Professional Documents
Culture Documents
Case Study Design 3
Case Study Design 3
• Malankara Plantations Limited is spread across a very large land area with its
Administrative Office in Kottayam, Kerala.
• The Office Complex is an 86-year old heritage building, mainly built of wood with
tiled roof on wooden rafters.
• The old structure is historically registered under classification “Heritage” in India
and its preservation is mandated by the state.
Project Yield
Earlier a 30 kVA Diesel Generator set was used for backup power supply for
approximately 5 hours in a day. It was operational for 260 days a year consuming
approx. 7800 litres of diesel.
The project benefited from carbon financing, meeting the energy security needs,
and preventing the release of greenhouse gases into the atmosphere by reducing
DG operations to almost nil.
It reduced up to 47 tons of carbon emissions per year, saving an estimated 97% in
diesel fuel consumption.
Project Challenges
TS came across challenges in the way of successful execution of the project. A few
of challenges being faced by TS during the process of project implementation were
High energy consumption, Space constrain, Keeping the heritage structure intact
and Local weather conditions.
By its long experience and expertise TS overcame all the challenges by pioneering
the most appropriate designs and engineering soluitons as required for the project.
As a first step, TS conducted a detailed Energy Audit and addressed the cause of
high energy consumption by replacing inefficient devices and incorporating
energy management measures.
TS was thus able to reduce the existing energy consumption by 50% which, in
turn, helped reduce the array capacity.
Local Weather Condition
To address the cloudy and rainy days, TS adopted the technology of A-si thin film
modules which perform even under low light and cloudy conditions.
It helped ensure the required generation of power even during the heavily cloudy
and rainy days.
The array capacity was designed for the worst days of the year considering the 15-
year climatic data of the region.
Heritage Structure
Being a heritage building, the structure posed a challenge as it could not be
altered in any way.
To overcome this barrier, TS designed and engineered a Space Frame
structure to mount the solar modules 9 Meters above the ground (Courtyard).
The space frame structure supported by four columns each occupying merely
2 sqm of foot print at the corners allowed access and usage of the courtyard
as before.
The structure provided shade to the Courtyard as well as a Rain Water
Harvesting system for the building.