Professional Documents
Culture Documents
Loss Prevention in Chemical Industries Involve
Loss Prevention in Chemical Industries Involve
– Safety indexes
– Safety audit
What is HAZOP?
• Systematic technique to IDENTIFY potential HAZard
and OPerating problems
• Normal operation
3
HAZOP Team
HAZOP studies are carried out using a `brainstorming' approach
by a team, chaired and coordinated by a qualified person
experienced in HAZOPs:
• Team Leader
• Team Secretary
• Process Engineer
• Mechanical Engineer
• Commissioning/Operations
• Engineer/Manager
• Instrument Engineer
Strength of HAZOP
5
Weakness of HAZOP
6
Guide Words
NONE /No e.g., NO FLOW caused by blockage; pump failure;
valve closed or jammed :
REVERSE Opposite, e.g., REVERSE FLOW caused by pump
failure
MORE Quantitative increase, e.g., MORE FLOW, Temp,
10
Storage Tank
To
atmosphere
Nitrogen To flare
H
RV-1
Equipment & Valve
PV-2 PICA FV Flow control valve
PV-1
T Tank
V-8
P Pump
V-7 PV Pressure control valve
RV Relief valve
V Valve
V-5
H
TIA
From tank
trucks Storage
Instrument
Tank LIA
H
L Level
L T Temperature
V-1 P Pressure
F Flow
I Indicator
V-2 FICA
PI C Controller
L
To process A Alarm
V-4 FV-1
V-3
HAZOP Table - level
Cause Deviation Consequences Safe guard Action
Level
Less 1. Rupture Reagent release Potential fire LIA Estimate release quantity
discharge line
2. V3 open or Reagent release Potential fire LIA Estimate release quantity
broken
3. V1 open or Reagent release Potential fire LIA V1 protection
broken
4. Tank rupture Reagent release Potential fire LIA What external event
cause tank rupture
More 5. Too much truck Overfill Reagent release via LIA Does RV1 allow for
unload RV1 liquid release?
Consider high level alarm
shutoff
6. Reverse flow Overfill Reagent release via LIA Consider check valve at
from process RV1 pump discharge
Consider high level alarm
shutoff at feed
NO Same as less
HAZOP Table - pressure
Pressure
Less 9. Break in nitrogen Reagent release Potential fire PICA Consider independent
or flare line PLA
10. Lose nitrogen Tank implode Reagent release PICA Consider vacuum break
valve
11. PV2 fails closed Tank implodes Reagent release PICA Consider PAL
12. PICA fails, Tank implodes Reagent release Tank not designed for
closing PV2 vacuum
More 13. PICA fails, Reagent release via Tank rupture if RV1 PICA What PV1 and RV1
closing PV1 RV1 fails capacity
14. PV1 fails closed Reagent release via Tank rupture if RV1 PICA Consider independent
RV1 fails PAH
15. V7 closed Reagent release via Tank rupture if RV1 PICA Is V7 locked open
RV1 fails
16. Overfill tank Truck unload Tank rupture if RV1 PICA Consider second high
fails level shutoff
17. Temperature of Reagent release in Tank rupture if RV1 PICA What prevent high temp
inlet higher RV1 fails of feed
than normal Consider PAH
18. Volatile Reagent release in Tank rupture if RV1 PICA Consider PAH
impurities in RV1 fails Consider sampling before
feed unloading
Hazop Table - composition
Cause Deviation Consequences Safe guard Action
Composition
Other than 7. Wrong reagent Possible reaction Tank rupture Consider sampling before
unload
Less 19. Temperature of Possible vacuum Thermal stress on tank What are temp limits of
inlet cooler tank
than usual
20. Low tank See 9-12 Thermal stress on tank What are pressure limits
pressure of tank
High 21. temperature of See 17 Thermal stress on tank What are temp limits on
inlet is higher tank
than usual
22. external fire Tank fails Reagent release What could cause
external fire
What are fire protection
capabilities
Is fire protection
adequate
Preliminary HAZOP Example
Cooling Coils
Monomer
Feed Refer to reactor system shown.
16
Preliminary HAZOP on Reactor
Guide Word Deviation Causes Consequences Action
REVERSE Reverse cooling Failure of water source Less cooling, possible runaway Install check valve
flow resulting in backward reaction
flow
MORE More cooling flow Control valve failure, Too much cooling, reactor cool Instruct operators
operator fails to take action on procedures
on alarm
AS WELL AS Reactor product More pressure in reactor Off-spec product Check maintenance
in coils procedures and
schedules
OTHER THAN Another material Water source May be cooling inefffective If less cooling, TAH will
besides cooling contaminated and effect on the reaction detect. If detected, isolate
water water source. Back up
water source?
17
Case Study – Shell & Tube Heat
Exchanger
• Using relevant guide works, perform HAZOP study on shell & tube
heat exchanger
Process
fluid
Cooling water
18
HAZOP on Heat Exchanger
Guide Word Deviation Causes Consequences Action
NONE No cooling water flow Failure of inlet cooling Process fluid temperature is Install Temperature
water valve to open not lowered accordingly indicator before and after
the process fluid line
Install TAH
MORE More cooling water Failure of inlet cooling Output of Process fluid Install Temperature
flow water valve to close temperature too low indicator before and after
process fluid line
Install TAL
LESS Less cooling water Pipe leakage Process fluid temperature too Installation of flow meter
low
REVERSE Reverse process fluid Failure of process fluid inlet Product off set Install check valve (whether
flow valve it is crucial have to check?)
CONTAMINATION Process fluid Contamination in cooling Outlet temperature too low Proper maintenance and
contamination water operator alert
19
Documents needed for HAZOP Study
HAZOP leader
• Plan sessions and timetable
• Control discussion
• Limit discussion
• Encourage team to draw conclusion
• Ensure secretary has time for taking note
• Keep team in focus
• Encourage imagination of team members
• Motivate members
• Discourage recriminations
• Judge importance issues
Responsibility of HAZOP Team
Members
HAZOP Secretary
• Take adequate notes
• Record documentations
• Inform leader if more time required in taking notes
• If unclear, check wording before writing
• Produce interim lists of recommendations
• Produce draft report of study
• Check progress of chase action
• Produce final report
Responsibility of HAZOP Team
Members
Process Engineer
• Provide a simple description
• Provide design intention for each process unit
• Provide information on process conditions and design
conditions
• Provide a simple description
• Provide design intention for each process unit
• Provide information on process conditions and design
conditions
Responsibility of HAZOP Team
Members
Chemist
• Provide details of process chemistry
• Provide details of process hazards (polymerisations,
byproducts, corrosion etc)
Project Engineer
• Provide details of cost and time estimation and also
budget constraints.
• Ensure rapid approval if required