Leader – JEC Joint Venture

利達–怡和機器聯營

Drainage Services Department


Contract No. DC/2009/24

Harbour Area Treatment Scheme Stage 2A –


Upgrading of Preliminary Treatment Works
at Sandy Bay, Wah Fu, Cyberport, Aberdeen
and Ap Lei Chau
Leader – JEC Joint Venture
利達–怡和機器聯營

Site Safety and Environmental


Management Committee
Meeting No.95
(12 July 2019)
Leader – JEC Joint Venture
利達–怡和機器聯營
Major Construction Activities
(June 2019– July 2019)

1. Operation and Maintenance of Treatment Plant (ABN, ALC PTW) - E&M


2. Site Clearance Works (ALC PTW)
3. Sea Wall Construction (ALC PTW)
4. Coring and Grouting Works (ALC PTW)
5. Dismantling Temporary Workshop and Office at ALCMS Sewage Pumping Station
6. FRP working platform installation (ALC PTW) - E&M
7. Filter Replacement Works (ALC PTW) - E&M
8. Clearance of Wet Well (ALC PTW) - E&M
9. Lightning conductor installation works(ALC PTW)- E&M
Leader – JEC Joint Venture
利達–怡和機器聯營
Summary of risk assessment/method statement/safe working procedure
RA No Activities Location of Risk Safe work ICE Rev
PTW Assessment procedures required no
RA/291 H2S removal Efficiency Test and All PTW 19/09/2016 No No 0
commissioning Test of DOU

RA/308 Road works All PTW 16/03/2017 No No 0

RA/309 Verification of Flume Channel Sandy Bay 16/03/2017 No No 0


Flow Instrument (E&M)

RA/319 Equipment installation in Inlet Aberdeen 10/08/2017 No No 1


chamber (E&M)

RA/330 Installation of New Deodorization Ap Lei 10/11/2017 No NO 0


Chau

RA/331 Installation of E&M facilities Cyberport 20/11/2017 Yes NO 0


RA/332 Excavation for roadworks, soft Aberdeen 28/11/2017 No No 0
landscape works and storm
drains under the preserved tree

RA/334 Installation of Outdoor Lighting Aberdeen 04/12/2017 No No 0

RA/336 Re-adjustment of flume channel Aberdeen 13/12/2017 No No 0


flow instrument
Leader – JEC Joint Venture
利達–怡和機器聯營
Summary of risk assessment/method statement/safe working procedure
RA No Activities Location of Risk Safe work ICE Rev
PTW Assessment procedures required no
RA/339 Minor repair and Repainting of Aberdeen 02/02/2018 No No 0
existing Boundary Walls
RA340 Demolition and construction of north Aberdeen 01/02/2018 No No 0
boundary wall
RA342 Construction of New Run-In and Aberdeen 12/03/2018 No No 0
Installation of sliding gate
RA343 Soft Landscaping works in ABN-6 Aberdeen 12/03/2018 No No 0
Portion
RA344 Diving Survey at ALC PTW Ap Lei Chau 24/03/2018 No No 1

RA345 E&M Installation of overflow sensor Sandy Bay 16/06/2018 No No 0


at overflow chamber
RA346 Dismantling site office at Sai Ying Sai Ying 29/03/2018 No No 0
Pun Pun
RA347 Construction of Staircase1 Ap Lei Chau 11/04/2018 No No 0

RA348 Reinstatement Works to the Damaged Ap Lei Chau 15/05/2018 No No 0


Seawall and associated works
RA/349 Malfunction CCTV Replacement at Cyberport 29/05/2018 No No 0
Cyberport PTW
Leader – JEC Joint Venture
利達–怡和機器聯營
Summary of risk assessment/method statement/safe working procedure
RA No Activities Location of Risk Safe work ICE Rev
PTW Assessment procedures required no
RA/350 Maintenance of screw conveyors Wah Fu 29/05/2018 No No 0
liners and spiral at Wah Fu PTW

RA/351 Defect rectification at Sandy Bay Sandy Bay 29/05/2018 No No 0


PTW

RA/352 Defect rectification at Cyberport PTW Cyberport 29/05/2018 No No 0

RA/353 Defect rectification outstanding and Ap Lei Chau 13/06/2018 No No 0


additional works for Civil works
RA/354 Polyurethane Injection Method to Aberdeen 20/06/2018 No No 0
Seal Water Leaks for RM1
Connection Wall in Existing Inlet
Pumping Station in Aberdeen
RA/355 E&M defects rectification and Wah Fu 26/6/2018 No No 0
overhaul work
RA/357 Method Statement and Dissembling Wah Fu 31/7/2018 No No 0
of Ventilation Fan For Inspection and
Maintenance at Wah Fu PTW
RA/358 Dismantling temporary compartment ALC 9-8-2018 No No 0
Leader – JEC Joint Venture
利達–怡和機器聯營
Summary of risk assessment/method statement/safe working procedure
RA No Activities Location of Risk Safe work ICE Rev
PTW Assessment procedures required no
RA/359 Method Statement for Installation of Cyberport 9/8/2018 No No 0
Carbon Box on Existing Biotrickling
Filter at Cyberport PTW
RA/360 Method Statement for Installation of Sandy Bay 9/8/2018 No No 0
Carbon Box on Existing Biotrickling
Filter at Sandy Bay PTW
RA/361 Demolishing work for the Tiled Ap Lei Chau 19/9/2018 No No 0
Workshop Building at ALC PTW
RA/362 Production video by Drone All PTW 29/9/2018 No No 0

