Professional Documents
Culture Documents
Bridge Hydraulics (Sanjay)
Bridge Hydraulics (Sanjay)
Bridge Hydraulics (Sanjay)
HYDRAULICS
F
C C
Important definitions (para 2 0f sub structure code)
For streams with non-erodible beds, the afflux may be worked out by
Molesworth formula given below :
h = {V2/17.88 + 0.01524} x {(A/a) 2- 1}
Para 4.3.2 Where such Stream flow records exist for less
than the desired recurrence interval but sufficient for the
statistical analysis-
design discharge may be : Computed statistically
for the desired recurrence interval.
Method of Estimation of Design discharge
(Para 4.3 of substructure code )
Para 4.3.3 where records of floods are not of sufficient length to
permit reliable statistical analysis but where
A unit hydrograph is
1 Cm RAINFALL EXCESS the hypothetical
response of a water
shed ( in terms of
tp run off volume &
timing) to a unit
input of rainfall
It can be defined as
TYPICAL
UNIT
direct run off
HYDROGRAPH hydrograph resulting
from one unit ( say 1
cm) of effective
Qp rainfall occurring
DISCHARGE IN m 3/s
It is a hydrograph of
direct surface run off
resulting from unit
Ts effective excess rainfall
generated uniformly over
catchment.
TIME IN HOURS
Basic principles of UH
For a given watershed
Physiographic Parameters.
Hydrometeorologcal parameters
CATCHMENT PARAMETERS
AREA OF CATCHMENT -A
5
4
CG OF THE CATCHMENT
3
LENGTH OF LONGEST STREAM : L
L
Lc 2
LENGTH OF STREAM FROM
NEAREST TO CG TO THE BRIDGE
SITE – Lc
Q50 0.278CI 50 A
C= runoff coefficient
A : catchment area in sq KM
I50 : 50 year rainfall intensity mm/hr = R50(tc) / tc
Runoff coefficient
C X ( R.F ) 0.2
Catchment
Duration of Rainfall
area
=3.2468 hrs.
=194.8 mins
50-YEAR ONE DAY RAIN FALL(mm)
Sample: Flood estimation
Q₅₀ = 0.278 x C x I x A
Runoff coefficient (C)
For Black cotton soil (from table sr. no.(d))
C = 0.456 (R x F)^ 0.20
Areal reduction Factor F:
Catchment area Duration of Rainfall
( sq.km ) < 30 min. 30 to 60 min. 60 to 100 min.
> 13.00 < 25.00 0.68 0.78 0.85
R=50 yr 24 hrs Rainfall Ref. Fig 1Of RBF16 (Plate 8 from CWC
report of Subzone 3f) = 220mmX 1.15 ( = 25.3cm)
i) Tc h ratio ( from map fig 4 of RBF (16) is based on time concentration 0.570
=
& Ratio of 50yrs T hrs Rainfall / 50yrs 24hrs Rainfall)
ii) 1 h ratio ( from map fig 4 of RBF (16) is based on time concentration 0.380
=
& Ratio of 50yrs T hrs Rainfall / 50yrs 24hrs Rainfall)
Tc h ratio 0.570
iii) Coeff. K' = = = 1.500
1 h ratio 0.380
iv) 50 year 24 hrs rainfall from fig1 of RBF 16 =220x1.15= = 253 mm
Q₅₀ = 0.278 x C x I x A
0.278x0.84x42.5x24.71
Q₅₀ = 0.278 xCxIxA
245.24x C xm3/s
Q₅₀ = 0.278 IxA
Flood estimation for Medium
catchments : area >25 sq km
and <2500 sq km–
By developing SUG based on
FERs
Estimation of design discharge by SUH
Why?
