L&T Heavy Engineering

Manufacturing & Machining Facility


at Badlapur Production Centre (BPC)

Location – John Galt International, MIDC, Badlapur


Facility F2 – Manufacturing (PC3)
Facility B21 – Machining (PC4)

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved 1 of 45
L&T Heavy Engineering
Facilities at John Galt-MIDC, Badlapur

Plot B21 (M/c Shop)


Plot Size: 2400 m2
Covered Area: 2100 m2

Plot B6 (Warehouse,
CMF & M/c)
Plot Size: 4400 m2
Covered Area: 3000 m2

Plot F2 (Fabrication Shop)


Plot Size: 25000 m2
Covered Area: 9900 m2

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved 2
L&T Heavy Engineering

John Galt, Badlapur –Facilities


Plot F2 • Area under shed 9900 m2 + Open Area
~10000 m2 (usable) + 5 Buildings ~ 5100 m2
(Total Area
25000 m2) • Allocated for Main Fabrication Shop

Plot B21 • Area under shed ~2100 m2


(Total Area- • Allocated for Machine shop
2400 m2)

• Area under shed ~3000 m2 + Open Area ~ 1100m2


Plot B6 + Building ~ 300 m2
(Total Area • One Bay (1500 m2) + Open Area Allocated for store
4400 m2) • One Bay (1500 m2) for CMF & m/c.

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved 3
L&T Heavy Engineering

Plot “F2” – Manufacturing Shop

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
4
L&T Heavy Engineering
Facility at Plot “F2”- Manufacturing Shop

Total Area
Covered POWER
Bay 1 Bay 2 Bay 3 (Open &
Area - m2 Connection
Covered)
BAY
158 L x 21 W 158 L x 23 W 142 L x 21 W 9900 25000 m2 200 KVA existing+
SIZE
New 500 KVA.
25T – 2 nos DG Back-up Exist.
CRANES 10 T - 3 nos 10T – 3 nos 125 KVA+ Addnl.
10 T – 1 no.
315 KVA
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
5
L&T Heavy Engineering
Facility at Plot “F2”- Manufacturing Shop

14.0 m
12.5 m
(Under
Hook Ht)

Bay 2L Bay 3L
Bay 1L 11 m
9.50 m (Under
Hook Ht)
Bay 1 Bay 2 Bay 3

Floor at two levels 21 m 23.5 m


21 m

Bay 1 / 1L Bay 2 / 2L Bay 3 / 3L


BAY SIZE
162 L x 21 W 162 L x 23.5 W 140 L x 21 W
CRANE S 10 T - 3 nos. 25T – 2 nos., 10T-1 no 10T – 3 nos.
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
6
L&T Heavy Engineering
Plot “F2” – Manufacturing Shop

F2 - Plant Layout wrt


Flow is Finalized.

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
7
L&T Heavy Engineering

F2 Plant Status NDE Block


 NDE Block Ready (RT/UT processing, TPI room, Dark Room) Civil,
Electrical, furnishing completed.

NDE BLOCK

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
8
L&T Heavy Engineering
F2 Plant Status RT Enclosure
 RT Enclosure - Civil, Electrical work Completed.
 BARC Authorities inspection completed on 22 Mar’13.

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
9
L&T Heavy Engineering
F2 Plant Status
Welding Consumable Store, Hot Room
Welding Consumable Stores, Hot room Ready.

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
10
L&T Heavy Engineering
F2 Plant Status Main Stores, Excise Office
Main Stores, Excise room work completed.
Toilet commissioning in progress.

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
11
L&T Heavy Engineering
F2 Plant Status Water Storage Facility
Underground Water Storage Tank (2.6 Lac Liter) completed.

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
12
L&T Heavy Engineering
F2 Plant Status Concreting of Lower Bays
 Bay 1 (Lower) flooring in progress.

Levelling with soil completed,


Laying of rubble in progress

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
13
L&T Heavy Engineering
F2 Plant Status F2 - Plant Office
 Civil work of Plant office (Admin Block) completed
 Electrical, Furnishing work completed.
 Compound Wall, Entry Gate to Office renovation completed.
 Painting completed & finishing will be completed by 30 Apr’13.