RA/363 Installation of Movable Ultrasonic Cyberport 26-9-2018 No No 0


Sensor Support
RA/364 Method Statement For Installation of Wah Fu 15/10/2018 No No 0
Carbon Box on Existing Biobriskling
Filter at Wah Fu PTW
RA/365 Dismantling Exiting Site Office at ALC 24/10/2018 No No 0
ALC PTW
RA/366 Re-adjustment of Flume Channel ALC 7/11/2018 No No 0
Flow Instrument
RA/367 Inspection Pit for Existing DN 600 ABN 15/11/2018 No No 0
Outfall Pipe
Leader – JEC Joint Venture
利達–怡和機器聯營
Summary of risk assessment/method statement/safe working procedure
RA No Activities Location of Risk Safe work ICE Rev
PTW Assessment procedures required no
RA/359 Method Statement for Installation of Cyberport 9/8/2018 No No 0
Carbon Box on Existing Biotrickling
Filter at Cyberport PTW
RA368 Construction Works of Stormwater ABN 17/12/2018 No No 0
Outfall at ABN PTW

RA368 Marine Ground Investigation Works ALC 18/12/2018 No No 0


at ALC PTW

RA369 Land Ground Investigation Works at ALC 20/12/2018 No No 0


ALC PTW

RA370 Method Statement for Site Clearance ALC 21/01/2019 No No 0


Works for the Damaged Seawall after
Typhoon "Mangkhut" at ALC PTW
RA371 Method Statement for Emergency ALC 21/01/2019 No No 0
Grouting for Undermined Structures
after Typhoon " Mangkhut" at ALC
PTW
Leader – JEC Joint Venture
利達–怡和機器聯營
Summary of risk assessment/method statement/safe working procedure
RA No Activities Location of Risk Safe work ICE Rev
PTW Assessment procedures required no
RA/372 Method Statement for Diving Survey ALC 20/02/2019 No No 0
at ALC PTW

RA373 Method Statement for Installation ALC 10/04/2019 No No 1


Works of Temporary Floating
Breakwater at ALC PTW

RA374 Method Statement for Seawall ALC 01-04-2019 No No 0


Reinstatement Works at ALC PTW

RA375 Method Statement for installation of ALC 26-04-2019 No No 0


additional FRP working platform in
effluent pumping station at Ap Lei
Chau PTW
RA376 Method Statement for Dismantling ALC 19-06-2019 No No 0
Temporary Workshop and Office at
ALCMS Sewage Pumping Station
Leader – JEC Joint Venture
利達–怡和機器聯營
The High Risk Activities in coming 4 weeks
Major concern in safety Planned safety and environmental control Result of the planned control
and environment

Access to works area •Specific design to metal scaffold, access ladder and • Proper access tower and specific
steps for works area design working platform was erected.
• Materials were removed from the
access.
Objective falling from •Flashing and audio warning system develop during the • Banksmen operated the system during
height lifting operation using by the banksmen so as to arouse lifting operation.
workers’ attention working under the dry well and wet • The tag line was applied.
well • Loose materials were put into the
material skip during lifting operation.
• Safety net was applied to the surface
of the scaffold.
Working at height •Close monitor the performance of the erection of metal • Proper working platforms were erected
scaffold according to the ICE design and statutory for the worker
requirements. • Adequate number of independent
•Provision of additional independent lifeline lifelines were provided to the workers
• Keep monitoring the situation of
wearing safety harness and ensuring
to attach the independent lifeline.
• Proper safe access was provided.
Leader – JEC Joint Venture
利達–怡和機器聯營
The High Risk Activities in coming 4 weeks
Major concern in safety Planned safety and environmental control Result of the planned control
and environment

• Working over or • Safety training ,tool box talk and briefing to all the • Appointed competent person monitor
nearby the water workers before working the working procedure during work
• Permit to work system for working over or nearby the • All safety rescue equipment
water maintained in valid condition
• All safety rescue equipment standby • Prior inspection was taken and
• Provided safety access embarking or disembarking achieved satisfactory level
• Prohibit working outside of guardrail • All procedure, notice of appointments
• Implement “Blue Card System” for workers and in/house rule had been displayed.
• Regular drill for the worker • Emergency drill will hold regularly.
• Loadshifting • Fence off and warning signs to separate worker • The moving area was fenced off.
machinery / Crane/ access from the loadshifting machinery operation area • The mirror and the reversing warning
Lifting e.g. backhoe, lifting crane devices already installed on the
vehicle.
• All LA/LG hold valid statutory
certificate
• Confined Space • Comply with the cop of confined space • Planning and design of the confined
space work at this moment

• Heatstroke/ heat • To provide sufficient drinking • Sufficient drinking was provided


stress • To provide break time for workers • Break time was arranged
• To provide rest area with shelter • Rest area with shelter was in use
• To provide souvenir to workers • Souvenir prepared to workers
Summary of Design and As-built / Loading Leader – JEC Joint Venture
Certificates for Temporary Works 利達–怡和機器聯營

