Project Delivery Systems
Traditional delivery system
◦ Design – Bid – Build
Owner
Design-Build
Contractor
Design Sub-
Consultants Contractors
Design-build delivery system
Keuntungan :
-Singular responsibility Kelemahan :
-Kualitas -Perlu deskripsi yang
-Cost savings jelas ttg proyek dr
-Time savings owner
-Potential for reduced -Kesulitan menetapkan
administrative burden biaya kontrak kerja
-Mengetahui kebutuhan -Mahalnya biaya tender
biaya awal sejak dini -Kemungkinan
-Risk management rendahnya kualitas hasil
-Pemberian -Kurangnya kontrol
penghargaan terhadap sub-
kontraktor
Agency Construction Management
delivery system
Owner
Sub Sub
Consultants Contractors
Construction Manager-at-risk
Owner
A/E Construction
Manager
Sub Sub
Consultants Contractors
Other delivery systems
Owner design-builder
Owner
Design Construction
Department Department
Optional Own
Contractors
Workforce
Other delivery systems
Owner Construction Manager
CM Owner
A/E
Prime Contractors
Subs
Other delivery systems
Turnkey
Joint Venture
Members of a Project Team
Director of Operations/Construction
Project Manager
Project Engineer
Superintendent
Foreman
Owner’s Representative
Designer / A/E
Subcontractors
etc
PROCUREMENT_TENDER
Procurement
Procurement is the acquisition (purchase)
of goods and/or services at the best
possible total cost of ownership, in the
right quantity and quality, at the right time,
in the right place for the direct benefit or
use of governments, corporations, or
individuals, generally via a contract.
Tenders
Tendering is the traditional method for
obtaining a competitive price for the supply
of goods or services.
Tendering process is also used in many
instances to sell goods and services
Methods for Tender
Depending on the nature of the project
and situation on hand, there are three
methods for calling for tenders:
◦ By invitation
◦ By invitation after registration of
interest
◦ Public tenders
Tenders in Indonesia
According to Keppres 16/1994:
Pelelangan umum value > Rp. 50.000.000
Pelelangan terbatas value > Rp.
50.000.000
Pemilihan langsung value >15 – 50 million
Pengadaan langsung
- value up to 5 mil w/o SPK
- 5 – 15 million w SPK
Advantage of “Pelelangan umum”:
Large numbers of participants
Many cost offers for comparison
Disadvantages:
Participants are not wellknown
Must be careful
Methods of procurement:
Tenders
Direct Selection, i.e. choosing a supplier by direct negotiation
by comparing bids from several qualified suppliers
Direct appointment, i.e. choosing a supplier directly in cases
involving small-scale purchases or single suppliers or urgent
need, subject to approval of ministers or heads of local
government or state-owned enterprises, as appropriate;
Self-Management, i.e. planning and executing the contract by
the prospective purchaser of the good/services itself using its
own workers, equipment or contract workers.
All tenders must be completed and winners announced within
a minimum of 36 working days and maximum 45 working days
after the announcement of the tender.
Presidential Decree (Keppres) No. 18/2000
(http://www.usembassyjakarta.org/econ/indonesia2000.html)
(1) Contracts over this limit require the winning contractor, foreign or domestic, to
"cooperate with a small or medium scale company or cooperative in the implementation of
the contract."
Tender Steps
Preparation
Specification & Drawing
Tender Comitee
Requirement for bidders
Evaluation criteria
Implementation
Announcement/invitation
“Aanwijzing”
Tender meeting
Evaluation/ Appointment
Finishing
Return “Tender Bond”
SPK
Contract
Tender Document
Tender Fail
Bids that meet req. < 3 bidders
Bid value > standard
Value are not reasonable
Other bidder(s) objection is true
E-Procurement (Dept. PU)
PENGUMUMAN PELELANGAN
PAKET PEKERJAAN SATUAN KERJA
DILINGKUNGAN DEPARTEMEN PEKERJAAN UMUM
WAKTU PENDAFT
NO DATA NAMA PAKET PAGU DANA
ARAN
4 Peningkatan Lingkungan Permukiman Rp. 421,294,000 21 Mar 07 s/d 28 Mar
Kumuh 09
3 Dukungan Perkim pada pulau-pulau kecil Rp. 1,000,000,000 01 Mar 07 s/d 17 Mar
dan terpenci 08
2 Penyusunan Rencana Tata Bangunan dan Rp. 350,000,000 10 Jan 07 s/d 22 Oct
Lingkungan 07
1 Pemb. Jembatan Mure Piga Tahap II Rp. 3,200,000,000 01 Feb 07 s/d 08 Feb
08
TENDER DOCUMENT
Instructions to Tenderers
Terms & Conditions
◦ Price basis
◦ Terms of payment
◦ Legal clauses
◦ Basis for contract
Technical Specifications
◦ Functional requirements
◦ Performance requirements
◦ Operational and maintenance requirements, etc.
Appendices (Drawing, Data, etc.)
SCOPE OF TENDER
Scope of a tender may cover:
◦ Supply only of equipment and/or materials
◦ Supply, installation, and commissioning of a
system
◦ Design, supply, installation, and commissioning
of a system (Turnkey)
◦ Build, Own, Operate, and Transfer (BOOT)
It should be noted that the scope of tender
divides the responsibility of the implementation
of the system between the principal and the
supplier.
AWARD OF CONTRACT
The principal and the successful tenderer
(bidder) enter into a contract.
The tender document, along with any
amendments during the bidding process,
will be the basis of the contract.
A project manager on each side (principal
& tenderer) will be assigned to the
project.
KEPUTUSAN PRESIDEN ttg
PELELANGAN
Dalam perkembangannya Keputusan Presiden ( KEPRES ) mengalami
beberapa kali penyempurnaan, antara lain adalah sebagai berikut :