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
14
L&T Heavy Engineering
F2 Plant Status F2 - Plant Office
 Garden at the entrance of Plant office (Admin Block).

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
15
L&T Heavy Engineering
F2 Plant Status Electrical, LAN, Telephone Cabling
 Server Room, EPABX for Telephone lines commissioned.
 Installation of Hume Pipes for Electrical/LAN, BSNL Cable completed.
construction of drainage in progress.

Drainage construction completed, grid covering balance

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
16
L&T Heavy Engineering
F2 Plant Status Development of outside area
 Surrounding Plot Survey done.
 Landscape/leveling/roads finalized by Structural Consultant.

Levelling completed, Road construction in progress


Levelling of
plate yard

Retaining wall constr.


26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
L&T Heavy Engineering
F2 Plant Status Development of Facilities
 Plant, Crane Support Structure, Building inspection done by L&T
Structural Consultant.
 L&T Safety Audit Points are being implemented.
 Access road leveling for trailer movement/ entry into shops/exit
from F2 examined by L&T Logistics, Transporters.
 Workmen Cloak rooms Layout finalized, 80 Lockers received.
 Canteen/Dining Area Allocated.
 Overhead Water Tanks for Drinking/Sanitation(37,000 Liters)
already commissioned.
 Underground drinking/sanitation water piping work in progress.

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
18
L&T Heavy Engineering
F2 Plant Status Development of Facilities
 Canteen / Dining Area for workers.

Tables
arranged

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
19
L&T Heavy Engineering
F2 Plant Status Development of Facilities
Slab laying completed

Toilets for
Workmen in
progress

Primer coating for


security cabin and
initial plastering
completed for
Temple.

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
20
L&T Heavy Engineering
F2 Plant Status LAN Connectivity with Powai
 LAN Tower from Bharti Airtel installed, RF Commissioned.
 Connectivity with Powai Server already established.
 Connectivity between 3 locations i,e,F21, B21, B6 established.

18 m Tall Mast over F2


Building Terrace

Interconnecting
Tower F2, B21, B6

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
21
L&T Heavy Engineering
F2 Plant Status Planning of WTC/First Aid Facility
 Old existing structure demolished, Plan for WTC/First Aid/ Training
room /Cylinder Storage finalized and digging for column is i/p.
 Exploring CNG Piping inside F2 to eliminate Gas Cylinders.

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
22
L&T Heavy Engineering
F2 Plant Status Readiness for Manufacturing
 Bay- 1, 2 & 3 - Upper areas vacated and cleaned.
 CMF piping work from R&C-Shop2 shifted to Bay-2, Upper area
 Bay-3, Lower earmarked for Nuclear jobs. Planning the partitioning of
the Bay-3 Lower side.

Bay 1 - Upper Bay 2 - Upper Bay 3 - Upper

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
23
L&T Heavy Engineering
F2 Plant Status Construction -Electrical Sub-Station
 MSEB Permission for increased Power received / DG set ordering
completed.
 Civil work for Electrical Sub-Station in Progress.
 Full Power 200+500 KVA; DG set 125+315 KVA by 30 May’13.
New DG installed

