CP101: Breakdown of S-Curve As of 25 Oct 2017: No. Work Item Weight (%) Plan (%) Actual (%) Deviation (%) Note
CP101: Breakdown of S-Curve As of 25 Oct 2017: No. Work Item Weight (%) Plan (%) Actual (%) Deviation (%) Note
1
Plan: Actual Assumption
CP101: Breakdown of S-Curve as of 25 Oct 2017
Others 2.33 0.36 0.24 -0.12 Delayed due to unfinished STR and ARC work
3
Plan: Actual Assumption
CP102: Breakdown of S-Curve as of 25 Oct 2017
Weight Plan Actual Deviation
No. Work Item Note
(%) (%) (%) (%)
FTM st 0.13 0.00 0.00 0.00
11 Signage & Graphics
CPR st 0.12 0.00 0.00 0.00
12 Testing & Commissioning 0.18 0.00 0.00 0.00
13 Product Support 0.03 0.00 0.00 0.00
Provisional Sum 0.71 0.00 0.00 0.00
Provisional Sum for day work 0.54 0.00 0.00 0.00
Total: 100.00 78.10 78.03 -0.07
4
Plan: Actual Assumption
CP103: Breakdown of S-Curve as of 25 Oct 2017
5
Plan: Actual Assumption
CP103: Breakdown of S-Curve as of 25 Oct 2017
Weight Plan Actual Deviation
No. Work Item Note
(%) (%) (%) (%)
HJN st 0.41 0.23 0.16 -0.07
7
Plan: Actual Assumption
CP104: Breakdown of S-Curve as of 25 Oct 2017
Weight Plan Actual Deviation
No. Work Item (%) (%) (%) (%)
Note
4 Bored Tunnels including First Pour Concrete 15.69 15.69 15.69 0.00
5 Stations
Water Supply. Plumbing SNY st 0.79 0.72 0.66 -0.06 Delay in IST st.: Delay will be catch-up by E/NOV 2017
7
and Drainage IST st 0.82 0.63 0.63 0.00
3 Bored Tunnels including First Pour Concrete 19.21 19.21 19.21 0.00
BNH st 1.12 0.69 0.57 -0.12 Delay in BNH st. and STB st.: Delay will be catch-up by
7 Fire Services
STB st 1.00 0.91 0.88 -0.03 E/NOV 2017
4 Stations
13
Plan: Actual Assumption