Unit hydrograph can be developed, if site specific
concurrent rainfall-runoff data is available for 5-8 yrs. But
collection of adequate data for every site is neither
practicable nor economically feasible.
tr
1 Cm RAINFALL EXCESS
p
t
TYPICAL
UNIT
HYDROGRAPH
W 75
W R75
DISCHARGE IN m /s
Qp
3
W 50
W R50
TB
TIME IN HOURS
e.g. (For kaveri sub zone -3(i) ) the parameters are as under
tp Time taken from centre of rainfall excess(1 cm) in 1 0.553(L LC √S)0.405
hr unit duration to the UG peak( in hrs)
3
DISCHARGE IN m /s UH DUE TO X 1< 1cm RAINFALL EXCESS
X2.q
q
X1.Q
TB B
TIME IN HOURS
( CONSTANT FOR A GIVEN t )r
Method / steps for Estimation of Design discharge (Q50)
for catchments ( 25 to 2500 sqkm)
Therefore
£Q =A/0.36, Sum total of UH ordinates is equal to A / 0.36
{Note: The 50 year -24hrs rainfall data for all India are available as Fig-1
of RDSO report RBF-16}
Then from fig-10 of report for a given storm duration ratio is to be read, Say
for 7 hrs duration the ratio is 0.74
0.1004
Now Base flow qb = 0.032 / (A) , where A is catchment area in sqkm and
3
qb is base flow rate in m /sec/sq.km
Step-5: Estimation of 50 Yr flood peak
1 Q1 Q1 R1 Q0 R2 - - -
2 Q2 Q2 R1 Q1 R2 Q0 R3 - -
3 Q3 Q3 R1 Q2 R2 Q1 R3 Q0 R4 - Q3 R1+ Q2 R2+
Q1 R3+ Q0 R4+
Q
4 Q4 Q4 R1 Q3 R2 Q2 R3 Q1 R4 Q0 R5
5 Q5 Q5 R1 Q4 R2 Q3 R3 Q2 R4 Q1 R5
Q5 R2 Q4 R3 Q3 R4 Q2 R5
Sample calculations
SUG
Br.No. 807/1 of NGP-SEGM (C. Rly.)
Design Data
1 Name of HydroMeterological Sub-Zone = 3f Lower Godavari
2 Name of Tributary Kistana River
3 Shape of Catchment Fan Shape
4 Location - Latitude = 79° 0'36.00"E
- Longitude = 20°54'5.13"N
∑ Li x [D(i-1)+Di] 8129.338
Se = =
L² 3905
Se = 2.082 m/Km
Synthetic Unit Hydrograph Parameter
Ref. Table 3.2 . From page no 12 of FER for 3f
X-Co-Ordinate Y- Co-Ordinate
0 0.000 0 0.000
Tm - WR₅ₒ 5.202 Qp x 0.50 154.327
Tm - WR₇₅ 6.282 Qp x 0.75 231.491
Tm 7.853 Qp 308.654
Tm + W₇₅- WR₇₅ 9.904 Qp x 0.75 231.491
Tm + W₅ₒ- WR₅ₒ 11.593 Qp x 0.50 154.327
Tᴃ 27.311 0 0.000
Estimation of Design Storm (Ref. Clause no. 5.2 step-2 of FER for 3f)
Point Rainfall
( Plate 10 of flood estimation report . 50 yr 24 hour Rainfall map of India)
Td hrs
Td hrs Td hrs
Time in Storm Distn. Hourly
time Storm Distn.
hours Col3x130.91 Storm
Distrn. From Table
/100
cm cm
0 0.00 0 0 0
1 12.50 41 4.871 4.871
2 25.00 65 7.722 2.851
3 37.50 76 9.029 1.307
4 50.00 83 9.861 0.832
5 62.50 90 10.693 0.832
6 75.00 94 11.168 0.475
7 87.50 98 11.643 0.475
8 100.00 100 11.881 0.238
Design Loss Rate
Ref. Page No 14. Para 3.5 of FER for 3f
Design loss Rate = 0.4 cm/hrs
Base Flow
Ref. Page No 14. Para 3.6 of FER for 3f
Design Base Flow = 0.05 cumecs/sq.Km
= 0.05x834.2 cumecs
= 41.710 cumecs
Computation of Critical Sequence of Rainfall
Ref. Page no. 21 step -4 of FER
Hourly Rainfall Rainfall
Time in SUH increment Constant loss Rainfall Excess Peak Excess in
direct ruoff
hours Ordinates of rainfall rate excess value for Critical
(cm) peak Discarge Order
(Cumes) (cm) (cm/hr) (cm) S.U.G. cm
0.432
0 0 0 0 0 - - 0.907
1 8 4.871 0.4 4.471 4.471
2 20 2.851 0.4 2.451 2.451
3 40 1.307 0.4 0.907 0.432
4 75 0.832 0.4 0.432
5 140 0.832 0.4 0.432
6 210 0.475 0.4 0.000 0.432 90.646
7 290 0.475 0.4 0.000 2.451 710.894
8 308 0.238 0.4 0.000 4.471 1377.090
9 275 0.907 249.390
10 222 0.432 95.825
11 175
12 132 Total 2523.845
13 100 Base flow 41.710
14 75 Q50 2565.555
15 58
16 45
17 34
18 27
19 22
20 17
21 14
22 11
23 9
24 6
25 4
26 2
27 0
2319
Computation of Design Flood Hydrograph
Ref. Page no. 22 item (b) of FER
Total Design
SUH Direct Surface RunOff(DSRO) in m3/s due to rainfall Excess increament in cm Base Flow
Time Surface Flood
Ordinate
Flow Hydrodrap
Hrs 0.000 0.432 0.907 4.471 2.451 0.432 0.000 cm m3/s h Ord.