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
24
L&T Heavy Engineering
F2 Plant Status Readiness Milestones
Sr.
Action Plan (phase - 1) Target Dates Current Status
No.
1 JGI to get Bay-2 vacated and release three buildings. 15-Jan-2013 Completed
2 JGI to get open Area and one buildings. 28-Feb-2013 Completed
NDE Block/Dark Room, Welding Consumable
3 stores/Hot Room, Cleaning , Lighting in shop top side 28-Feb-2013 Completed
Bay - 2 for ASME Audit.
RT Enclosure (Civil, Electrical) work completed.
4 15-Mar-2013 Completed
BARC Audit completed on 22 Mar’13 Satisfactorily.
5 Enhance Power Supply 500KVA, DG Set 315 KVA 15-Mar-2013 Sanction Recd
LAN connection & Movement of contractors,
6 Machines, Tools, Tackles and Start component 15-Mar-2013 Completed
manufacturing of “Non-AI /IBR “ jobs
JGI to get Bay-3 Upper & Lower vacated. Fencing /
7 15-Apr-2013 In progress
Painting / Lighting of Buildings/shops as required.
Planning
8 Cloak Rooms, Toilet, Leveling of Open Area, roads 15-May-2013
completed
9 ASME Audit of the Facility, Start ASME jobs 10-June-2013
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
25
L&T Heavy Engineering
F2 Plant Status Major Infrastructure Enhancement
Sr. Current
Action Plan (Phase -2) Target Dates
No. Status
1 Concreting of Shop Floor –Bay -2 - Lower side 30 Mar 2013 completed
Installation of New Power connection- 500 KVA &
30 May 2013 Started
2 DG Set – 315 KVA
Levelling of land, concreting of rail area for Gantry
3 Installation of Gantry Crane, Shot Blasting & 30 Jun 2013 in progress
painting Shed - 8 W x 8 H x 20 L
4 Installation of Gantry Crane 30 Sept 2013 Planned
Sr. Current
Action Plan (Phase – 3) Target Dates
No. Status
1 Concreting of Shop Floor - lower Bay 1 30 Apr 2013 In Progress
2 Levelling of Open Area - remaining 30 May 2013 In Progress

3 Approach Road & Surrounding Lighting 8 June 2013 In Progress


4 25 T Cranes - 2 nos. & Inter bay transfer Trolley 30 Sept 2013 Planned

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
26
L&T Heavy Engineering

Facility at Plot “B21” – Machining Shop

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
27
L&T Heavy Engineering
Facility at Plot “B21”Machining Shop

Covered Total Area


Bay 1 Bay 2 Power Connection
BAY Area (Open & Covered)
SIZE 58 L x 18 W 58 L x 18 W 2100 m2 2400 m2 200 KVA500KVA
with DG Back-up
CRANES 10 T - 2 Nos 10T – 2 Nos 125KVA315 KVA
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
28
L&T Heavy Engineering
B21 Plant Status Facility at Plot “B-21” – Machine Shop

B21 - Plant Layout wrt


Flow is Finalized.
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
29
L&T Heavy Engineering
B21 Plant Status Foundation laying for Machines
Bay-1, Pit for foundation of DHD,VTL & CNC-VTL completed.
Shop Fencing Wall Constructed. HMC commissioning in progress

HMC Commissioning 5-axis Foundation

Bay - 1 Boundary Wall

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved 30
L&T Heavy Engineering
B21 Plant Status Installation of Drilling Machines
 Installation of 3 radial drilling M/cs in Bay-2 in progress.
 HMC, VTL, Lathe M/c’s planned to be shifting completed,
commissioning in progress.
Tiles polishing in progress

Radial Drilling Partition

Lathe Machine
Foundation in progress

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved 31
L&T Heavy Engineering
B21 Plant Status Power Upgradation
 Power Sanction 200 to 500 KVA obtained. DG 300 KVA installed.

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved 32
L&T Heavy Engineering
B21 Plant Status

Gangway marking

Front Roof

Tool Storage
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved 33
L&T Heavy Engineering
B21 Plant Status Vacating/Cleaning of Bay - 2
 Civil work of Main office, Partition wall and Toilets in progress.

