Corrosion: Various Forms of Corrosion

You might also like

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 26

Corrosion

Various forms of Corrosion:-


1. Uniform corrosion
2. Galvanic corrosion
3. Crevice corrosion
4. Pitting corrosion
5. Stress corrosion
6. Fatigue corrosion
7. Erosion corrosion
8. Cavitation corrosion

4 March 2019 1
Corrosion

1. Uniform Corrosion
– Most common form of the corrosion, which is characterized by chemical
or electrochemical reaction which proceeds evenly and uniformly over
the entire exposed area
– The corrosive product may either form a protective layer on the metal or
as in the case of direct chemical attack, the corroded material will
dissolve in the corrosive environment
– This type of corrosion can be prevented or reduced by (i) Choice of
proper materials, (ii) Coatings
2. Galvanic Corrosion
– This occurs when two dissimilar metals are placed in contact
– The less resistant metal becomes anodic and the more resistant metal
cathodic

4 March 2019 2
Corrosion

3. Crevice corrosion
– This is an intense, localized corrosion, which occurs within crevices on metal
surfaces exposed to corrosives
– Crevice corrosion can be minimized by using welded joints instead of riveted
or bolted joints. Similarly in equipment sharp corners and stagnant areas
should be avoided

4. Pitting Corrosion
– This occurs between surfaces in close contact
– It is extremely localized and occurs due to presence of impurities, rough
spots and scratches
– Adding inhibitors to metals is helpful in reducing pitting

4 March 2019 3
Corrosion

5. Stress corrosion
– This corrosion is the result of internal or external stresses and corrosive
environment
6. Fatigue corrosion
– In this type of corrosion, cyclic loads combine with corrosion to cause corrosion
fatigue
7. Erosion corrosion
– Caused due to combination of corrosive fluid and mechanical wear resulting from
impingement of liquid or abrasion of solid particles
– This effect depends mainly on liquid velocity
– All types of equipment exposed to moving fluids are subject to erosion corrosion
– Some of these are piping systems, valves, pumps, blowers, centrifuges, agitators, heat
exchanger tubes, equipment for spraying fluids etc.

4 March 2019 4
Corrosion

8. Cavitation
– Occurs due to repeated collapse of vapor bubbles on a metal surface. This
causes mild physical damage to protective films, severe deformation and
fracture of surface
– Occurs in equipment where high velocity liquid flow and pressure changes
are encountered, such as pump impellers, resulting in vapor bubbles

4 March 2019 5
Cost Information Required

• Flowsheet
• Stream table
– Flows of each component in every stream
– Stream temperatures and pressures
– In some cases
• Enthalpies
• Densities, etc.
• Operating costs can be calculated
– With the known stream flow rates & stream temperatures
– Using material & energy balances
– The utility flows for various units
– Boiler feed water, steam, electricity
– Cooling water for reactors, boilers, compressors and condensers
6 Dr. Pradipta Chattopadhyay | BITS Pilani, Pilani Campus
Capital Cost

Capital Costs

Fixed Working

Manufacturing Non-Manufacturing Raw material inventory


• Equipment (Reactors, • Directly related to • Goods in process
Compressors process but outside • Finished product
• HE, Pumps, Tanks, etc.) but built in separate Inventory
• Based on Installed cost location • Store supplies & all
• (Delivered cost • And indirect cost: other items
+Installation not directly involved
with material and
labour of equipment
BITS – Pilani (Rajasthan)
installation
Dr. Pradipta Chattopadhyay | BITS Pilani, Pilani Campus
Profitability Estimate

Gross Profit = Gross Sales per year – Manufacturing cost

Manufacturing cost = Operating costs + Capital costs

Operating costs = Raw materials + Direct expenses + Indirect expenses

(Direct + Indirect) expenses = Utility cost + other operating expenses

Direct expenses = Labor + Supervision + Payroll + Repairs (maintenance) + Utilities

Indirect expenses = Depreciation (on machines, equipment and buildings) + Taxes


& Insurance on property + others

8 Dr. Pradipta Chattopadhyay | BITS Pilani, Pilani Campus


Net Profit

Net Profit = Gross Profit – (SARE + Income Tax)


•SARE: Acronym for Sales, Administration, Research & Engineering
(@ 10% gross profit)
•Income Tax (@ 50% gross profit)

Return on Investment (ROI)


Net Profit
Return on total F & W Capital  100
Total F & W Capital

9 Dr. Pradipta Chattopadhyay | BITS Pilani, Pilani Campus


Break-up of Total Capital
Investment & Start-up Cost

10 Dr. Pradipta Chattopadhyay | BITS Pilani, Pilani Campus


Break-up of Total Capital
Investment & Start-up Cost

11 Dr. Pradipta Chattopadhyay | BITS Pilani, Pilani Campus


Break-up of Total Capital
Investment & Start-up Cost

12 Dr. Pradipta Chattopadhyay | BITS Pilani, Pilani Campus


Gross Earning and Total
Product Cost

13 Dr. Pradipta Chattopadhyay | BITS Pilani, Pilani Campus


Estimation of Costs

• We had seen the types of costs that are included


in an economic analysis

• How to generate these cost data?

