estimate to complete
existing, current work
• Get technical status to date
• Obtain hours to date and estimated hours-
to-complete for CPFF LOE Contracts.
• If there is a projected overrun, make sure
that Contractor does not mix up cost for
new work with overrun in order to get fee
on the overrun.
20
Adding Scope, Schedule, Cost
Step Three
• Summarize Changes. Map out how much
must be added to the contract to account
for (1) cost status of existing contract and
(2) proposed new work.
21
CPFF Completion Changes:
Fee-bearing Costs &
Non-fee-bearing Costs
• If SOW Scope is increased, the increased cost is
fee-bearing.
•
22
CPFF Changes: Fee-bearing
Costs & Non-fee-bearing Costs
23
CPFF Changes: Overruns
De-scope:
Preferable to a Partial Termination
Step One
• Get cost-to-date and estimate to complete
for current work.
• Get technical status to date
25
CPFF Changes: Descopes
Step Two
• Evaluate labor, material, travel, indirect costs,
profit for new work. Negotiate Cost Plus Fee
for Deleted Work:
• Look for the following when evaluating the
proposal:
– Underestimating labor, material
– Omitting types of labor or material
– Omitting Indirect Costs
– Omitting Profit
26
CPFF Changes: Descopes
Step Three
• Summarize Changes. Map out how much must be
added to and/or deleted from the contract to
account for (1) cost status of existing contract, and
(2) proposed deleted work.
27
Example 1: Scope Increase to
CPFF Completion-type Contract
Increased Scope Change on CPFF Completion,
Without Getting Cost-to-Complete Status
Quotation Instructions:
• Propose Estimated Cost and Fixed Fee for adding one
support package:
28
Example 1(a): Scope Increase to
CPFF Completion-type Contract
Increased Scope Change on CPFF Completion,
Buyer Obtained Cost to Complete Status, and
“Balanced the Books”:
Quotation Instructions –
• Provide Cost to Date through the Most Current Accounting
Period.
• Provide Technical Status To Date through most current
Accounting Period.
• Provide Estimated Cost to Complete for the Current Work.
• Propose Estimated Cost and Fixed Fee for adding one
support package.
Let’s look at the difference in the results
29
Example 2: Adding New Term to
CPFF-Level Of Effort Contract
Adding new Term Without Getting Cost and Hours-
to-Complete Status, e.g. “Balancing the Books”
Quotation Instructions:
• Propose Estimated Cost and Fixed Fee for adding 4 months.
Contract Cost
And Fee
Thru 8/31/07 New Contract
Term Neg. 9/1/07 – 12-31-07 Value
30
Example 2(a): Adding New Term to
CPFF-Level Of Effort Contract
Increased Scope Change on CPFF LOE, Buyer
Obtained Cost to Complete Status, and “Balanced
the Books”:
Quotation Instructions –
• Provide Cost to Date through the Most Current Accounting
Period.
• Provide Hours through Most Current Accounting Period.
• Provide Estimate to Complete thru Balance of Contract Term.
• Propose Estimated Hours to Complete thru Balance of
Contract Term
• Provide CPFF and Hours for new Term
Let’s look at the difference in the results
31
Example 3: De-Scope
Delete Task #4:
Quotation Instructions:
• Provide Cost to Date thru Most Current Accounting Period
• Provide Estimated Cost to Complete for the Current Work
• Get Technical Status on current work.
• Propose Detailed Deducted Estimated Cost and Fixed Fee for
deleting Task #4. Use current costs to price the proposal.
32
Group Exercise:
Fixing the Mismanaged CPFF
33
Group Exercise:
Fixing the Mismanaged CPFF
• Contractor quoted indirect rate of 387%; it was 186% when
contract was placed 3 years ago.
34
Summary
• Consider getting Quarterly Cost Status Reports
• Avoid adding and deleting funding off CPF’s as
if they are T&M’s. Go through the proper
processes.
• Ask the right questions of Line and Contractors.
• Evaluate Cost Status vs. Technical Completion
for Cost Type Contracts.
• Understand what is fee bearing and what is not.
35
Questions?
36