CAT CASES Syndicate 4 - Rev01
CAT CASES Syndicate 4 - Rev01
K
C (7)
(20)
N
Finish
(4)
E F G L M
(30) (14) (14) (14) (10)
Project duration
• Based on the CPM, the longest path duration is 86 days. So, this
represents the Critical Path (minimum time for this project to be
completed)
• Project duration = 86 days
Path Duration (days)
A-H-I-J-K-N 61
B-H-I-J-K-N 66
C-H-I-J-K-N 66
D-J-K-N 53
E-J-K-N 61
E-F-G-L-M-N 86
Legend
0 21
D Early start Early finish
(21) Activity
0 15 54
33 name
A
(15) (days)
25 40 Late start Late finish
20 27 27 34 34 55
0 20 H I J
Start B
(7) (7) (21)
(20)
40 47 47 54 54 75
20 40
55 62
0 20 K
C (7)
(20) 75 82
20 40
82 86
N
Finish
(4)
82 86
0 30 30 44 44 58 58 72 72 82
E F G L M
(30) (14) (14) (14) (10)
0 30 30 44 44 58 58 72 72 82
Start & Finish dates for activities on the critical path
The following activities are on the critical path and therefore the
Start & Finish dates are fixed and cannot be delayed, otherwise the
full project will be delayed