As-built / Loading
Design Certificate
Certificate
ALC ELS for Rising Main F1110/D/391 ELS for Rising Main F1110/ 02/03/ PTW-
PTW no.2 at ALC PTW no.2 at ALC PTW C/255 2018 S/CGS/I
CE/3630
ALC Typical Falsework and F1110/D/40 Typical Falsework and F1110/ 10/04/ PTW-
PTW Formwork for 4 Formwork for C/256 2018 S/CGS/I
staircase 1(Stage 1) staircase 1 CE/3988
(Stage 1)
ALC Typical Falsework and F1110/D/40 Typical Falsework and F1110/ 17/04/ PTW-
PTW Formwork for 4 Formwork for C/257 2018 S/CGS/I
staircase 1(Stage 2) staircase 1 CE/3988
(Stage 2)
ALC Typical Falsework and F1110/D/40 Typical Falsework and F1110/ 24/04/ PTW-
PTW Formwork for 4 Formwork for C/258 2018 S/CGS/I
staircase 1(Stage 3) staircase 1 CE/3988
(Stage 3)
ALC Working Platform at F1110/D/219 Working Platform at F1110/ 10/05/ PTW-
PTW Grip Trap Area at ALC Grip Trap Area at ALC C/259 2018 S/CGS/I
PTW PTW CE/2026
ALC Working Platform at F1110/D/219 Working Platform at F1110/ 10/05/ PTW-
PTW +3.70 Mpd Floor at +3.70 Mpd Floor at C/260 2018 S/CGS/I
ALC PTW ALC PTW CE/2026

ALC Working Platform F1110/D/219 Working Platform F1110/ 10/05/ PTW-


PTW along GL.7 and GL.1 along GL.7 and GL.1 C/261 2018 S/CGS/I
at ALC PTW at ALC PTW CE/2026
Leader – JEC Joint Venture
利達–怡和機器聯營

Safety and Environmental


Training
Leader – JEC Joint Venture
利達–怡和機器聯營
Training Program for the Coming Two Month (July 2019 – August 2019 )
July 2019 Aug 2019
Safety
Electrical Safety (Safety requirement of the protection of U/G Cables) Electrical Safety (Safety requirement of Electrical wiring)
Temporary Works Safety (Safe work on the loading platform) Temporary Works Safety (Safe work procedure for erection of scaffold)
Safety of Wood working Machinery Safety of falling objective
Housekeeping on site Safety of lifting appliance

Electrical Safety (Safety requirement of Electrical Hand Held Tools) Electrical Safety (Safety requirement of Distribution Board)
Temporary Works Safety (Safety requirement for metal scaffold) Temporary Works Safety (Safety consideration in design criteria of metal
Material storage and stacking scaffold)
Lifting Appliance safety Working at height
Manual Handling Safety
Electrical Safety (Safety requirement of PPE for Electrical Works)
Temporary Works Safety (Planking requirement on walkway and working Electrical Safety (Safety requirement of Generator)
platform) Temporary Works Safety (Safety requirement for the tailor-made product of
Safe use of ladder scaffold)
Confined Space Safety Lifting Gear Safety
Gas Welding Safety
Electrical Safety (Safety requirement of the protection of O/H Cables)
Temporary Works Safety (Safety requirement for the ELS system of Electrical Safety (Safety requirement of Electrical Plugs and Sockets)
excavation) Temporary Works Safety (Safety requirement for the proprietary product of
The use of Personal Protective Equipment scaffold )
Site Traffic Safety Safe use of abrasive wheel
Arc Welding Safety
Environmental
Temporary drainage system, Environmental
Noise control measures Trees Protection
Dust control measures Environmental Noise
Site cleaning Treatment of waste water
Odour Control
Leader – JEC Joint Venture
利達–怡和機器聯營

Training Summary (June 2019)


No. of Attendees

A. Site Safety Cycle and HIA (for contracts with site safety Total: 340 people
cycle)
B. Tool Box Talk Total: 360 people

C. Induction & Refresher Training Total: 3 people


Leader – JEC Joint Venture
利達–怡和機器聯營

Accident / Dangerous Occurrence / Near Miss


Summary and Emergency Preparedness
Leader – JEC Joint Venture
利達–怡和機器聯營
Reportable accident / Non-reportable accident / Dangerous
occurrence / Near miss / Incident Summary
•There was NO accident (Reportable / Non-reportable) in this
reporting period.
•The cumulative number of reportable accident is One since work
commencement.
•Cumulative accident rate 0.007 per 1000 workers (Target: Below
0.8)
•Cumulative Freq. rate 0.048 per 100,000 hours(Target: Below
0.25)
Month Non- Reportable Dangerous Near Miss Incident
reportable Accident Occurrence
Accident
Up to Last Nil Nil Nil Nil Nil
Month
(May. 19)
This Month Nil Nil Nil Nil Nil
(June. 19)
Leader – JEC Joint Venture
Emergency Drill Summary 利達–怡和機器聯營

