Professional Documents
Culture Documents
Layout Strategies
Layout Strategies
Layout Strategies
Lecture 7
Process-Oriented Layout
Laboratories
Figure 9.3
M M D D D D
L L
G G G P
L L
G G G P
L L
Grinding Painting Department
Department
L L
Receiving and A A A
Shipping Assembly
Process-Oriented Layout
Arrange work centers so as to minimize
the costs of material handling
Basic cost elements are
Number of loads (or people) moving
between centers
Distance loads (or people) move
between centers
40’
Painting (2) 30 50 10 0
Receiving (4) 50 0
Shipping (5) 0
Testing (6)
Figure 9.4
© 2011 Pearson Education, Inc. publishing as
Prentice Hall
Current Interdepartmental Flow
Graph
100
10
100
Figure 9.6
© 2011 Pearson Education, Inc. publishing as
Prentice Hall
The Cost of Material Handling
n n
Minimize cost = ∑ ∑ Xij Cij
i=1 j=1
= $570
40’
50 100
Figure 9.7
© 2011 Pearson Education, Inc. publishing as
Prentice Hall
The Cost of Material Handling:
Improved Layout
n n
Cost = ∑ ∑ Xij Cij
i=1 j=1
= $480
Assembly
4 6 7 9
5 8
2 10 12
1 3 11
A B C Raw materials
Part Routing Matrix
Machines
Parts 1 2 3 4 5 6 7 8 9 10 11 12
A x x x x x
B x x x x
C x x x
D x x x x x
E x x x
F x x x
G x x x x
H x x x
Figure 5.8
Reordered Routing Matrix
Revised Cellular Layout
Assembly
8 10 9 12
11
4 Cell 1 Cell 2 6 Cell 3
7
2 1 3 5
A B C
Raw materials
Advantages of Work Cells
1. Reduced work-in-process inventory
2. Less floor space required
3. Reduced direct labor, and setup cost
4. More employee participation
5. Increased use of equipment and machinery
2. Determine the
number of operators
required
Total operation time required
Workers required = Takt time
20
10
0
Assemble Paint Test Label Pack for
shipment
© 2011 Pearson Education, Inc. publishing as Operations
Prentice Hall
Staffing Work Cells Example
600 Mirrors per day required
Mirror production scheduled for 8 hours per day
From a work balance chart total operation time
= 140 seconds
= 140 / 48 = 2.91
© 2011 Pearson Education, Inc. publishing as
Prentice Hall
Repetitive and Product-Oriented
Layout
Organized around products or families of
similar high-volume, low-variety products
Raw
Station Station Station Station Finished
materials item
1 2 3 4
or customer
In 1 2 3 4
5
Workers
6
Out
10 9 8 7
McDonald’s Assembly Line
Both types of lines must be balanced so that the time to perform the work at
each station is the same
© 2011 Pearson Education, Inc. publishing as
Prentice Hall
Product-Oriented Layouts
Advantages
1. Low variable cost per unit
2. Low material handling costs
3. Reduced work-in-process inventories
4. Easier training and supervision
5. Rapid throughput
Disadvantages
1. High production volume is required to be justifiable
2. Work stoppage at any point ties up the whole operation
3. Lack of flexibility in product or production rates
6-36
Cycle Time
• The maximum time allowed at each workstation to complete its set of tasks on
a unit
• Cycle time also establishes the output rate of a line
6-37
How Many Workstations are Needed?
• The required number of workstations is a function of
• Desired output rate
• Our ability to combine tasks into a workstation
• Theoretical minimum number of stations
N min
t
Cycle time
where
N min theoretica l minimum number of stations
t Sum of task time s
Measuring Effectiveness
• Balance delay (percentage of idle time)
• Percentage of idle time of a line
Idle time per cycle
Balance Delay 100
N actual Largest WS time
where
N actual Actual number of stations
• Efficiency
• Percentage of busy time of a line
Efficiency 100% - Balance Delay
Measuring Effectiveness
• Efficiency
0.1 min. 0.7 min. 1.0 min. 0.5 min. 0.2 min.
0.1 min. 0.7 min. 1.0 min. 0.5 min. 0.2 min.
0.1 min. 0.7 min. 1.0 min. 0.5 min. 0.2 min.
CT = cycle time
Example: 8 hours per day
OT = 8 x 60 = 480 minutes per day
Cycle Time = CT = 1.0 min
Maximum Output = OT/CT = 480/1.0 = 480
units per day
Cycle Time = CT = 2.5 min
Minimum Output = OT/CT = 480/2.5 = 192
units per day
Cycle Time Determined by Desired Output
OT
CT = cycle time =
D
D = Desired output rate
t
Nmin =
CT
t = sum of task times
Nmin = theoretical Minimum Number of
Workstations Required
Performance
Time Immediate
Task (minutes) Predecessors
A 10 —
B 11 A This means that
C 5 B tasks B and E
cannot be done
D 4 B until task A has
E 12 A been completed
F 3 C, D
G 7 F
H 11 E
I 3 G, H
Total time 66 min.
G 7 F 10 11
C
3 7
H 11 E
A B F G
I 3 G, H 4
3
Total time 66 12
D
11 I
E H