Rehabilitation and Recovery Management Service: Revised Guideline in Administration of NDRRM Fund
Rehabilitation and Recovery Management Service: Revised Guideline in Administration of NDRRM Fund
I. BACKGROUND
NGA Office/Person
Indicative
Timeline
Responsible (Working Days)
15
Evaluates and days
With
OCD PDNA
recommends to OCDRO
OCD National
?
Office
Yes
Conducts further OCD
review National
Endorsement 10
- Recommends project days
Step 2
to the President
OCD/DND
Total:
15 days – with PDNA
30 days – w/o PDNA
Review and Approval Process of LGU Requests
Office/Person Timeline
LGU
Responsible
Receipt and
Screening
Step 1 OCDRO 10 days
- Establishes eligibility
- Activates RP-VET
Evaluation
OCD Step 2 - Technical, financial RP-VET 40 days
and/or field validation
- Submits validation report
Endorsement
Step 3 - Conducts further review OCD/DND 10 days
- Recommends project to
the President
Total – 60 days
Allow prevention, mitigation and preparedness
projects such as:
a. Acquisition of land or lot for resettlement of high risk
population
b. Site development for resettlement
c. Multi-purpose evacuation center
d. Water catchment/storage facility
e. Retrofitting of LGU buildings
f. Integrated early warning and Disaster Operations Center
g. Construction of local DRR public infrastructure (i.e. multi-
purpose evacuation center with women and child-friendly
spaces)
h. Disaster Risk Insurance
Sample RP-VET Composition
Lead Evaluating Proposed Partner
Type of Project
Agency Agency/ies
Post-Disaster: Relief, Rehabilitation, Recovery and Reconstruction Projects
DPWH, NIA, DepEd,
1. Repair, rehabilitation, and reconstruction of local public infrastructure damaged or DILG
DOH, NEDA, DENR-
destroyed by natural or human induced disasters
MGB, OCD
2. Support and assistance for resettlement of affected populations from transition to NHA, DILG, DPWH,
permanent sites (i.e. land acquisition, site development, and cash-based DSWD DOST, DENR-MGB,
programming) OCD
3. Local economic recovery for employment and income generation and reintegration, DILG, DOLE, DA,
DTI
and other capacity building projects for affected communities, among others OCD
Pre-Disaster: Disaster Mitigation, Prevention and Preparedness Programs and Projects
DILG, NHA, DOST,
1. Acquisition of land or lot for resettlement DENR
OCD, DENR-MGB
NHA DSWD, DPWH, NEA,
2. Site development of resettlement areas
LWUA, OCD
3. Construction of local DRR public infrastructure (i.e. multi-purpose evacuation center DILG
DSWD, DPWH, OCD
with women and child-friendly spaces)
Priority LGUs will those be with (1) high risk profile (violet), (2) low income
class (orange), and (3) high performance (blue).
Target
Target
Actual
Actual
Cost / LGU Fund