06-3-Assembly Line Balancing

You might also like

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 37

Dr.

Ron Lembke

ASSEMBLY LINE BALANCING


ASSEMBLY-LINE BALANCING

 Situation: Assembly-line production.


 Many tasks must be performed, and the
sequence is flexible
 Parts at each station same time

 Tasks take different amounts of time

 How to give everyone enough, but not too much


work for the limited time.
PRODUCT-ORIENTED LAYOUT

Operations

Belt Conveyor
PRECEDENCE DIAGRAM
Draw precedence graph
(times in minutes)

B
A 5 G
20
15
E I J
8
C D 12 7
H
5 10 F 12
3
LEGAL ARRANGEMENTS

A B
5 G
20 15
E I J
C D 8
12 7
H
5 10 F 12
3

 Ok: AC|BD|EG|FH|IJ
 ABG|CDE|FHI|J C|ADB|FG|EHI|J
 NOT ok: BAG|DCH|EFJ|I
 DAC|HFE|GBJ|I
LEGAL ARRANGEMENTS
A B CT = maximum of workstation times
5 G
20 15
E I J
C D 8
12 7
H
5 10 F 12
3

 AC|BD|EG|FH|IJ = max(25,15,23,15,19) = 25
 ABG|CDE|FHI|J = max(40,23,27,7) = 40
 C|ADB|FG|EHI|J = max(5,35,18,32,7) = 35

AC BD EG FH IJ
CYCLE TIME
 The more units you want to produce per hour, the less time a
part can spend at each station.
 Cycle time = time spent at each spot

Production Time in each day


C=
Required output per day (in units)
 C = 800 min / 32 = 25 min
 800 min = 13:20
NUMBER OF WORKSTATIONS

 Given required cycle time, find out the


theoretical minimum number of stations
Sum of task times (T)
Nt =
Cycle Time (C)
 Nt = 97 / 25 = 3.88 = 4 (must round up)
ASSIGNMENTS

Assign tasks by choosing tasks:


 withlargest number of following tasks
 OR by longest time to complete

Break ties by using the other rule


NUMBER OF FOLLOWING TASKS

Nodes # after
Choose C first, then, if possible,
C 6 add D to it, then A, if possible.
D 5
A 4
B,E,F 3
G,H 2 A B G
5
20
I 1 E 15
I J
C D 8
H 12 7
5 10 F 12
3
PRECEDENCE DIAGRAM
Draw precedence graph
(times in seconds)

B
A 5 G
20
15
E I J
8
C D 12 7
H
5 10 F 12
3
NUMBER OF FOLLOWING TASKS
Nodes # after A could not be added to first
station, so a new station must be
A 4 created with A.
B,E,F 3 B, E, F all have 3 stations after,
G,H 2 so use tiebreaker rule: time.
I 1 B=5
E=8
F=3
Use E, then B, then F.
A B
5 G
20 15
E I J
C D 8 7
H 12
5 10 F 12
3
PRECEDENCE DIAGRAM
E cannot be added to A, but E can be added
to C&D.

B
A 5 G
20
15
E I J
8
C D 12 7
H
5 10 F 12
3
PRECEDENCE DIAGRAM

Next priority B can be added to A.

B
A 5 G
20
15
E I J
8
C D 12 7
H
5 10 F 12
3
PRECEDENCE DIAGRAM
Next priority B can be added to A.
Next priority F can’t be added to either.

B
A 5 G
20
15
E I J
8
C D 12 7
H
5 10 F 12
3
NUMBER OF FOLLOWING TASKS
Nodes # after
G,H 2 G and H tie on number coming after.
G takes 15, H is 12, so G goes first.
I 1
PRECEDENCE DIAGRAM
G can be added to F.
H cannot be added.

B
A 5 G
20
15
E I J
8
C D 12 7
H
5 10 F 12
3
PRECEDENCE DIAGRAM
I is next, and can be added to H, but J
cannot be added also.

