26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved 1 of 45
L&T Heavy Engineering
Facilities at John Galt-MIDC, Badlapur
Plot B6 (Warehouse,
CMF & M/c)
Plot Size: 4400 m2
Covered Area: 3000 m2
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved 2
L&T Heavy Engineering
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved 3
L&T Heavy Engineering
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
4
L&T Heavy Engineering
Facility at Plot “F2”- Manufacturing Shop
Total Area
Covered POWER
Bay 1 Bay 2 Bay 3 (Open &
Area - m2 Connection
Covered)
BAY
158 L x 21 W 158 L x 23 W 142 L x 21 W 9900 25000 m2 200 KVA existing+
SIZE
New 500 KVA.
25T – 2 nos DG Back-up Exist.
CRANES 10 T - 3 nos 10T – 3 nos 125 KVA+ Addnl.
10 T – 1 no.
315 KVA
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
5
L&T Heavy Engineering
Facility at Plot “F2”- Manufacturing Shop
14.0 m
12.5 m
(Under
Hook Ht)
Bay 2L Bay 3L
Bay 1L 11 m
9.50 m (Under
Hook Ht)
Bay 1 Bay 2 Bay 3
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
7
L&T Heavy Engineering
NDE BLOCK
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
8
L&T Heavy Engineering
F2 Plant Status RT Enclosure
RT Enclosure - Civil, Electrical work Completed.
BARC Authorities inspection completed on 22 Mar’13.
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
9
L&T Heavy Engineering
F2 Plant Status
Welding Consumable Store, Hot Room
Welding Consumable Stores, Hot room Ready.
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
10
L&T Heavy Engineering
F2 Plant Status Main Stores, Excise Office
Main Stores, Excise room work completed.
Toilet commissioning in progress.
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
11
L&T Heavy Engineering
F2 Plant Status Water Storage Facility
Underground Water Storage Tank (2.6 Lac Liter) completed.
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
12
L&T Heavy Engineering
F2 Plant Status Concreting of Lower Bays
Bay 1 (Lower) flooring in progress.
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
13
L&T Heavy Engineering
F2 Plant Status F2 - Plant Office
Civil work of Plant office (Admin Block) completed
Electrical, Furnishing work completed.
Compound Wall, Entry Gate to Office renovation completed.
Painting completed & finishing will be completed by 30 Apr’13.
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
14
L&T Heavy Engineering
F2 Plant Status F2 - Plant Office
Garden at the entrance of Plant office (Admin Block).
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
15
L&T Heavy Engineering
F2 Plant Status Electrical, LAN, Telephone Cabling
Server Room, EPABX for Telephone lines commissioned.
Installation of Hume Pipes for Electrical/LAN, BSNL Cable completed.
construction of drainage in progress.
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
16
L&T Heavy Engineering
F2 Plant Status Development of outside area
Surrounding Plot Survey done.
Landscape/leveling/roads finalized by Structural Consultant.
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
18
L&T Heavy Engineering
F2 Plant Status Development of Facilities
Canteen / Dining Area for workers.
Tables
arranged
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
19
L&T Heavy Engineering
F2 Plant Status Development of Facilities
Slab laying completed
Toilets for
Workmen in
progress
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
20
L&T Heavy Engineering
F2 Plant Status LAN Connectivity with Powai
LAN Tower from Bharti Airtel installed, RF Commissioned.
Connectivity with Powai Server already established.
Connectivity between 3 locations i,e,F21, B21, B6 established.
Interconnecting
Tower F2, B21, B6
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
21
L&T Heavy Engineering
F2 Plant Status Planning of WTC/First Aid Facility
Old existing structure demolished, Plan for WTC/First Aid/ Training
room /Cylinder Storage finalized and digging for column is i/p.
Exploring CNG Piping inside F2 to eliminate Gas Cylinders.
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
22
L&T Heavy Engineering
F2 Plant Status Readiness for Manufacturing
Bay- 1, 2 & 3 - Upper areas vacated and cleaned.
CMF piping work from R&C-Shop2 shifted to Bay-2, Upper area
Bay-3, Lower earmarked for Nuclear jobs. Planning the partitioning of
the Bay-3 Lower side.
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
23
L&T Heavy Engineering
F2 Plant Status Construction -Electrical Sub-Station
MSEB Permission for increased Power received / DG set ordering
completed.
Civil work for Electrical Sub-Station in Progress.
Full Power 200+500 KVA; DG set 125+315 KVA by 30 May’13.
New DG installed
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
24
L&T Heavy Engineering
F2 Plant Status Readiness Milestones
Sr.
Action Plan (phase - 1) Target Dates Current Status
No.
1 JGI to get Bay-2 vacated and release three buildings. 15-Jan-2013 Completed
2 JGI to get open Area and one buildings. 28-Feb-2013 Completed
NDE Block/Dark Room, Welding Consumable
3 stores/Hot Room, Cleaning , Lighting in shop top side 28-Feb-2013 Completed
Bay - 2 for ASME Audit.