Main Office painting work Toilet for staff


in progress

Partition wall between 2 bays


construction in progress
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved 34
L&T Heavy Engineering
B21 Plant Status Readiness Milestones
Sr. Target Current
Action Plan
No. Dates Status
1 JGI to get Bay-1 vacated from existing contractor 15-Dec-2012 Completed
2 Readiness of Foundation of DHD 20-Feb-2013 Completed
3 Foundation work for CNC-VTL, VTL 30-Mar-2013 Completed
4 JGI to get Bay-2 vacated from existing contractor 15-Apr-2013 Completed
5 Drilling Machines (6 out of 15) in operation 30-Apr-2013 Completed
Up-gradation of Power 200 to 500KVA; DG-125 to 300 KVA
6 Electrical connections / painting / lighting / air ventilators / 30-Apr-2013 Sanction
front Shed / boundary wall height of Bay-1 &2 Received

7 Installation of remaining drilling machines (9 nos.) 30-Apr-2013 In Progress


8 Installation of HMC, CNC VMC (2 Nos), Lathe (4 nos) 15-May-2013 In progress
9 Dismantling, Shifting, Install. Commissioning of VTL 31-May-2013 In progress
Dismantling, Shifting, Install. Commissioning of CNC-VTL,
10 15-Jun-2013 Planned
DHD **
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
L&T Heavy Engineering

Facility at Plot “B6”

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
36
L&T Heavy Engineering

Facility at Plot “B6”

Covered Total Area Power


Bay 1 Bay 2
Area (Open & Covered) Connection
BAY SIZE 80 L x 18 W 80 L x 18 W 3000 m2 4400 m2 200 KVA with
125 KVA DG
CRANES 10 T - 2 nos 10T – 2 nos Back-up
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
37
L&T Heavy Engineering
Facility at Plot “B-6” – Warehouse & CMF, M/c Shop

B6 - Plant Layout wrt


Flow is Finalized.

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
38
L&T Heavy Engineering
B6 Plant Status Vacating/ Cleaning of B6, Bay 2
 Bay-2 being vacated, cleaning/painting of structures started.

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
39
L&T Heavy Engineering
B6 Plant Status New Metallic Roofs installed

 Plant Structural inspection done by L&T Structural consultant

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
40
L&T Heavy Engineering
B6 Plant Status New Metallic Roofs installed
Electrical old cables removed, laying of new cables in progress

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
41
L&T Heavy Engineering
B6 Plant Status New Metallic Roof/side panels
 Partition completed, Structural Column repairs completed

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
42
L&T Heavy Engineering
B6 Plant Status New Metallic Roof/side panels
 Shop roof, side Asbestos sheets replacement by Galvanized sheets.

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
43
L&T Heavy Engineering
B6 Plant Status Electrical Sub-Station
 Repair of Electrical Sub-station room completed

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
44
L&T Heavy Engineering
B6 Plant Status Earthing Pit in B6
Earthing pit revamping completed

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
45
L&T Heavy Engineering
B6 Plant Status Readiness Milestones
Sr. Current
Action Plan Target Dates
No. Status
Finalise contract for operations of Stores & LAN
1 30-Nov-2012 Completed
Connection.
JGI to get Bay-1 + Open area vacated from Existing
2 15-Dec-2012 Completed
Contractor .
Partition between Bay-1 & Bay-2, Storage Racks,
3 20-Dec-2012 Completed
Overhead Lights, Security arrangement.
4 Readiness of the Warehouse- BAY-1 15-Jan-2013 Completed

5 JGI to get Bay-2 vacated and cleaned. 30-Mar-2013 In Progress


Electrical connections, lighting, floor cleaning
6 30-Mar-2013 In Progress
painting.

7 Installation and commissioning of Lathe/Rolling M/c 30-May-2013 In Progress


Contractor mobilisation for Warehouse . 1- Feb-2013/ Started/
8
Machining of jobs to start. 1-June-2013 Planned

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
46
L&T Heavy Engineering
BPC Status Logistics & Facilities
• Bus from Thane (W) to JGI Badlapur (48 kms)
Transportation for
• Shuttle Service, between Badlapur Station & JGI and
L&T staff
between Powai & JGI.

Transportation for
• Train
Contractors’
Workmen
• First aid centre inside F2 Plant
• Hospitals – ESIC attachments
Medical Facility
• Attachment to Private Hospitals- Dhanavantari, Fortis
• Ambulance – 24x7 Basis
• Emergency Preparedness Plan will be made in
Force Majeure
consultation with Safety department.

26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
47
L&T Heavy Engineering

Thank You