Planned Month / Date Type of Drill Status


February 2015 Fell from height Rescue Drill Done on 11 Feb 15

April 2015 Chemical spillage drill Done on 16 Apr 15

Jul/Aug 2015 Fire Drill Done on 29 Jul 15 / 30 Jul 15 / 3 Aug 15 / 2 Sep

Oct 2015 Confined Space Rescue Drill Done on 22 Oct 15

Dec 2015 Fire Drill Done on 9 Dec 15 / 10 Dec 15 / 11 Dec 15

Jan 2016 Chemical spillage drill Done on 4 Feb 16

Mar 2016 Confined Space Rescue and Fire Done on 16 Mar 16


Drill
Jun 2016 Electrocution Drill Done on 29 June 16

Sep 2016 Fire Drill Done on 09 Sep 16

Oct 2016 Fire Drill ABN: Done on 07 Oct 16


CPT: Done on 18 Oct 16
Dec 2016 Fire Drill CPT: Done on 29 Dec 16

Jan 2017 Fire Drill ALC: Done on 24 Jan 17

Feb 2017 Fire Drill ABN: Done on 9 Feb 17


Leader – JEC Joint Venture
Emergency Drill Summary 利達–怡和機器聯營

Planned Month / Date Type of Drill Status


Apr 2017 Confined Space Rescue Drill ABN: Done on 27 Apr 17

June 2017 Fire Drill ABN: Done on 29 Jun 17

August 2017 Heat Stoke Drill ALC: Done on 09 Aug 17

November 2017 Fire drill ALC: Done on 30 Nov17

February 2018 Confined rescue drill ABN: Done on 28 Feb 18

May 2018 Heat stroke ALC: Done on 29 May 18

August 2018 Flooding ALC: Done on 27 Aug 18

October 2018 Electrocution Drill ABN: Done on 19 Oct 18

November 2018 (Additional) Fire Drill ALC: Done on 11 Nov 18

December 2018 Falling From Height Drill ABN: Done on 21 Dec 18

February 2019 Fire Drill ALC: Done on 21 Feb 19

April 2019 Electrocution Drill ALC: Done on 11 Apr 19

June 2019 Heat stroke Drill ALC: Done on 27 June 19

Marine Rescue - Person overboard ALC: Done on 19 June 19


Drill
Leader – JEC Joint Venture
利達–怡和機器聯營

Plant and Equipment


Inventory of Lifting Appliance Updated (08 July 2019) Leader – JEC Joint Venture
利達–怡和機器聯營
Radius SWL
Year of Expiry dates of statutory forms
Serial QPME ID Plant (M) (tonne) Certificat Date
Owner Type Model Manufactu Date in
number Code number Form Form Form 4 Form 5 e number out
re
2 3
Kin Excavator SK70SR- YT05- NA NA NA NA 19/82019 19/82019 NA 0.6T 084455- 20/8/20 Off Site
Shing 15760 2018 18
2

廣聯機 Excavator SK200-8 YN12- NA NA NA NA 11/11/2019 11/11/2019 NA 1.4T 11836- 06-03- On Site
械貿易 65608 2018 2019
有限公

廣聯機 Excavator SK200-8 YN12- NA NA NA NA 06/03/2020 06/03/2020 NA 1.4T 03485- 30-03- Off Site
械貿易 65607 2019 2019
有限公

廣聯機 Excavator SK350LC-8 YC11- NA NA NA NA 09/05/2020 09/05/2020 NA 2.8T 050880- 17-04- On Site
械貿易 06630 2019 2019
有限公

Inventory of Lifting Appliance Updated (08 July 2019) Leader – JEC Joint Venture
Marine 利達–怡和機器聯營
QPME Serial number Plant Year of Expiry dates of statutory forms Radi SWL
ID Code number Manufacture Form1 Winches, Pulley Blocks us (tons)
Derricks and their (Form4) (M)
Certificate
Owner Type Model accessory gear Date in Date out
number
(Form2)

Will Pak Derrick NA NA NA NA NA 06-03-2020 07-03-2023 NA NA 40T LA/19/0022 15-03-2019 Still On


Site
Will Pak Pulley block NA NA G60 NA NA 06-03-2020 NA 07-03-2023 NA 150T LA/19/0022b 15-03-2019 Still On
LA/19/0022c Site
Will Pak Pulley block NA NA G4 NA NA 06-03-2020 NA 07-03-2023 NA 90T LA/19/0022b 15-03-2019 Still On
LA/19/0022c Site
Will Pak Pulley block NA NA G61 NA NA 06-03-2020 NA 07-03-2023 NA 35T LA/19/0022b 15-03-2019 Still On
LA/19/0022c Site
Will Pak Pulley block NA NA G26 NA NA 06-03-2020 NA 07-03-2023 NA 35T LA/19/0022b 15-03-2019 Still On
LA/19/0022c Site
Will Pak Pulley block NA NA G5,10,56 NA NA 06-03-2020 NA 07-03-2023 NA 25T LA/19/0022b 15-03-2019 Still On
LA/19/0022c Site
Will Pak Pulley block NA NA G1,9,23,27,29, NA NA 06-03-2020 NA 07-03-2023 NA 15T LA/19/0022b 15-03-2019 Still On
30,39,40,50- LA/19/0022c Site
55