• We need to know the following


– Methods for calculating capital and operating costs
– Techniques for putting the capital and operating costs on the same
basis
– Profitability measures
– A simple model for screening process alternatives

14 Dr. Pradipta Chattopadhyay | BITS Pilani, Pilani Campus


Estimation of Operating Cost

• Simple to estimate
• Once we know the flows of the raw materials
streams and utility flows (fuel, steam, cooling
water, power)
• We simply multiply the flow by the rupee value of
that stream
• One way to keep utility costs uniform is to relate
all utility prices (electricity, various steam levels,
and cooling water costs) to an equivalent fuel
value

15 Dr. Pradipta Chattopadhyay | BITS Pilani, Pilani Campus


Estimation of Capital Cost

• We use equipment cost correlations


• Capital cost of a Heat Exchanger (HE) = f (HE
Area)
– It is not necessary to specify
• Number of tubes
• Number of baffles
• Baffle spacing
• or any other details of the design
• Cost of furnace = f (heat duty required)
• Cost of Distillation column = f (column height &
diameter)
16 Dr. Pradipta Chattopadhyay | BITS Pilani, Pilani Campus
Purchased Equipment Cost

• Extensive data is available in ‘Plant design and


economics for chemical engineers’ by Peters and
Timmerhaus
• Other correlations
– Chilton (1949), Chem. Engg. 56 (6), p 67
– Happel and Jordan (1975), Chem. Process Economics
– Guthrie (1969), Chem. Engg. 76 (6), p 114
• Update by Project ASPEN, MIT, USA

17 Dr. Pradipta Chattopadhyay | BITS Pilani, Pilani Campus


Installed Equipment Costs

• Lang, H.J. (1948), “Simplified approach to


Preliminary Cost Estimates”. Chem. Engg. 55 (6),
p 112.
• For more accurate estimates:
– Hand (1958) used different factors for different kinds of processing
equipment
Installed Equipment cost for
Distillation columns = 4 (Purchased cost)
Heat exchangers = 3.5 (Purchased cost)
Compressors = 2.5 (Purchased cost)
Fired heaters = 2 (Purchased cost)
Miscellaneous equipment = 2.5 (Purchased cost)

18 Dr. Pradipta Chattopadhyay | BITS Pilani, Pilani Campus


Guthrie’s Correlations

Purchased cost = (Base cost) (Index) (Fc)

Installed cost = (Base cost) (Index) (IF + Fc – 1)


Base cost for carbon steel
IF = installation factor
Index = correction factor for inflation
Fc = correction factor for material of construction

• Data is mostly in the form of graphs

19 Dr. Pradipta Chattopadhyay | BITS Pilani, Pilani Campus


ASPEN Correlations

• Developed by Project ASPEN at MIT, USA


• These correlations are part of a large
– Computer-aided design programs

ASPEN expression of HX is:


CE = CB FD FMC FP
Where, CE = HX cost in the 1979
CB = base cost for a carbon steel, floating head
exchanger with a 100 psig pressure
between 150-12000 ft2 of surface area
FD = design-type correlation (tube & shell passes)
FMC = material-of-construction correction factor
FP = pressure correction factor
20 Dr. Pradipta Chattopadhyay | BITS Pilani, Pilani Campus
Contd..

• The expression for base cost (CB):


– ln CB = 8.202 + 0.01506 (ln A) + 0.06811 (ln A)2
Where, A is the area of heat exchanger
• Equations for correction factors FD, FMC, and FP
are available
• Similarly, cost expressions for a variety of other
pieces of equipment are available

21 Dr. Pradipta Chattopadhyay | BITS Pilani, Pilani Campus


Updation of cost correlations

• Chilton’s correlations were published in 1949


• Guthries’ correlations were published in 1968
• ASPEN correlations are more recent
• However it takes about 3 years to build a chemical
plant and so we must be able to predict future
costs

Base cost in present year  Base cost in certain year i.e. base year 
 cost index for present year 
 
 cost index for base year 
22 Dr. Pradipta Chattopadhyay | BITS Pilani, Pilani Campus
Cost Models: Total Capital
Investment
Total Capital Investment  Fixed Capital  Working Capital  Start - up

WorkingCap ital  0.15Tot. Inv. 


Start - up  0.1Fixed Cap.

Fixed Capital  Direct Cost  Indirect Cost

DirectCost  Onsite  Offsite

Onsite  Installed Equipment Cost Offsite  0.45(Onsite )

23 Dr. Pradipta Chattopadhyay | BITS Pilani, Pilani Campus


Cost Models: Total Capital
Investment
Indirect Cost  Owner' s cost  Conting.
Owner' s cost  0.05Onsite  Offsite 
Conting.  0.20Onsite  Offsite 
Fixed Cap.  Onsite  Offsite  Owner' s Cost  Conting.
 1.25Onsite  Offsite 

Tot. Cap. Inv.  Fixed Capital  Working Capital  Start - up


 Fixed Capital  0.15Tot. Cap. Inv.   0.1Fixed Cap.

Tot. Cap. Inv.  2.36Onsite 


24 Dr. Pradipta Chattopadhyay | BITS Pilani, Pilani Campus
Cost Models: Total Product
Cost

Total Product Cost  1.03Raw Matl.  Util.   2.13Labor 


 0.103Fixed Cap.  0.025Revenue 

Fixed Cap.  1.81Onsite  Labor  105 Operators


For small process, 24hr/day, 7 days/wk

Total Product Cost  1.03Raw Matl.  Util.   0.186Onsite 


 2.13 105 Operators
 0.025Revenue 
25 Dr. Pradipta Chattopadhyay | BITS Pilani, Pilani Campus
Important References

• V. Mahajani & S. Umarji, “Joshi's Process Equipment Design”,


Macmillan Publishers India Ltd., 4th Ed., 2009.

• M.S. Peters & K.D. Timmerhaus, Plant Design and Economics for
Chemical Engineers, McGraw- Hill, 4th Edition, 1991.

• James M. Douglas, Conceptual Design of Chemical Processes,


McGraw-Hill International Edition, 1988.

4 March 2019 26

You might also like