RT Enclosure (Civil, Electrical) work completed.
4 15-Mar-2013 Completed
BARC Audit completed on 22 Mar’13 Satisfactorily.
5 Enhance Power Supply 500KVA, DG Set 315 KVA 15-Mar-2013 Sanction Recd
LAN connection & Movement of contractors,
6 Machines, Tools, Tackles and Start component 15-Mar-2013 Completed
manufacturing of “Non-AI /IBR “ jobs
JGI to get Bay-3 Upper & Lower vacated. Fencing /
7 15-Apr-2013 In progress
Painting / Lighting of Buildings/shops as required.
Planning
8 Cloak Rooms, Toilet, Leveling of Open Area, roads 15-May-2013
completed
9 ASME Audit of the Facility, Start ASME jobs 10-June-2013
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
25
L&T Heavy Engineering
F2 Plant Status Major Infrastructure Enhancement
Sr. Current
Action Plan (Phase -2) Target Dates
No. Status
1 Concreting of Shop Floor –Bay -2 - Lower side 30 Mar 2013 completed
Installation of New Power connection- 500 KVA &
30 May 2013 Started
2 DG Set – 315 KVA
Levelling of land, concreting of rail area for Gantry
3 Installation of Gantry Crane, Shot Blasting & 30 Jun 2013 in progress
painting Shed - 8 W x 8 H x 20 L
4 Installation of Gantry Crane 30 Sept 2013 Planned
Sr. Current
Action Plan (Phase – 3) Target Dates
No. Status
1 Concreting of Shop Floor - lower Bay 1 30 Apr 2013 In Progress
2 Levelling of Open Area - remaining 30 May 2013 In Progress
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
26
L&T Heavy Engineering
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
27
L&T Heavy Engineering
Facility at Plot “B21”Machining Shop
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved 30
L&T Heavy Engineering
B21 Plant Status Installation of Drilling Machines
Installation of 3 radial drilling M/cs in Bay-2 in progress.
HMC, VTL, Lathe M/c’s planned to be shifting completed,
commissioning in progress.
Tiles polishing in progress
Lathe Machine
Foundation in progress
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved 31
L&T Heavy Engineering
B21 Plant Status Power Upgradation
Power Sanction 200 to 500 KVA obtained. DG 300 KVA installed.
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved 32
L&T Heavy Engineering
B21 Plant Status
Gangway marking
Front Roof
Tool Storage
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved 33
L&T Heavy Engineering
B21 Plant Status Vacating/Cleaning of Bay - 2
Civil work of Main office, Partition wall and Toilets in progress.
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
36
L&T Heavy Engineering
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
38
L&T Heavy Engineering
B6 Plant Status Vacating/ Cleaning of B6, Bay 2
Bay-2 being vacated, cleaning/painting of structures started.
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
39
L&T Heavy Engineering
B6 Plant Status New Metallic Roofs installed
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
40
L&T Heavy Engineering
B6 Plant Status New Metallic Roofs installed
Electrical old cables removed, laying of new cables in progress
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
41
L&T Heavy Engineering
B6 Plant Status New Metallic Roof/side panels
Partition completed, Structural Column repairs completed
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
42
L&T Heavy Engineering
B6 Plant Status New Metallic Roof/side panels
Shop roof, side Asbestos sheets replacement by Galvanized sheets.
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
43
L&T Heavy Engineering
B6 Plant Status Electrical Sub-Station
Repair of Electrical Sub-station room completed
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
44
L&T Heavy Engineering
B6 Plant Status Earthing Pit in B6
Earthing pit revamping completed
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
45
L&T Heavy Engineering
B6 Plant Status Readiness Milestones
Sr. Current
Action Plan Target Dates
No. Status
Finalise contract for operations of Stores & LAN
1 30-Nov-2012 Completed
Connection.
JGI to get Bay-1 + Open area vacated from Existing
2 15-Dec-2012 Completed
Contractor .
Partition between Bay-1 & Bay-2, Storage Racks,
3 20-Dec-2012 Completed
Overhead Lights, Security arrangement.
4 Readiness of the Warehouse- BAY-1 15-Jan-2013 Completed
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
46
L&T Heavy Engineering
BPC Status Logistics & Facilities
• Bus from Thane (W) to JGI Badlapur (48 kms)
Transportation for
• Shuttle Service, between Badlapur Station & JGI and
L&T staff
between Powai & JGI.
Transportation for
• Train
Contractors’
Workmen
• First aid centre inside F2 Plant
• Hospitals – ESIC attachments
Medical Facility
• Attachment to Private Hospitals- Dhanavantari, Fortis
• Ambulance – 24x7 Basis
• Emergency Preparedness Plan will be made in
Force Majeure
consultation with Safety department.
26 Mar 2013 © 2011 Larsen & Toubro Limited : All rights reserved
47
L&T Heavy Engineering
Thank You