Will Pak Derrick NA NA NA NA NA 06-01-2020 06-01-2021 NA NA 35° 80T M17003- 09-04- On Site
35°(Top hoist) F2A 2019
40T
35° (Top hoist
side eyes)
80T
Inventory of Lifting Gear updated (08 July 2019) Leader – JEC Joint Venture
利達–怡和機器聯營
Expiry date of statutory forms
Owner Owner’s mark Type SWL(T) Certificate number
Form 6 Form 7

LJJV RW29 Metal Container 3T CT/2035/19 Nil 18-09-2019

LJJV G279 Steel Waste Skip 3T CT/2032/19 Nil 18-09-2019


LJJV CS90 Concrete Skip 2.4T CT/2028/19 Nil 18-09-2019
LJJV K1788 Metal Cage 2T CT/2033/19 Nil 18-09-2019

LJJV J87 Mild Steel Water Tank 1.5T CT/2029/19 Nil 18-09-2019

LJJV M38 Metal Container 1.5T CT/2034/19 Nil 18-09-2019

LJJV MC46 Man Cage 0.2T CT/2031/19 Nil 18-09-2019

LJJV TK88 Water Tank 2T CT/2030/19 Nil 18-09-2019

LJJV K1 Lifting Bracket 1000Kg 190130N-015 Nil 29/7/2019


(JEC) EMSD Reg.
No.: HEL725
LJJV K2 Lifting Bracket 1000Kg 190130N-016 Nil 29/7/2019
(JEC) EMSD Reg.
No.: HEL726
Inventory of Lifting Gear updated (08 July 2019) Leader – JEC Joint Venture
利達–怡和機器聯營
Marine
Expiry date of statutory forms
Owner Owner’s mark Type SWL Certificate number
Form 1 Form 5 Form6
Will Pak G28,60 High Tensile Steel Dee Shackles 55T LA/19/0022b 07-03-2020 07-03-2023 NA
LA/19/0022c
Will Pak G2,3,11,14,17,18,24,2 High Tensile Steel Dee Shackles 35T LA/19/0022b 07-03-2020 07-03-2023 NA
LA/19/0022c
5,
41-45
Will Pak G6-8,12,13,15,19,20- High Tensile Steel Dee Shackles 25T LA/19/0022b 07-03-2020 07-03-2023 NA
LA/19/0022c
22,
31-38,46-49,51,59
Will Pak G16 High Tensile Steel Dee Shackles 17T LA/19/0022b 07-03-2020 07-03-2023 NA
LA/19/0022c
Will Pak G58 Steel Port Guy Link Chain 10T LA/19/0022b 07-03-2020 07-03-2023 NA
LA/19/0022c
Will Pak NA Wire rope dia. 26mm(6x31 IWRC) 9.5T LA/19/0022d 07-06-2019 NA 07-03-2023

Will Pak S1 Six Sheave Steel Block 120T M17003-F4A 06-01-2020 10-01-2021 NA
Will Pak S22 Five Sheave Steel Block 90T M17003-F4A 06-01-2020 10-01-2021 NA
Will Pak S6 Double sheave block with hook 60T M17003-F4A 06-01-2020 10-01-2021 NA
Will Pak S2, S8 Three Sheave Steel Block 35T M17003-F4A 06-01-2020 10-01-2021 NA
Will Pak S4, S17, S57 Double sheave steel block 25T M17003-F4B 06-01-2020 10-01-2021 NA
Will Pak S1, S25-27 Single sheave block 15T M17003-F4B 06-01-2020 10-01-2021 NA
Will Pak S2, S7, S10, S20, S21, Single sheave block 15T M17003-F4B 06-01-2020 10-01-2021 NA
S23, S28-31
Will Pak S16, S49 High tensile steel ‘’dee’’ shackles 55T M17003-F5A 06-01-2020 10-01-2021 NA
Will Pak S13, S14,S18, S19, S36- High tensile steel ‘’dee’’ shackles 35T M17003-F5A 06-01-2020 10-01-2021 NA
42, S50
Will Pak S15 Steel port guy link chain 15T M17003-F5A 06-01-2020 10-01-2021 NA
Will Pak NA Steel wire rope 28mm 10.5T M17003-F6A 10-07-2019 NA NA
Will Pak V90813 Lifting eyes for vibratory pile driver 20T M17108-F5B NA 06-09-2021 NA
Leader – JEC Joint Venture
利達–怡和機器聯營
Safety and Environmental Personnel
Safety: Safety Officer : Ng Tsz Lun, Eyck
Safety Supervisor : Chan Cho Cheuk(Civil) / Cheng Che Fai (Civil)/ Chan Kok Yiu
(E&M)
First Aider : Ng Tsz Lun, Eyck
Safety Representative : Tsui Chi Kin / Chan Shu Hang /
: Cheung Sai Man / Chan Kwong Fook (LJJV)
: Lo Yuet Man (Asia Landscape)
: Wong Kam Shan (Hing Wah)
: Lai Ho Sang (Wing Cheong)
: Yip Chi Ming (Smart)
: Yung Lit Yan (Kin Shing)
: Wong Ding Keung (Advance Drill)
: Tao Tat Lai (Living Green)
: Wong Man Shing (Man Shing-E&M)
: Wong Koon Kong (Holihock-E&M)
: Lo Pui Kee(Hang Lee)
: Pang Po On(New Inway)
: Chan Ming Chung (Shing Tat)
: Sze Kam Sze (Shun Tai)
: Jam Wing Kun(Tug Link)
: Ching Hon Nam(Chung Yuk)
Environmental:
1. Environmental Engineer: Stephen Leung
2. Environmental Officer: Edmond Wong
Summary Of Competent Person
Leader – JEC Joint Venture
利達–怡和機器聯營
Competent person/Operator Name Relevant certificate Certificate number Certificate
expiry date
EOT crane operator Lee Chi Kwong Cert issued by CICTA B117422 16/09/2019

