Project Management A
Project Management A
Definition :
Project – is a temporary endeavor
undertaking to create unique product,
service or result.
2
Phases of Project Management :
Initiating
Planning
Executing
Closing
3
Name of Project :
4
INITIATION PHASE :
1. Request for Proposal:
6
3. Project Objective
To comply with the ISO (International Standard
Organization) compliant requirements directed
by the BFAD (Bureau of Foods and Drugs), a
national agency regulating hygiene processes
and safety practices in consumption-based
products by using food grade and anti-microbial
material and equipment in their manufacturing
plants.
7
4. Project Description
Uptown Industrial Sales, Inc. will replace the
dilapidated epoxy painted floor in the refinery’s
mixing room by supplying and applying a 4 mm
thick, Koncreflex MD Polyurethane material,
cream color. This job will be accomplished within
the agreed ten (10) working days period. The
material and workmanship shall bear the warranty
of five (5) years from the date of acceptance by
the end user of the project.
8
5. Milestone
Project Stage Target Completion
9
6. Key Stakeholders
Name Designation Role in project
1. Engr. Luz Head – Refinery She will initiate project request and will
Fernandez Department, First officially accept the project completion.
Farmers
2. Engr. Christian OIC – Purchasing He will invite suppliers/contractors to
Aguirre Dept., First Farmers quote and will issue purchase order.
3. Rose Ramos Executive Secretary- She will process the billing documents.
Operations, First
Farmers
4. Lydia Dayo Cashier- First Farmers Will release payment check to supplier.
5. Fidel Caraig Product Manager – He will quote the Koncreflex MD PU offer
Uptown to First Farmers.
6. Aron Leonoras Project Manager – Will oversee the implementation and
Uptown management of the project.
7. Al Beduya Project Foreman – Will lead the application and completion
Uptown of the project.
10
7. Contracting Parties
13
5. Personnel Needed:
a. Project Manager: Engr. Aron Leonoras
b. Project Foreman: Al Beduya
c. Coating Specialist: Ariel Aragon
d. Helpers: Twelve,12 contractual
personnel, to be hired at site
14
6. Materials and equipment needed:
a. 370 Sets, Koncreflex MD-Cream Color, Packaging
20 kg/set
b. 30 Sets, Koncreflex Primer, Packaging 10 kg/set
c. 30 Bags, Silica Sand 40/80, Packaging 25 kg/bag
d. 10 unit, Vacuum Cleaner, Industrial type
e. 10 unit, Electric stirrer
f. 10 units, Electric grinder, 4 “diameter
g. 10 pcs, Pointed-tip Hammer
h. 10 pcs, Leveling Pad
i. 10 Set, Extension Cord, 20 feet long
j. 10 pcs, Empty Plastic Pail/Container, 20 liter cap.
15
7. Project Schedules: Please see Gantt
Chart in Appendix E.
16
EXECUTING PHASE:
1. The Project Manager will coordinate working
schedules and protocols with the Purchasing
Department for the clearances of personnel who
will work in the area, and with the end user who
will provide the needs of electricity and water.
18
4. The helpers will provide the general labor
as maybe directed by the Project
Foreman and Coating Specialist.
19
MONITORING AND CONTROL
1. Measuring the ongoing project: Planned Activity
vs. Actual: Please see Appendix F.
2. Critical Path Method (CPM) of the project:
Please see Appendix G.
Should there be any deviations in the actual
progress of works vis-à-vis the planned schedules,
the Project Manager or Project Foreman may call
for an overtime work in order to expedite the
delayed activities
20
CLOSING PHASE
1. Contract Closure:
a. Customer’s checking of applied area in terms
of workmanship and conformity to required
specifications. In accepting the outcome of
the project, authorized end user will
acknowledge the Delivery Receipt (DR) and
Sales Invoice (SI) of Uptown Industrial
Sales, Incorporated.
21
b. Demobilization of Uptown Personnel,
including securing of gate pass
clearance for withdrawal of tools and
equipment from mill premises.
22
2. Project Closure:
a. Uptown, thru its Project Manager,
Engr. Aron Leonoras will compen-
sate the labor services of its hired
contractual workers.
b. Project Manager, Engr. Aron
Leonoras will submit billing state-
ment to First Farmers in order to process its
seventy percent (70%) balance payment.
c. Project Manager, Engr. Aron Leonoras will
collect the First Farmers’ payment check.
23
End of Report