1 2 3 4 5 6 7 8 9 11 12 13
0 0 0.000 0.000 0
1 8 0.000 3.453 0.000 3.453 41.71 45.163
2 20 0.000 8.633 7.255 0.000 15.888 41.71 57.598
3 50 0.000 21.582 18.137 35.769 0.000 75.488 41.71 117.198
4 80 0.000 34.532 45.344 89.421 19.611 0.000 188.908 41.71 230.618
5 148 0.000 63.884 72.550 223.554 49.027 3.453 412.467 41.71 454.177
6 210 0.000 90.646 134.217 357.686 122.568 8.633 0.000 713.749 41.71 755.459
7 290 0.000 125.177 190.443 661.718 196.109 21.582 0.000 1195.030 41.71 1236.740
8 308 0.000 132.947 262.993 938.925 362.801 34.532 0.000 1732.198 41.71 1773.908
9 275 0.000 118.703 279.317 1296.610 514.785 63.884 0.000 2273.299 41.71 2315.009
10 222 0.000 95.825 249.390 1377.090 710.894 90.646 0.000 2523.845 41.71 2565.555
11 175 0.000 75.538 201.326 1229.544 755.018 125.177 0.000 2386.604 41.71 2428.314
12 132 0.000 56.977 158.703 992.578 674.124 132.947 0.000 2015.328 41.71 2057.038
13 100 0.000 43.165 119.707 782.437 544.202 118.703 0.000 1608.213 41.71 1649.923
14 75 0.000 32.373 90.687 590.181 428.988 95.825 0.000 1238.055 41.71 1279.765
15 58 0.000 25.035 68.015 447.107 323.579 75.538 0.000 939.275 41.71 980.985
16 45 0.000 19.424 52.599 335.330 245.136 56.977 0.000 709.466 41.71 751.176
17 34 0.000 14.676 40.809 259.322 183.852 43.165 0.000 541.824 41.71 583.534
18 27 0.000 11.654 30.834 201.198 142.179 32.373 0.000 418.239 41.71 459.949
19 22 0.000 9.496 24.486 152.016 110.311 25.035 0.000 321.345 41.71 363.055
20 17 0.000 7.338 19.951 120.719 83.346 19.424 0.000 250.778 41.71 292.488
21 14 0.000 6.043 15.417 98.364 66.187 14.676 0.000 200.686 41.71 242.396
22 11 0.000 4.748 12.696 76.008 53.930 11.654 0.000 159.037 41.71 200.747
23 9 0.000 3.885 9.976 62.595 41.673 9.496 0.000 127.625 41.71 169.335
24 6 0.000 2.590 8.162 49.182 34.319 7.338 0.000 101.591 41.71 143.301
25 4 0.000 1.727 5.441 40.240 26.965 6.043 0.000 80.415 41.71 122.125
26 2 0.000 0.863 3.627 26.826 22.062 4.748 0.000 58.128 41.71 99.838
27 0 0.000 0.000 1.814 17.884 14.708 3.885 0.000 38.291 41.71 80.001
28 0.000 8.942 9.805 2.590 0.000 21.337 41.71 63.047
29 0.000 4.903 1.727 0.000 6.629 41.71 48.339
30 0.000 0.863 0.000 0.863 41.71 42.573
31 0.000 0.000 0.000 41.71 41.710
32 0.000 0.000 41.71 41.710
33 0.000 0.000 41.71 41.710
34 0.000 0.00 0.000
Assumption
If, however, a river spills over its banks and the depth of spill is appreciable
the waterway shall be suitably increased beyond the bank-to-bank width in
order to carry the spill discharge as well.