CP for noise Lau Luen Tak Registered Safety Officer NA NA


assessment Charles
Ng Tsz Lun Registered Safety Officer
Cert issued by OSHC
CP for scaffold Lee Wai Man Cert issued by CITA NA NA
inspection Chan Ho Man Cert issued by CICTA NA NA
Ngan Sui Ping Cert issued by CICTA NA NA
Li Chi Ming Cert issued by CITA B097295 NA
Chan Cho Cheuk Cert issued by CICTA S-MYF-1410-00029 NA

CP for excavation Cheng Che Fai Over 5 years relevant NA NA


inspection Lee Kam Lung experience in Civil Works NA NA
So Po NA NA

CP for manual handling Lau Luen Tak Registered Safety Officer NA NA


Charles
Tool box talk trainer(s) Lau Luen Tak Occupational Safety and TTT13JS0231606 NA
Charles Health Trainer
So Po Safety Training Technique M-STT-0411-00163 NA
Lee Kam Lung Safety Training Technique M-STT-0811-00113 NA
Cheng Che Fai Safety Training Technique M-STT-1307-00049 NA
Ng Tsz Lun Safety Training Technique
Leader – JEC Joint Venture
Summary of Certified Worker (DSD) 利達–怡和機器聯營
Certified Worker’s Start Working Relevant certificate Expiry Date of Certified Expiry Date of Certified MC/ SC
Name Month Worker Worker engaged in DSD’s
works
Arranged to renew the
Lee Chi Kong 11 Nov 12 CICTA 18/04/2020 LJJV
certificate
Chan Cho Cheuk TBC HKSTA &CICTA 04/01/2020 03/05/2021 LJJV

Yeung Fai TBC HKSTA &CICTA 28/03/2020 06/05/2020 LJJV


TBC Arranged to renew the
Wong Chi Keung CICTA 01/05/2020 LJJV
certificate
Xu Lun TBC HKHR & CICTA 18/04/2019 04/05/2020 LJJV
Arranged to renew the
Chan Lun Ming 8 Feb 10 HKSTA 07/06/2020 LJJV
certificate
Lam Po Lai TBC CIC 14/11/2021 LJJV
Leader – JEC Joint Venture
Summary of Competent Person (DSD) 利達–怡和機器聯營
Competent Person’s Start Working Relevant certificate Expiry Date of Competent Expiry Date of Competent MC/ SC
Name Month Person Person engaged in DSD’s
works
Arranged to renew the
Tse Kwok Keung 19 Dec 13 CICTA 19/04/2020 LJJV
certificate
Arranged to renew the
Chan Lun Ming 8 Feb 10 CICTA 07/06/2020 LJJV
certificate
Lee Kam Lung 5 Jan 06 CICTA 11/08/2020 21/10/2018 LJJV
Chan Cho Cheuk TBC HKSTA 04/01/2020 25/04/2021 LJJV
Chi Kin Ming CIC 01/09/2019 01/09/2019 LJJV
Leader – JEC Joint Venture
利達–怡和機器聯營

Registration of NRMM updated (08 July 2019)


Machine Trade
No PTW Machine Type Name of Subcontractor Model Serial No. Engine Make & Model Remark
Name

SK70S YT05-
1 ABN Excavator Kin Shing Kobelco
R-2 15760
SDG10 1533B10 EPD-A-000797-
2 ABN Generator Leader Airman Isuzu & 4HK1
0 278 2018
SK200- YN12- Hino & J05E- EPD-A-002422-
3 ALC Excavator Will Pak Kobelco
8 65608 TA 2018
SK350L YC11- Hino & J08E- EPD-A-001375-
4 ALC Excavator Will Pak Kobelco
C-8 06630 TM 2018
Air PDS17 53- EPD-EE-011408-
5 ALC Will Pak Airman Isuzu & C240
compressor 5S 4042334 2015
Air PDS17 53- EPD-EE-011267-
6 ALC Will Pak Airman Isuzu & C240
compressor 5S 4042004 2015
Leader – JEC Joint Venture
利達–怡和機器聯營

