By:Jane

By: Jane Claries


Claries Alcoriza Alcoriza
 is defined as pre-Commissioning activity
which is initiated after installation of
instruments in the field and carry out the
instrument loop checks between installed
field instrument and respective control
system i.e. PLC or DCS.
Console
Engineer

Field
Technician
 To ensure that the system works
normally without any trouble or
malfunctions and correcting the
deficiencies before commissioning.
 Before carrying out the loop test or the
sequence test, all related instruments must
be calibrated.
 When performing tests, two groups will be
required, one in the field and other in the
control room.
 When a particular loop ties into DCS/PLC
system, a technician may be required in the
rack room for troubleshooting.