Para 4.5.2 In the case of a river having a comparatively
wide and shallow section, with the active channel in flood
confined only to a portion of the full width from bank to
bank,
constriction of the
natural waterway
would normally be
desirable from both
hydraulic and cost
considerations.
Pw = Wetted perimeter in
metres which can be taken as the
effective width of waterway in
case of large streams
Waterway based on width of active channel including spilling of water if any = ----
Illustration -1) Suppose bank to bank width of river is 18 meters and active channel
width is 9 meters then waterway to be provided can be taken as 9 meters provided it
satisfies all the norms in terms of velocity of flow, free board, clearance, HFL.
Illustration 2) Suppose bank to bank width is 21 meters, the river is flowing full bank
to bank and there is a water spilling beyond banks by say 4 meters width. In this case
the waterway to be provided shall be 25 meters
Step-2: Selecting type of bridge (pipe culvert / Box culvert / Arch / Slab / Girder
Bridge)
The type of bridge shall be selected on the basis of various factors such as
design discharge (Q50), linear water way requirement, velocity of flow, scour
depth requirement, approach bank height, soil strata conditions.
Step-3: Fixing norms for Free board, vertical clearance based on type of bridge
selected)
Norms for velocity of flow
The norms for velocity of flow can be taken as 3 m/sec based on sub structure
code Para 5.9.2.1.2. However, velocity during annual peak flow if available can
be used for guidance.
Norms for HFL
The computed value of HFL based on depth of flow calculated for assumed
water way width should be close to observed HFL. River flow conditions during
annual peak flow can also be used for guidance.
Step-4: Value of n & bed slope of stream:
2/3 1/2
Slope (S) :While calculating velocity of flow ( V = 1/n x R xS ), the average
slope (S) of the river bed is to be determined from a point about 2 kms
upstream of the Railway crossing to a point 2 kms downstream of the same. In
case there are sharp changes in the bed slopes, the local bed slope should be
determined over a shorter length. (Para 305(2) Bridge manual).
iii) Natural channel with variable section & some vegetation growing 0.050
on banks
V= Q /A Q is Design discharge
2/3 1/2
V= (1/n x R xS ) Manning formula
d
Total width of waterway assumed = B,
No of piers assumed = N
B
Effective width of pier assumed = b
Effective width of waterway shall be (B’) = B – n x 2 b
2/3 1/2
=> Q50/( B’ x d) = (1/n) [(B’x d)/ (B’+ 2d)] (S )
Using above equation, work out depth of flow (d) for assumed value of width of
water way (B)/ effective width of waterway B’.
Step-6: Estimating various parameters for the set of assumed value of B
(width of water way) & calculated value of d (depth of flow)
Note: For various widths of waterway as assumed @ suitable interval , between the
minimum & maximum possible width of waterway estimated in the step-2,
workout depth of flow d for 5 to 7 values of assumed width of waterway & the
calculate the above 4 parameters i.e. velocity of flow , calculated HFL, vertical
clearance, free board. Compare the values of calculated parameters with laid down
norms as discussed in step 4 above.
Step-7 : Finalisation of span & working out various parameters for chosen
span
Based on the exercise done under step-7, the minimum span, which satisfy
all laid down norms in terms of velocity of flow, HFL, vertical clearance, free
board and which can utilise as far as possible the available standard spans
of RDSO is finalise.
Now for this proposed span arrangement, the depth of flow is calculated on
the basis of accurate value of hydraulic radius and the various parameters
i.e. actual velocity of flow, HFL, vertical clearance & Free board are
computed, compared & checked again with norms laid down for these
parameters to finalise the span arrangement.
Sample calculations
Waterway
Working out depth of flow (d) for assumed width of water way (B)
Q/(BxY) =
245.24/(3 x 6.5x4.45) = 1/0.05x(3 x 6.5x4.45)/(3 x 6.5+2x4.45)^2/3x0.004545^1/"2
2.83 m/sec = 2.84 m/sec
Flow is Sub-Critical
Checking for adequacy of waterway provided For Bridge:-
As Waterway requirment fullfilled , hence there is no contraction in waterway at c/s of Ex. Bridge
Therefore Afflux at bridge section will be zero.