• The SSCM No. 94 was held on 20 June 2019


• The SECM No. 94 was held on 20 June 2019

• The Weekly Coordination Safety and Environmental


Meetings were held on 10,17, 21 & 26 June
Sub-Contractor’s Safety Performance Information Sheet for Leader – JEC Joint Venture
June 2019 利達–怡和機器聯營
• Excellent = 2.5 (3
Items /Sub-contractors Will Pak Asia Landscape M&M 保信 additional provisions
above Legislative
1. Housekeeping 1 1 1 1 Requirements)
2. Working at Height 1 1.5 1 1 • Very Good = 2 (2
additional provisions
3. Prevention of Falling above Legislative
1.5 1.5 1.5 1.5
Object Requirements)
• Good = 1.5 (1 additional
4. Personal Protective provision above the
1.5 1.5 1.5 1.5
Equipment Legislative
Requirements)
5.Construction Plant and • Satisfactory = 1 (Meet
1.5 NA 1.5 1.5
Equipment Legislative
Requirements’)
6. Safe Use of Lifting
1.5 NA 1.5 1.5 • Poor = 0
Appliance
• Remark: Overall
7. Safe Use of Lifting performance would be
1.5 NA 1.5 1.5
gear rated Very Poor if the
8. Machine guarding NA NA NA NA ultimate score <0.9,
Poor between 1-1.4;
9. Use of Electrical Hand Satisfactory between
1.5 NA 1.5 1.5
Held Tools 1.5-1.9; Good between
10. Use of Electricity 1.5 NA 1.5 1.5 2-2.4; Very Good
between 2.5; Excellent.
11. Gas welding and
1.5 NA 1.5 1.5 [If any item got the rating
flame cutting
in poor, an enhancement
12. Fire Safety 1.5 1.5 1.5 1.5 training on relevant topic
Average Rating 1.41 1.42 1.41 1.41 will be provided to the
above subcontractor.
(Satisfactory) (Satisfactory) (Satisfactory) (Satisfactory)
Additional Environmental Measures (June 2019)
Site Management --- Mosquito Control

‘‘

Application of the pesticide


Application of the pesticide
for killing mosquito and
for killing mosquito and
larvae.
larvae.
Additional Environmental Measures (June 2019)
Site Management --- Mosquito Control

Applicationofofthe
Application thepesticide
pesticide
forkilling
for killingmosquito
mosquitoand
and
larvae.
larvae.
Additional Safety Measures (April 2019)
Prevention of Heatstroke/ Heat Stress


Additional Safety Measures (May 2019)
Prevention of Heatstroke/ Heat Stress


Additional Safety Measures (May 2019)
Prevention of Heatstroke/ Heat Stress


Proposed Additional Safety Measures (June 2019)
Prevention of Heatstroke/ Heat Stress

Safety Promotion Day for


Prevention of Heatstroke/ Heat Stress
1 Date: 29 June 2019
Planned Schedule:
2.1 10:00am – 10:30am Heat Stroke Drill
2.2 & 15:00pm – 15:35pm Tool Box Talk & Safety Quiz
2.3
2.4 Fruits, Drinks and Souvenir
delivery
2.5 15:35pm – 15:40pm ‘ Group Photo Taking
Proposed Additional Safety Measures (June 2019)
Prevention of Heatstroke/ Heat Stress


Proposed Additional Safety Measures (June 2019)
Prevention of Heatstroke/ Heat Stress


Proposed Additional Safety Measures (June 2019)
Prevention of Heatstroke/ Heat Stress


Proposed Additional Safety Measures (June 2019)
Prevention of Heatstroke/ Heat Stress


Proposed Additional Safety Measures (June 2019)
Prevention of Heatstroke/ Heat Stress


Proposed Additional Safety Measures (June 2019)
Prevention of Heatstroke/ Heat Stress


Proposed Additional Safety Measures (June 2019)
Prevention of Heatstroke/ Heat Stress


Proposed Additional Safety Measures (June 2019)
Prevention of Heatstroke/ Heat Stress


Proposed Additional Safety Measures (June 2019)
Prevention of Heatstroke/ Heat Stress


Proposed Additional Safety Measures (June 2019)
Prevention of Heatstroke/ Heat Stress


Proposed Additional Safety Measures (June 2019)
Prevention of Heatstroke/ Heat Stress


Proposed Additional Safety Measures (June 2019)
Prevention of Heatstroke/ Heat Stress


Proposed Additional Safety Measures (June 2019)
Prevention of Heatstroke/ Heat Stress


Contract No. DC/2009/24
Upgrading of Preliminary Treatment Works at
Sandy Bay. Cybersport, Wah Fu, Aberdeen and
AP Lei Chau
Pre-SSEMC meeting
Inspection on
14 June 2019
Contract No. DC/2009/24
Upgrading of Preliminary Treatment Works at
Sandy Bay. Cybersport, Wah Fu, Aberdeen and
AP Lei Chau
Safety Advice
Safety Advice (1) :
Excavator that required to work nearby water should be securely positioned to prevent
over turning into sea, properly demarcation to the safe working zone should be
established.

Major Safety Concern – Overturning of excavator

Before – Excavator found working After – Excavator was restricted to


too close to the edge of sea. work away from the water to prevent
overturning.

Location – AP Lei Chau PTW Site


Safety Advice (2) :
Housekeeping should be kept in good condition at all time.

Major Safety Concern – Housekeeping

Before – Poor housekeeping should be After – Housekeeping was improved


enhanced.

Location – AP Lei Chau PTW Site


Safety Advice (3) :
Fencing should be provided for storing of materials at height to prevent falling for a
person, necessary fall preventive measures should be implemented to prevent falling
hazards.

Major Safety Concern – Person falling from height.

Before – Area at height should be After – Independent life line and fall arrestor
provided with secured fencing and fall was provided for workers. They were
preventive measures should be instructed to wear safety harness and attach
implemented for workers. it on the fall arrestor.
Location – AP Lei Chau PTW Site
Safety Advice (4) :
Supports to temporary barriers should be properly maintained and damages should be
rectified or replaced promptly to ensure secured support to barriers.

