Supervised By:
Er. Pradip Paudel
3/22/2019 2
INTRODUCTION
3/22/2019 3
SALIENT FEATURES
Type Run of river
Rated net head 66.96 m
Design discharge 27.5 m3/sec
Catchment area 510 km2
Installed capacity 14.8 MW
Percentage Exceedence Q45
Average annual generation 92.5 GWh
Foundation stone laying 17 may, 1996
Civil construction started May, 1996
Trial construction started 9 dec, 2000
Construction cost 30,000,000 USD
Financed by Govt. of Nepal, NEA & EDCF ( Korea )
-HMG/ N : NRs. 341,256,000
-NEA: NRs. 1,358,344,776
-EDCF: KW 12,399,024,230 ( US$
9,672,641)
3/22/2019 4
POWER HOUSE AND HV
SWITCHYARD OF MHP
3/22/2019 5
INTAKE
3/22/2019 6
DESETTLING BASIN
3/22/2019 7
FORBAY
3/22/2019 8
TURBINE
3/22/2019 9
Francis turbine
Two sets of 7.6 MW hydraulic turbine
Each turbine complete with governor, inlet valve, pressure oil supply system
,spiral casing, runner , guide vanes, etc.
Guided fully under electronic control.
3/22/2019 10
Turbine generator coupled system
3/22/2019 11
Governing mechanism
3/22/2019 12
Erosion in turbines
Sediment erosions in hydro turbines.
Caused due to dynamic action of sediment flowing along with water
Reduces efficiency and life hence causes economic losses
3/22/2019 13
Remedies
3/22/2019 14
Cooling system is provided for
following generating equipments:
Generators
Upper generator bearing
Lower generator guide bearing
Turbine guide bearing
Governor oil
Compressor
Turbine shaft
3/22/2019 15
Cooling system
Two types:
Open loop cooling system
Close loop cooling system
3/22/2019 16
Open loop cooling system:
3/22/2019 17
Closed Loop cooling system
Pure water and oil with separate pipes run with valves and used to cool the
equipment.
Water at closed loop system is cooled at heat exchanger with water of open loop
system.
3/22/2019 18
Generating Unit
3/22/2019 19
Excitation System
3/22/2019 20
Brushless Excitation system
3/22/2019 21
Specification of Excitation System
3/22/2019 22
Control system
Conventional manual
control with analog
control panel.
The control parameters
are controlled rotating the
control knobs
The sensors used in plant
were by-passed to prevent
frequent tripping.
3/22/2019 23
Control system
3/22/2019 24
Communication control system
3/22/2019 25
Single line diagram
3/22/2019 26
Protective scheme for switchyard of Modi
HPS
HV(132kv) SF6 CB:
3/22/2019 27
HV Switchyard(CT and PT)
-1) PT ratings:
3/22/2019 28
-2) CT ratings
3/22/2019 29
Protective relays
3/22/2019 30
Lightning Arrestor/ Disconnecting
switches
There are 3 lightning arrestors used
in
• Transmission Line feeder.
• Two sets of LA are used for two
sets of power Transformers.
Disconnecting switches
• 4 sets of EM locking type in
switchyard ,
• 2 sets for Power transformer ,1 in
feeder side of 132KV bus.
• These all disconnecting switches
are remote control as well.
3/22/2019 31
Fire protection system
3/22/2019 32
Problems in Modi Hydropower Plant
Civil Problems
Electro-mechanical Problems
3/22/2019 33
Civil Problems
3/22/2019 34
Electro-mechanical Problems
3/22/2019 35
OUR SUGGESTIONS
Maintenance of Intake should be done immediately.
Timely cleaning of trash-rack, forbay etc.
Implementation of SCADA.
Use of optical fiber for communication.