Professional Documents
Culture Documents
Ias 41 Ias 11
Ias 41 Ias 11
AGRICULTURE
EXAMPLE 12.2: PHYSICAL CHANGE AND PRICE CHANGE
Background
The following example illustrates how to separate physical change and price change. Separating the
change in fair value less estimated point-of-sale costs between the portion attributable to physical
changes and the portion attributable to price changes is encouraged but not required by this standard.
Example
A herd of 10 two-year-old animals was held at January 1, 20X1. One animal 2.5 years of age was
purchased on July 1, 20X1, for $108, and one animal was born on July 1, 20X1. No ani-mals were
sold or disposed of during the period. Per-unit fair values less estimated point-of-sale costs were as
follows:
Animal Details $ $
1 (80 – 72) 8
1 70 237
If the fair value cannot be determined, then the valuation would be determined at cost, less accumulated
depreciation and accumulated impairment losses: $250,000.
However, there are other reliable sources available for the determination of fair value. Such sources should be
used. The mean value of all the available indicators above would be used (in the range of $150,000 to $225,000).
In addition, the farmer would consider the reasons for the differences between the various sources of other
information, prior to arriving at the most reliable estimate of fair value.
In the absence of recent prices, sector benchmarks, and other information, the farmer should calculate the fair
value as comprising the cost price, less impairments, less depreciation— resulting in a valuation of $250,000.
IAS 11
CONSTRUCTION CONTRACT
OBJECTIVE
The primary challenge in accounting for construction contracts is to allocate contract revenue
and costs to the correct accounting periods. The objective of this standard is to give guidance
on the appropriate criteria for recognition of construction contract revenue and costs, with a
focus on the allocation of contract revenue and costs to the accounting periods in which con-
struction work is performed.
Contract revenue is measured at the fair value of the consideration received or receivable. The
measurement of contract revenue is affected by a variety of uncertainties that depend on the
outcome of future events. The estimates often need to be revised as events occur and uncertainties
are resolved. Therefore, the amount of contract revenue may increase or decrease from one period
to the next.
Subsequent Measurement
When the outcome of a construction contract can be reliably estimated, contract revenue and
contract costs should be recognized as revenue and expenses respectively by refer-ence to the
stage of completion of the contract activity at the end of the reporting period.
In the case of a cost-plus contract, the outcome of a construction contract can be estimated
reliably when all the following conditions are satisfied:
• it is probable that the economic benefits associated with the contract will flow to the entity;
and
• the contract costs attributable to the contract, whether or not specifically reimbursable, can be
clearly identified and measured reliably.
When the outcome of a contract cannot be reliably estimated, revenue should be recognized to the
extent that recovery of contract costs is probable. The contract costs should be recognized as an
expense in the period in which they are incurred.
Any expected excess of total contract costs over total contract revenue (expected loss) is
recognized as an expense immediately.
Financial statements and schedules must be produced under the percentage of completion contract method,
showing:
A. the cash flows from the project each year;
B. the profit or loss for the project each year;
C. the Statement of Financial Position each year; and
D. the profit margin, asset turnover, debt to equity, return on assets, return on equity, and the current ratio
Explanation
A. The cash flow is simply the difference between the cash received and paid every year as
given in the problem:
Material 1,400
Labor 800
Operating overhead 150
Subcontractors 180
2. Current estimate of total contract costs indicates the following:
3. During the current financial year the customer requested a variation to the original contract,
and it was agreed that the contract price would be increased by $900,000. The total
estimated cost of this extra work is $750,000.
4. By the end of 20X6, certificates issued by quantity surveyors indicated a 25 percent stage
of completion.
Determine the profit to date, based on:
■ Option 1—contract costs in proportion to estimated contract costs
■ Option 2—percentage of the work certified
EXPLANATION
Contract profit recognized for the year ending December 31, 20X6, is as
follows:
d.Stage of completion Option 1 Option 2
Based on contract costs in proportion to
estimated total contract costs: