Status of Silkyara Tunnel

Construction of 4.5 Km long Silkyara Tunnel between


Km 25.40 to 50.25 Km
• CONTRACTOR : M/s Navayuga Engineering Co. Limited
• AUTHORITY ENGINEER : To be appointed
• LOA Date : 31.05.2018
• APPOINTED DATE : 09.07.2018
• DATE OF COMPLETION : 08.07.2022
• C. A. AMOUNT : Rs. 853.79 Cr.
• Financial progress : 10.36 %
• Physical progress : 5.36 %
As per CA Status
• Milestone I (10%) : 05-04-2019 (In Progress)
• Milestone II (25%) : 31-12-2019
• Milestone III (45%) : 26-09-2020
• Milestone IV (70%) : 23-06-2021
• Milestone V (100%) : 08-07-2022
Physical & Financial Progress (Silkyara Tunnel)
Sr. No Item of work Unit Total % of Scope of Total Work Completed up
scope work to 31st March 2019

1 Investigation & Detail Designs Km 4.86 2.326 2.326 %

2 Tunnel Portal no 2 6.36 1.62 %

3 Main Tunnel with escape passage km 4.531 71.548 0.100 km (1.03%)

4 Site Facility Km 4.86 1.272 0.3816 %

5 Electro & Mechanical Equipment of km 4.531 16.782 -


Tunnel
6 Ventilation System km 4.531 1.681 -

7 Approach roads mtr 328 0.031 -

Total 100 % 5.36%


Barkot Portal (North)
)
Thank you