B
A 5 G
20
15
E I J
8
C D 12 7
H
5 10 F 12
3
PRECEDENCE REQUIREMENTS

A B
5 G
20
15
E I J
C D 8
12 7
H
5 10 F 12
3
Why not put J with F&G?
AB CDE HI

FG J
CALCULATE EFFICIENCY
 We know that at least 4 workstations will be
needed. We needed 5.
Sum of task times (T)
Efficiencyt =
Actual # WS * Cycle Time

 = 97 / ( 5 * 25 ) = 0.776
 We are paying for 125 minutes of work, where it
only takes 97.
LONGEST FIRST
Try choosing longest activities first.
A is first, then G, which can’t be added to A.

B
A 5 G
20
15
E I J
8
C D 12 7
H
5 10 F 12
3
LONGEST FIRST
H and I both take 12, but H has more
coming after it, then add I.

B
A 5 G
20
15
E I J
8
C D 12 7
H
5 10 F 12
3
LONGEST FIRST
D is next. We could combine it with G, which we’ll do later. E is next, so
for now combine D&E, but we could have combined E&G. We’ll also
try that later.

B
A 5 G
20
15
E I J
8
C D 12 7
H
5 10 F 12
3
LONGEST FIRST

J is next, all alone, followed by C and B.

B
A 5 G
20
15
E I J
8
C D 12 7
H
5 10 F 12
3
LONGEST FIRST

F is last. We end up with 5 workstations.

A B
5 G
20
15
E I J
C D 8
12 7
H
5 10 F 12
3
CT = 25, so efficiency is again
Eff = 97/(5*25) = 0.776
LONGEST FIRST- COMBINE E&G
Go back and try combining G and E instead
of D and E.

B
A 5 G
20
15
E I J
8
C D 12 7
H
5 10 F 12
3
LONGEST FIRST- COMBINE E&G
J is next, all alone. C is added to D, and B is
added to A.

B
A 5 G
20
15
E I J
8
C D 12 7
H
5 10 F 12
3
LONGEST FIRST- COMBINE E&G

F can be added to C&D. Five WS again. CT is


again 25, so efficiency is again 0.776

B
A 5 G
20
15
E I J
8
C D 12 7
H
5 10 F 12
3
LONGEST FIRST - COMBINE D&G
Back up and combine D&G. No precedence violation.

B
A 5 G
20
15
E I J
8
C D 12 7
H
5 10 F 12
3
LONGEST FIRST - COMBINE D&G
Unhook H&I so J isn’t stranded again, I&J is 19, that’s better than
7. E&H get us to 20. This is feeling better, maybe?

B
A 5 G
20
15
E I J
8
C D 12 7
H
5 10 F 12
3
LONGEST FIRST - COMBINE D&G
5 Again! CT is again 25, so efficiency is again 97/(5*25) = 0.776

B
A 5 G
20
15
E I J
8
C D 12 7
H
5 10 F 12
3
CAN WE DO BETTER?

B
A 5 G
20
15
E I J
8
C D 12 7
H
5 10 F 12
3
CAN WE DO BETTER?
If we have to use 5 stations, we can get a
solution with CT = 20.

B
A 5 G
20
15
E I J
8
C D 12 7
H
5 10 F 12
3
CALCULATE EFFICIENCY
 With 5 WS at CT = 20
Sum of task times (T)
Efficiencyt =
Actual # WS * Cycle Time

 = 97 / ( 5 * 20 ) = 0.97
 We are paying for 100 minutes of work, where
it only takes 97.
OUTPUT AND LABOR COSTS
 With 20 min CT, and 800 minute workday
 Output = 800 min / 20 min/unit = 40 units
 Don’t need to work 800 min
 Goal 32 units: 32 * 20 = 640 min/day
 5 workers * 640 min = 3,200 labor min.
 We were trying to achieve
 4 stations * 800 min = 3,200 labor min.
 Same labor cost, but more workers on shorter
workday
HANDLING LONG TASKS

 Long tasks make it hard to get efficient


combinations.
 Consider splitting tasks, if physically possible.

 If not:
 Parallel workstations
 use skilled (faster) worker to speed up
SUMMARY
 Compute desired cycle time, based on Market
Demand, and total time of work needed
 Methods to use:
 Largest
first, most following steps, trial and error
 Compute efficiency of solutions

 A shorter CT can sometimes lead to greater


efficiencies
 Changing CT affected length of work day, looked at
labor costs

You might also like