PWB - 14 Pengendalian Biaya 2
PWB - 14 Pengendalian Biaya 2
1 Cost V.5.0.
Cost July
Jan 07
09
Control Costs Estimate Costs
Determine
Budget
MONITORING &
CONTROLLING PROCESSES
PLANNING
PROCESSES
INITIATING CLOSING
PROCESSES PROCESSES
EXECUTING
PROCESSES
2 Cost V.5.0.
Cost July
Jan 07
09
Earned Value
3 Cost V.5.0.
Cost July
Jan 07
09
Earned Value Technique
4 Cost V.5.0.
Cost July
Jan 07
09
Earned Value Technique
The Measurement:
5 Cost V.5.0.
Cost July
Jan 07
09
Earned Value Technique
• Illustrative graphic
Planned Value
Actual Cost Budget at
Completion
Cumulative Value
(BAC)
Cost Variance
Schedule Variance
Earned Value
6 Cost V.5.0.
Cost July
Jan 07
09
Earned Value: Illustration
• Sample case:
• Development 5 modules: A, B, C, D, E
• Modules will be produced per period
• Cost per module = $ 10
7 Cost V.5.0.
Cost July
Jan 07
09
Earned Value: Illustration
• Sample case:
• Development 5 modules: A, B, C, D, E
• Modules will be produced per period
• Cost per module = $ 10 S Curve
E
D D
C C C
B B B B
A A A A A
Period
1 2 3 4 5
Accumulative
Cost (Sched) $ 10 $ 20 $ 30 $ 40 $ 50
8 Cost V.5.0.
Cost July
Jan 07
09
Earned Value: Illustration (1)
• Condition case 1:
• In 3 rd period: $ 40 is
expended PV
• Module completion: EV
A=100%, B= 100%, C= E AC E
100%, D=100%, E=50%
D D D
C C C
B B B B
A A A A A
Period
Accumulative
1 2 3 4 5
Cost (Sched) $ 10 $ 20 $ 30 $ 40 $ 50 PV
Cost (Act) $ 10 $ 20 $ 40 AC
Value EV
(performed) $ 10 $ 20 $ 45
9 Cost V.5.0.
Cost July
Jan 07
09
Earned Value: Illustration (2)
1 2 3 4 5
Accumulative
$ 10 $ 20 $ 30 $ 40 $ 50 PV
Cost (Sched)
Cost (Act) $ 10 $ 20 $ 40 AC
Value EV
$ 10 $ 20 $ 45
(performed)
The Measurement:
Cost Variance (CV) = EV - AC = $45 - $40 = $5
(+) = under budget
Schedule Variance (SV) = EV - PV = $45 - $30 = $15
(+) = ahead schedule
Cost Performance Index (CPI) = EV/AC = $45 / $40 = 1.125
>1 performance of cost OK
Getting Rp xx out of every Rp 1
Schedule Performance Index (SPI): EV/PV = $45 / $30 = 1.5
>1 performance of schedule OK
Progressing at x% of the rate originally plan
10 Cost V.5.0.
Cost July
Jan 07
09
Earned Value: Illustration (3)
• Condition case 2:
• In 3 rd period: $ 30 is PV
expended
• Module completion: E
A=100%, B= 100%, C= AC
50%, D=0%, E=0% D D
C EV C C
B B B B
A A A A A
Period
1 2 3 4 5
Accumulative
Cost (Sched) $ 10 $ 20 $ 30 $ 40 $ 50 PV
Cost (Act) $ 10 $ 20 $ 30 AC
Value EV
(performed) $ 10 $ 20 $ 25
11 Cost V.5.0.
Cost July
Jan 07
09
Earned Value: Illustration (3)
1 2 3 4 5
Accumulative
$ 10 $ 20 $ 30 $ 40 $ 50 PV
Cost (Sched)
Cost (Act) $ 10 $ 20 $ 30 AC
Value EV
$ 10 $ 20 $ 25
(performed)
The Measurement:
Cost Variance (CV) = EV - AC = $25 - $30 = - $5
(-) = over budget
Schedule Variance (SV) = EV - PV = $25 - $30 = - $5
(-) = under schedule
Cost Performance Index (CPI) = EV/AC = $25 / $30 = 0.833
<1 performance of cost NOT OK
Getting Rp xx out of every Rp 1
Schedule Performance Index (SPI): EV/PV = $25 / $30 = 0.833
<1 performance of schedule NOT OK
Progressing at x% of the rate originally plan
12 Cost V.5.0.
Cost July
Jan 07
09
Estimate At Completion (EAC)
• Condition case 2:
Alternative 1 :
EAC = Actual + Remaining Budget = AC + (BAC – EV)
Used when current variances are thought not typical of the future
Sample: = 30 + (50 - 25) = $55
Alternative 2 :
EAC = Actual + New Estimate for Remaining Budget = AC + ETC
Used when original estimate was fundamentally flawed
Sample: = 30 + xxest = $xx
Alternative 3 :
EAC = Actual + Remaining Budget/CPI = AC + ( [BAC–EV] / CPI )
Used when current variances are thought to be typical of the future
Sample: = 30 + ( [50 - 25] / 0.625 ) = $70
13 Cost V.5.0.
Cost July
Jan 07
09
Estimate At Completion (EAC)
• Condition case 2:
Alternative 4 :
EAC = Actual + Remaining/CPI/SPI =
= 30 + (20/0.625):0.833
= 30 + 38.42 = $68.42
Alternative 5:
EAC = BAC / CPI = 50 / 0.625 = $80
Used when if no variances from the BAC have occurred or will
continue at the same rate of spending