Major Safety Concern – Safe of place of works.

Before – Supports to barriers should be After – The deformed support was


properly maintained, any damages should
removed
be rectified promptly.

Location – AP Lei Chau PTW Site


Safety Advice (5) :
Area with risk of persons falling from height should be provided with proper
and secured barriers and fencing to prevent person falling from height.

Major Safety Concern – Fall prevention.

Before – Area with risk of falling from After – The risk of falling person was
height should be properly fenced off with removed.
secured barriers.

Location – AP Lei Chau PTW Site


Safety Advice (6) :
Metal tube ends with risk of tripping over hazards should be properly covered and
protected to prevent injuries to workers.

Major Safety Concern – Injuries to workers.

Before – Metal tube with risk of tripping After – The risk of tripping over
over hazards should be properly
managed to prevent injuries to workers.
hazard was removed.

Location – AP Lei Chau PTW Site


Safety Advice (7) :
Steps should be taken to ensure all access and egress to works area are in good
condition and appropriate warning should be provided to prevent tripping over hazards
to workers.

Major Safety Concern – Tripping over hazards.

Before – Insufficient fixing of access to After – Access was modified.


prevent tripping over hazards to workers.

Location – AP Lei Chau PTW Site


Safety Advice (8) :
Barriers for edge of falls should be properly fixed to prevent falling hazards to workers.
Metal barriers should be appropriately fixed for secure fixing of fencing purpose.
Sufficient width of access should be provided.

Major Safety Concern – Falling hazards.

Before – Metal tube for barriers to After – The protruded parts of


prevent falls found not properly fixed.
barriers were protected and the
And sufficient width should be provided.
access was extended.

Location – AP Lei Chau PTW Site


Safety Advice (9) :
Sharp edges with risk of tripping over hazards should be properly fixed with warning to
prevent injuries to workers.

Major Safety Concern – Tripping over hazards

Before – Sharp edge with risk of tripping After – Sand bags were placed to
over hazards should be properly fixed. prevent tripping over hazard.

Location – AP Lei Chau PTW Site


Safety Advice (10) :
Smoking should be prohibited from al construction site area.

Major Safety Concern – Power to prohibit smoking from site.

Before – Smoking should be prohibited After – The workplace was tidied and
from all works area within construction LJJV enhanced the supervision for
site. Cigarettes ends found at various
the prohibition of smoking.
places on site.

Location – AP Lei Chau PTW Site


Contract No. DC/2009/24
Upgrading of Preliminary Treatment Works at
Sandy Bay. Cybersport, Wah Fu, Aberdeen and
Ap Lei Chau
Environmental Advice
Environmental Advice (1) :
Muddy water should be properly managed to prevent wash off from shore into open
sea, steps should be taken to minimize contamination to the environment.

Major Environmental Concern : Sea pollution

Before – Muddy water should be properly After – Silt curtain was installed
managed to prevent pollution to sea.
properly.

Location – AP Lei Chau PTW Site


Leader – JEC Joint Venture
利達–怡和機器聯營
Advice, Warning Letter, Directive, Inspection Report from Labour Department (LD)
/ Marine Department (MD) / Fire Service Department (FSD) / Environmental
Protection Department (EPD) / Food and Environmental Hygiene Department
(FEHD)

• No government parties visited to our construction site from last SSEMC meeting until
present day except:

Date & Time Authority Details


03-07-2019 MD General Inspection
10:20am-10:50am
04-07-2019 MD General Inspection
10:50am-12:00pm
05-07-2019 MD General Inspection
10:30am-11:20am
06-07-2019 MD General Inspection
10:45am-11:20am

Safety and Environmental related Complaint and Enquiry


• No complaint received until present day.
Leader – JEC Joint Venture
利達–怡和機器聯營

Summary of Environmental Permit / License


Type of License Location of PTW Reference No Date Issue Validity
Water Discharge License Cyberport WT00021529-2015 04/05/2015 31/05/2020

Wah Fu WT00016837-2013 09/08/2013 End of contract


Aberdeen WT00027953-2017 01/06/2017 31/03/2022

Ap Lei Chau WT00027342-2017 02/03/2017 31/03/2022

Chemical Waste Producer Sandy Bay 5218-171-L2783-01 14/12/2011 End of contract


Cyberport 5218-171-L2783-02 30/12/2011 End of contract
Wah Fu 5218-171-L2783-05 30/12/2011 End of contract
Aberdeen 5218-171-L2783-04 30/12/2011 End of contract
Ap Lei Chau 5218-171-L2783-03 30/12/2011 End of contract

Waste Disposal Project : DC/2009/24 Billing Account No: 08/09/2011 NA


7013634
Leader – JEC Joint Venture
利達–怡和機器聯營

Summary of Environmental Permit / License


Type of License Location of PTW Reference No Date Issue Validity

Disposal of Special Waste Ap Lei Chau 14759 24/11/2018 23/11/2019


at Landfills Admission Ticket

Disposal of Special Waste Aberdeen 14760 24/11/2018 23/11/2019


at Landfills Admission Ticket