Network Performance Improvement For Natal and Tahun Baru 24 OCT 2018

You might also like

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 9

NARU 2018

NETWORK PERFORMANCE IMPROVEMENT FOR NATAL AND TAHUN BARU


24 OCT 2018
Content:
ORGANIZATION CHART
01 Information Structure organization and responsibility matrix

TIMELINE & TRACKER


02 Information time plan and progress activity

CLUSTER POI OPTIMIZATION


03 Information of POI CAPACITY, QUALITY AND COVERAGE IMPROVEMENT

CROWED MANAGEMENT
04 Information for crowed management details

PIC STANDBY TEAM


05 Information PIC team standby during NARU2018
Content:
ORGANIZATION CHART
01 Information Structure organization and responsibility matrix

TIMELINE & TRACKER


02 Information time plan and progress activity

CLUSTER POI OPTIMIZATION


03 Information of POI CAPACITY, QUALITY AND COVERAGE IMPROVEMENT

CROWED MANAGEMENT
04 Information for crowed management details

PIC STANDBY TEAM


05 Information PIC team standby during NARU2018
NARU 2018| Organization Chart
Content:
ORGANIZATION CHART
01 Information Structure organization and responsibility matrix

TIMELINE & TRACKER


02 Information time plan and progress activity

CLUSTER POI OPTIMIZATION


03 Information of POI CAPACITY, QUALITY AND COVERAGE IMPROVEMENT

CROWED MANAGEMENT
04 Information for crowed management details

PIC STANDBY TEAM


05 Information PIC team standby during NARU2018
NARU 2018 | Time Line and PIC
BEFORE AFTER
BRANCH / POI1 Grand Total
W41 W42 W46 W47 W48
GORONTALO 1 2 1 2 6
KAWASAN OUTLET DEVICE 1 1 2
MALL GORONTALO 1 1 2
Mudik's Route 1 1 2
KENDARI 1 3 4
KENDARI BEACH 1 1
MALL LIPPO KENDARI 1 1
Mudik's Route 1 1
PANTAI TORONIPA 1 1
KOLAKA UTARA 1 1 2
PANTAI RIA KOLAKA 1 1 2
MAKASSAR 1 1
Mudik's Route 1 1
MANADO 1 1 1 3
Mudik's Route 1 1
TONDANO STAT 1 1 2
PALU 3 3 1 5 12
AIRPORT PALU 1 1 2
LAPANGAN HAJI HAYUN TOLI-TOLI 1 1 2
Mudik's Route 1 1 2
PERTOKOAN PALU 1 1 2
POSO CITY 1 1 2
TOBOLI PARIGI 1 1 2
Grand Total 6 5 5 7 5 28
Content:
ORGANIZATION CHART
01 Information Structure organization and responsibility matrix

TIMELINE & TRACKER


02 Information time plan and progress activity

CLUSTER POI OPTIMIZATION


03 Information of POI CAPACITY, QUALITY AND COVERAGE IMPROVEMENT

CROWED MANAGEMENT
04 Information for crowed management details

PIC STANDBY TEAM


05 Information PIC team standby during NARU2018
NARU 2018 | MAP POI
NARU 2018

You might also like