SOLAR POWER

PROJECT IMPLEMENTATION
1
SOLAR PROJECT - SYNOPSIS

2
POLICY OVERVIEW:
Clause Details
Time span of the policy 2015-2020
Categories of projects
Category 1 Projects set up for sale to Telangana DISCOMs or third party users
Category 2 Captive/Group Captive projects
Category 3 Solar Rooftop Projects – Grid connected and Off-grid
Category 4 Projects set up in solar parks
Single Window Clearance @ Rs.10K/MW max of Rs. 2 L/project. Mechanism will be handled
Single Window Clearance by TS – iPASS.

NA Conversion Deemed conversion to NA on payment of 10% of the basic value of the land.
T&D Charges Waiver Waived for only Captive Users within the state.
Banking Energy 100% banking adjusted @2% of energy delivered. Unutilized energy purchased @ APPC tariff.
Electricity Duty Waived for sale to DISCOM/Third Party/Captive Use
Cross Subsidy Surcharge 100% exemption for five years since CoD
Grid Evacuation Developer's responsibility to get PE and Supervision charges waved.
Gram Panchayat fee INR 25K/acre to be paid to Gram Panchayat as development charges for the land acquisition.
VAT Exemption 100% refund of VAT/SGST for all inputs required for solar power plants for a period of 5 yrs
Stamp Duty Exemption 100% exemption from payment of Stamp Duty for purchase of land for SPPs
PCB Clearance SPPs being a part of green energy will be given clearance with in a week by TSPCB.
Factories Act SPPs will be registered as factories and the process shall be completed within a week.
3
REGULATORY : OPEN ACCESS PRICE REALIZATION
TELANGANA
S.No Description Working FY:18-19
Captive 3rd Party Sale
1 HT Cat - II (D): 6.15 6.15
2 TOD Charges Adjusted 6.48 6.48
SLDC Annual Fee /MW/Yr 4214.27 4214.27
3 SLDC Operating Fee/MW/Mnth 2342.73 2342.73
SLDC Per Unit Charge 0.013 0.013
4 Transmission Loss (%) 3.95 3.95
5 Wheeling Loss (%) 3.99 3.99
6 Loss in (Rs./Unit) 0.40 0.40
Transmission Charges/KW/Mnth 94.44 94.44
7
Transmission per unit Charge 0.52 0.52
Wheeling Charges/KW/Mnth 19.95 19.95
8
Wheeling per unit Charge 0.11 0.11
9 CSS 1.46
10 Addl. CSS 0.52
11 Net Open Access Charges 1.05 3.03
12 Net Cost of Power 5.30 6.76 4
STATUTORY APPROVALS:
PRE CONSTRUCTION

5
PROJECT SITE IDENTIFICATION:

Obtain suitable land parcel and take necessary consent from la

6
PROJECT DEVELOPMENT: SALE TO DISCOM

Statutory

Statutory

7
Sale to Discom

8
PROJECT DEVELOPMENT:

Land Revenue
Acquisition
Land

9
SINGLE WINDOW MECHANISM FOR SOLAR POWER PROJECTS:

Single point contact


for all clearances

Pre conditions to apply for TS iPASS


1. Technical Feasibility for PE in case Captive sale.
2. PPA signing in case DISCOM/3rd party sale.

I. Solar Policy Cell under TS-iPASS will act as the single window clearance for all approvals.
II. Transaction fee Rs. 10,000/MW with max of Rs. 2 L per project is charged.
III. TS-iPASS will receive necessary application from SPPs & and disburse them to the relevant
departments and process to issue all the required clearance.
IV. TS-iPASS cell to hand over documents specifically related to Energy Department (TSDISCOMS/
TSTRANSCO and CEIG) to SPC/TSSPDCL, for further processing of clearances.

1
PROJECT SITE IDENTIFICATION:
Statutory Requirement