Professional Documents
Culture Documents
Construction of Multistoried Boys Hostel by Kanwarjot Singh
Construction of Multistoried Boys Hostel by Kanwarjot Singh
Construction of Multistoried Boys Hostel by Kanwarjot Singh
Origin of CMS
Projects Undertaken By CMS
Construction Process
Site Clearance
Demarcation of Site
Excavation : 5’4” with
JCB’s and manually
Construction Process contd.
PCC
Mix =1:5:10
Layer of 4”
Compacted from 15
mm to 10mm with
rammer
30 degree angle at
joints
Surface is watered
and cleared
Construction Process contd.
Foundation: Raft And
Isolated
We Assured
1) Steel is free from dirt
2) Proper binding of
steel
3) Cover blocks
Reinforcement
Type of Steel :Fe 415
Kamdhenu
Terms Used
Lap Length = Not
More than 50% of bars
are cut at one section
Anchorage Length
Column=47d
Beams/Slab=58d
Cover Blocks 1:3
Reinforcement contd..
Cover to
Structural
reinforcement
Element
(inches)
Footings 2
Columns 1
Beams 0.75
Shuttering And Scaffolding
Treatment of forms:
Cleaned with iron brush
to make sure no
dirt/concrete
Erection : Checking the
alignment
Stripping Time
Slab = 8-10 days in
summers and 10-12 days
in winter
Checked No wooden Ballies
were used
Shuttering And Scaffolding
contd…
Concreting
Facts about cement &
concrete -PPC 53
M25 consisting
Water Content: 180 kg/m³
Cement Content: 409.10
(kg/m³)
Super-plasticizer: 1.5% by
weight of cement
Concrete Mixer and
Batching Plant with
capacity of 30m³/hr
1 lot=0.5m³
Concreting cont…
Pouring Of Concrete
Checks
Oiling of Shuttering
plates
Cover Blocks
Compaction
150mm and 115 mm
depth is achieved
Proper compaction at
joints
Use of vibrator and
steel rods
Concreting cont…
Curing
Check On Curing in Morning
Marking of Dates of Casting
Opening In Dimension
Room ( L*B)ft²
Air 2.5*1.5
Condition
Window 3.25*5.25
Door 3*8.25
Plastering
Checking Of
Plastering Material
like cement used and
wire mesh
1:4 for 10mm on
ceiling and 1:3 for
12.5 mm on walls
Checking Alignment
with the help of
wooden plank
Electrical Conduiting
Office Work
Checking Of Record Maintenance of
Cement /Steel
Filling of records of scheduled and actual
date of casting
Mix Design
Calculation of Quantities Used
Basic Design of Building using Staad Pro
Problems Faced And Solutions
Offered
Location Of Beam Near Mess Area :
Structural Engineer And Architect
Consulted
Safety Precautions/ Child Labor: Not
Allowed To Work
Problems with Mix Design / Curing /
Shuttering : Reported and there after had
continuous checks
Thank You
Engineers … are not superhuman. They make
mistakes in their assumptions, in their
calculations, in their conclusions. That they
make mistakes is forgivable; that they catch
them is imperative. Thus it is the essence of
modern engineering not only to be able to check
one’s own work but also to have one’s work
checked and to be able to check the work of
others.
- Henry Petroski