內容
Page_2
一。Overview of Automation levels (1)
PLANT LEVEL
A1
一。Overview of Automation levels (2)
Lập kế hoạch sản
xuất,phối hợp sản
xuất,quản lý chất lượng
Level 3
Thiết bị trường:
cảm biến,cơ cấu
chấp hành Level 0
A2
二。BOF level 2 automation system
B1
1. Main functions of BOF level 2 system (1)
• Level 2 system receives the order information and manages them.
According them, BOF procedures will be done:
BOF procedures
1 Scrap and hot metal are charged into BOF
2 Oxygen blowing/bottom gas blowing starts
3 Flux addition is performed
4 [O], [C] and temperature are measured by sub-lance
5 Coolant addition is performed if necessary
6 Blowing end
7 [O], [C] and temperature are measured by sub-lance
8 Ferro-alloy addition is performed
9 Tapping start
10 Transfer the ladle to next step
B2
1. Main functions of BOF level 2 system (2)
• Managing order data
– Level 2 system receives order data from level 3 system and
manages them. The order instruction has information to
decide the operation. It (order instruction) includes the
tapping schedule, production instruction, production
standard.
– After receiving order instruction, level 2 system calculates
the hot metal demand weight and scrap weight. And save
them.
B3
1. Main functions of BOF level 2 system (3)
Sample of order instruction:
Item Remark Item Remark
Order No. Process instruction: Use/no use
Mechanical stirring instruction for each
Steel grade BOF No. for de-P sub-system
Steel making request 9999/99/99 99:99 BOF No. for de-C
date LF
RH
Order weight Total weight (ton) Scrap code
Slab size (Thickness 99999x9999 Scrap ratio
and width)
Planed CC No. Mill range: Target after de-P
[C],[P],target%,…
Planed CC casting Mill range: [C], [P], Target after de-C
sequence No. [Mn] target %,…
B4
1. Main functions of BOF level 2 system (4)
Scrap code:
This is the code for blending scrap
Scrap type:
Chemical composition values for each scrap type
Blending rate of each scrap type for each scrap code
• Calculation of ferro-alloy to be charged
– Level 2 system will calculate the suggested ferro-alloy to
be charged (by brand)
– Data storage, data gathering, reports and operation
guidance is the auxiliary function of level 2 system.
B5
1. Main functions of BOF level 2 system (5)
• Weighing/managing main material
– Level 2 system retrieves a scrap instruction from production
instruction and after operator’s confirmation next heat and
modifying scrap weight data (if necessary), send the data to level
1 system. Level 2 system receives weighing result from level 1
system and sends it to level 3 system.
Confirmation Send scrap
Confirmation of scrap code weight
of next heat and scrap instruction to
weight level 1 system
B6
1. Main functions of BOF level 2 system (6)
• BOF control
– Based on level 3 system instruction, level 2 system will activate BOF
models and calculating preset data (oxygen amount, lance height,
bottom blowing rate, flux amount, in-blow sublance timing) and design
blowing pattern and flux charging pattern and send them to level 1
system.
– Level 2 system receives result data (flux amount/ferro-alloy
amount/sampling and temperature etc) and manages them and sends
them to level 3 system.
– After in-blow sublance, level 2 system will activate dynamic control
model and re-calculating total oxygen amount and coolant amount, and
sends them to level 1 system.
– At end-point sublance, level 2 system will estimate end-point value of
[Mn], [P] in steel. And according to target composition, ferro-alloy
amount will be decided.
B7
1. Main functions of BOF level 2 system (7)
• BOF control
B8
1. Main functions of BOF level 2 system (8)
• BOF control
B9
2. BOF blowing control system (1)
B10
2. BOF blowing control system (2)
SPCO Proposal
B11
2. BOF blowing control system (3)
B12
2. BOF blowing control system (4)
2.1. Blowing pattern designing function
2.1.1. Static control model
• Static control model will be activated at the time of declaration of heat.
-Burnt lime amount
- Hot metal data
(weight, temperature,
- Fluorspar amount
composition),
- Scrap data (weight Input STATIC Output - Iron ore amount
and composition), CONTROL
- Operation standard, MODEL - Total oxygen amount
- End-point target
([C], temperature) and
- Timing of in-blow
- Previous heat data
sublance
• The feedback parameter, maximum decarburization rate and total heat loss, are
calculated by using actual heat results after blowing and are adjusted for next heat.
B13
2. BOF blowing control system (5)
B14
2. BOF blowing control system (6)
2.2. Blowing pattern adjusting function
The blowing pattern adjusting function will be done by manual
intervention model.
Manual intervention model
• During blowing, the manual intervention model will be activated if the
operator request for adjustment of blowing pattern.
• The contents of manual intervention model are:
– Judgment of blowing pattern adjustment
– Determine the revised blowing pattern
– Actual adjustment by DCS and PLC
• The oxygen flow rate pattern, lance height pattern, flux charging pattern
and bottom gas kind and flow rate pattern maybe adjusted when the
manual intervention model is activated.
B15
2. BOF blowing control system (7)
2.3. End-point hitting function
The End-point hitting function will be done by dynamic control
model.
Dynamic control model
• This model is activated at the time of in-blow sublance. It calculates
the coolant amount and the oxygen amount after in-blow sublance.
In-blow sublance Addition oxygen
data amount
([C]% and Input DYNAMIC Output End-point
temperature)
CONTROL temperature
End-point target MODEL Coolant amount
([C]% and
• The feedback parameters, decarbonization transition
temperature)
point and coefficient of temperature rising model, are
calculated by using actual heat results after blowing
and are adjusted for next heat.
B16
2. BOF blowing control system (8)
B17
2. BOF blowing control system (9)
B18
3. Auxiliary functions of BOF automation system (1)
• The auxiliary function of BOF automation system:
- Data storage and reports: The level 2 computer stores and reports
operation result data. (see attachment 1)
- Data gathering: The level 2 computer gathers heat result data and heat
event data for report and operation. (see attachment 2)
- Data setting to level 1 system: (see attachment 3)
- Operation guidance: Various HMI screens will be provided for the
purpose of operation:
To view heat status
To request calculation
To activate model
To request printing reports (see attachment 4)
- Communication with other computer system (see attachment 5)
Database direct access
Message send/receive with TCP-IP socket communication
B19
3. Auxiliary functions of BOF automation system (2)
B21
3. Auxiliary functions of BOF automation system (3)
Attachment 2: Data gathering (1)
B22
3. Auxiliary functions of BOF automation system (4)
B23
3. Auxiliary functions of BOF automation system (5)
Attachment 3: Data setting to level 1 system
B24
3. Auxiliary functions of BOF automation system (6)
Attachment 4: Operation guidance
B25
3. Auxiliary functions of BOF automation system (7)
Attachment 5: Database direct access
B26
3. Auxiliary functions of BOF automation system (8)
Attachment 5: Message send/receive with TCP-IP
socket communication
B27