Formation Level
Minimum Formation Level Required = CHFL+Afflux+Free Board = 240.580
Formation Level
Minimum Formation Level Required = CHFL+Afflux+Free Board = 240.580
Para 4.6.2 Wherever feasible & especially for flashy rivers and with
beds having boulders or gravels sounding for purpose of
determining the depth of scour shall be taken in the vicinity of
site proposed for the bridge. Such sounding are best taken
during or immediately after flood
In calculating design depth of scour allowance shall be made in
the observed depth for increased scour due to
i)The Design discharge being greater than observed discharge
ii) Increase velocity due to constriction
iii)Increase in scour in the proximity of pier/abutments
Para 4.6.3 In the case of natural channels flowing in alluvial
beds where the width of waterway provided is not less than
Lacey’s regime width,
the normal depth of Scour (D) below the foundation design
discharge (Qf) level may be estimated from Lacey’s formulas as
indicated below
D = 0.473 (Qf/f)1/3
where D is depth in metres,
Qf is in cumecs and
f is Lacey’s silt factor for representative sample of bed material
obtained from scour zone.
Para 4.6.4 Where due to constriction of waterway,
the width is less than Lacey’s regime width for Q or
where it is narrow and deep as in the case of incised
rivers and has sandy bed, the normal depth of scour
may be estimated by the following formula :
D = 1.338 (qf2/f)1/3
Where
qf = the discharge intensity in cubic metre per second per
metre width and
‘f’ = silt factor as defined in clause 4.6.3.
Para 4.6.5 The silt factor ‘f’ shall be determined for representative samples
of bed material collected from scour zone using the formula :
f = 1.76 √m Where m is weighted mean diameter of the bed
material particles in mm
The Values for ‘f’ for different types of bed material, commonly met with are given below:
Step 1 - Design discharge for foundation: The design discharge for foundation
(Qf) shall be estimated based on Q50 & size of Catchment (Design discharge for
foundation (Para 4.4 S.S.C)
a)The normal depth of Scour (D) below the foundation design discharge
(Qf) level may be estimated from Lacey’s formulas as indicated below
1/3
D = 0.473 (Qf/f) --------- Eq-1 ( Para 4.6.3 SSC)
The scour depth calculated in step 3 above, refers to maximum anticipated scour
level from the water level corresponding to Qf, therefore the depth of maximum
scour level from the bed level can be ascertained if depth of flow corresponding to
Qf is known.
The depth of flow corresponding to design discharge for foundation (Qf) for given span
arrangement shall be worked out using equation discussed under para A step-6 above.
The maximum anticipated scour depth from bed level shall be accordingly worked out
after deducting the depth of flow corresponding to Qf.
The foundation should rest below the maximum anticipated scour length for certain
length called as grip length, the value of grip length in case of open foundation is
1.75 m in case of ordinary soil. However if the rock strata ( soft or rock ) is available
at higher level which is considered as non-erodible bed then the foundation should
keyed in rock for 0.3 m ( in case of hard rock) & 1.5 m ( in case of soft rock) .
Water level
corresponding to Q
f
1
()
3
Qf
D = 0.473
Water depth or
f
1
Bed level
()
3
q2
1.25D for Abutment = 1.338 f
f
2D for Pier
Scour level
Foundation depth
Max. anticipated scour level
Grip length
This should be the level
where foundation should Foundation level
rest
Step 6 Depth of foundation: The depth of foundation shall be accordingly = Maximum
scour depth from bed level (as worked out in Step 4) + Grip length (as discussed in Step
5).
Note : In case non scour able strata (rock strata) is available at shallow depths, then
the foundation shall rest at that level suitably keyed into the rock strata (as discussed in
Step 5 above), irrespective of scour depth calculated in the Step 2 and 3 above.
Note: Rly Board Instructions on Minimum span size: (Ref: Correction slip 25 dated 17-
12-12 of bridge manual)
Minimum clear span =1 m for new bridges and Rebuilding of existing bridges
Minimum headroom =1.2 m for new bridges, however while constructing /
rebuilding new bridges on existing lines all efforts to provide it, otherwise
PCE/CBE may permit relaxation
References:
1. Sub Structure Code -2013
2. RBF-16 report published by RDSO
3. Flood estimation report for kaveri basin sub zone – 3(i)