DIMENSIONERING

BETON DAN BAJA PADA KOLOM BALOK DAN PONDASI


KOLOM

KONSTRUKSI BETON TOTAL AREA PEMBEBANAN BETON = 243 m2


= AREA BASEMENT + LT 1 = 3 LT TOTAL AREA PEMBEBANAN BAJA
= 3 X 9 X 9 = 243 m2
= 810
KONSTRUKSI BAJA
TOTAL BEBAN PADA
= AREA PODIUM ( L + 2 + L + 3 )
= BETON = 243 X 1200 = 291.000 Kg
= 2 X 9 X 9 = 162 m2
AREA PEMBEBANAN = BAJA = 810 X 10.0000 = 810.000 Kg +

= TOWER ( KONSTRUKSI BAJA } = 1.101.600 Kg


= 8 X 9,0 X 9,0
= 648 m2
KUALITAS BETON K 450
= 1/3 X 450 = 150 Kg / cm

LUAS PENAMPANG KOLOM


= 1.101.600 : 150 = 7.344

BESAR KOLOM
= √7.344
85.697
90 = 90/90

AREA TOTAL PEMBEBANAN BAJA


KONT BAJA AREA PODIUM = ( Lt 2 + Lt 3 )
= 2 X 9,0 X 9,0
= 162 m2

AREA PEMBEBEBANAN
( KONT BAJA ) TOWER = 8 X 9,0 X 9,0
= 810 m2

TOTAL AREA PEMBEBANAN = 810.000 m2

TOTAL BEBAN PADA KOLOM = 810 X 1 = 810 TON

LUAS PENAMPANG KOLOM = 810 / 2250 Kg/Cm = 810.000 / 2.250 = 360


WF 600 X 200 LUAS PENAMPANG
= 134, 4 cm2 < 360 cm2

KING CROSS K 400 X 200 LUAS PB


NAMPANG 360 cm2
= 360 -134,4 = 225,6 X 2250
= 507, 600

BETON YANG TERSISA = 810 X 507,6


= 302,6
K 450 X 30% = 135 Kg/cm2

LUAS PENAMPANG BETON


X = 302.600 Kg / 135 = 2.241
= √2.241
= 47.399
= 50X50
PONDASI

Dik = L1 = 9m
L2 = 9m
N = 12 Lantai
P. Izin Digunakan = 50 Ton
Maka = L1 x L2 x N x BJ. Beton = N Tiang x P Izin
= N Tiang x 50.000
N. Tiang = 1.166.400 : 50.000
= 2,3328
= 3 Tiang Pancang
BALOK

Balok = L1 = 1/12 x Bentang


B. Induk = 1/12 x 900
= 75 cm
b = 2/3 x b
= 2/3 x 75
= 50 cm