Professional Documents
Culture Documents
New Lifting
New Lifting
1
First Time submission
Introduction
Scope
Glossary of Terms
Reference Documents
Rules for Safe Lifting Operations
Responsibilities, Competence and Training of Personnel Involved in Lifting Operations
Responsibilities
Person Responsible for Lifting Operations
Competent Person
Crane Operator
Competence and Training
Planning of Crane Operations
Define the Lift
Planning
Lift Categorisation
Risk Assessment
Lift Plan
Assessment of a Lifting Operation
9/21/2011 2
Tandem Lift Additional Factors of Safety
Crane Siting Considerations and Assessment
Crane Daily Checks and Inspections
Crane Access Ladders, Walkways and Hatches
Housekeeping
Pre-start Checks
Start Up of Prime Mover
Pre-Operations Checks and Function Tests
Safety Equipment
Checks to be Carried Out During Operation of the Crane
Execution
Communication of Lift Plan
Communication
Hand Signals
Radio Communication
Controlling Access to the Lift Area
Conducting the Lifting Operation
Moving the Load
9/21/2011 3
Load Handling
General Instructions for Crane Operators
The Crane Operator Must NOT
The Crane Operator MUST
Banksman and Load Handler (Slinger) Procedures
General Instructions for Banksmen
Reacting to Changing Circumstances
Typical Adverse Weather Guidelines
Annexure
Lift Plan
Cage types & weight
Organization chart
Load chart
Risk assessment
Emergency Evacuation Plan & Emergency response team
Test certificates
Operator certificates
Medical Certificate s
9/21/2011 4
Second Time Submission for same Activity ( Due to Change in Crane or Any other
etc)
Purpose
Scope of Work
Reference
Definition & Abbreviations
Rules for lifting operation
Materials
Responsibility & Authority
Design Calculation
Design and load calculation for lifting Frame
Construction Sequence
Lift Plan
Cage types & weight
Organization chart
Load chart
Risk assessment
Emergency Evacuation Plan & Emergency response team
Test certificates
Operator certificates
Medical Certificate s
5
Rules for Safe Lifting Operations
6
Types of
Cranes
Mobile
Hydraulic
Overhead
Gantry
Tower
Planning Before Start-
•
Up
Level the crane and ensure support surface is firm and
able to support the load
• Contact power line owners and determine precautions.
Know the location and voltage of overhead power lines.
• Know the basic crane capacities, limitations, and job site
restrictions, such as the location of power lines, unstable
soil, or high winds.
• Make other personnel aware of hoisting activities.
• Barricade areas within swing radius.
• Ensure proper maintenance and inspections.
• Determine safe areas to store materials and place
machinery.
Competent Person
• Leverage
• Stability
• Structural Integrity
Load Example – 30 ton
crane
• Will lift 27000 kgs at 10 feet from the center pin
of the crane
• Based on level surface, no wind, and outriggers
fully extended
• At 25 feet from the center pin with an 80 foot
boom, the capacity is only 6,800 Kgs
• At 74 feet from the center pin, the capacity is
only 2000 kgs
Load
s
Responsibilities, Competence and Training of
Personnel Involved in Lifting Operations
Crane Operator
Competence and Training
9/21/2011 20
Planning of Crane Operations
9/21/2011 21
Site Conditions
◦ Access/egress routes
◦ Inclines/gradients
◦ Location of adjacent buildings
◦ Location of overhead lines
◦ Ground firm enough to support crane and
outriggers
◦ No voids exist e.g. manholes, drains etc
9/21/2011 22
Planning the lift
◦ Area around lift is demarcated
◦ Load is within SWL of crane
◦ Location of lifting points ensure load is level
◦ Lifting points are strong enough to take the load
◦ There are no persons under the load AT ANY TIME
9/21/2011 23
Lifting Accessories
9/21/2011 24
Safe Use of Ropes & Wires
Must be in good condition before use I.e. not frayed
or corroded
Ropes & wires must be protected from sharp edges of
load by use of packing
No knots or hitches in slings or lifting ropes
Never drag ropes or wires over the ground
When using more than one sling, ensure they are of
the same material
9/21/2011 25
Safe Use of Chains
9/21/2011 26
Safe Use of Lifting Accessories
9/21/2011 27
Storage of Ropes, Wires, Chains & Lifting
Accessories
9/21/2011 28
Storage of Ropes, Wires, Chains & Lifting Accessories
9/21/2011 29
Risk Assessment
9/21/2011 30
Conflicting tasks in area;
Environmental conditions, including weather and
permissible limits;
Lighting in the pick-up and laydown areas;
Proximity hazards, obstructions, path of load;
Working under suspended loads;
Access and emergency escape routes for the Lifting
Equipment Operator and load handlers
Experience, competence and training of personnel;
Number of people required for task;
Pre-Use Inspection of equipment by the Operator;
Visibility of the load by the Operator and / or person
guiding the load;
Communication between all personnel taking part in the
lifting operation
9/21/2011 31
Lift Plan
9/21/2011 32
Assessment of a Lifting Operation
9/21/2011 33
Verify that the crane and other lifting equipment being used
is certified for use;
Verify that all those involved in the lifting operation have
participated in a toolbox talk at which the risks and hazards
and control measures were clearly described;
Verify that a visual inspection of all lifting equipment and
accessories has been completed;
Confirm the Banksman / Signaller’s level of competence;
Confirm the Load Handlers’ levels of competence;
Test that the communication methodology is suitable and
understood by all personnel involved in the lifting
operation;
Test the emergency response and contingency procedures;
Test the safety culture – will people ‘STOP’ the job if there
is an unsafe act or omission?
9/21/2011 34
Tandem Lift Additional Factors of Safety
9/21/2011 35
Crane Siting Considerations and Assessment
9/21/2011 36
Execution
9/21/2011 37
Moving the Load
Load Handling
Weather Conditions
Tag Lines
Lifting Over People
Structures Close to Lifting
Crane Radius
9/21/2011 38
Weight Calculation
Example Cage –Type
S.No Description Weight Remarks
9/21/2011 39
S.No Description Weight Lifting Total Wt Type of Remarks
Of part Access(Mt (MT) Lift
(Mt) )
9/21/2011 40
Multi-Crane Lifts
41
Multi-Crane Lifts
May be preferred when:
42
Multi-Crane Lifts
Things to Consider:
43
Multi-Crane Lifts
Two Cranes –
Horizontal Loads
The two cranes used on
this concrete beam
allowed the beam to be
landed first on one end
The two cranes were
probably on the jobsite,
resulting in cost savings
44
Multi-Crane Lifts
Two Cranes –
Horizontal
Loads
Here two matched
cranes lift an
asymmetrical load
Careful CG
calculation and load
distribution is very
important
45
Multi-Crane Lifts
Two Cranes –
Horizontal Loads
Two unequal cranes
lifting a process module
This lift was carefully
planned, allowing the
larger crane to lift at a
greater radius and
allowing for a
proportional lift
46
Multi-Crane
Lifts
Two Cranes –
Horizontal Loads
47
Multi-Crane Lifts
Two Cranes –
Horizontal Loads
This is an excellent
use of two cranes
The duct needs to be
lifted at an angle for
correct placement
With a single crane
lift, the rigging must
be selected to
provide the correct
angle
48
Multi-Crane Lifts
49
Multi-Crane Lifts
50
Multi-Crane Lifts
Two Cranes:
Tailing
Not all vertical
loads require
tailing with a
second crane
53
Multi-Crane Lifts
Tailing to the
Vertical
Not all up
endings require
a tail crane
54
Multi-Crane Lifts
Multiple Cranes:
Tailing
• Overturns
• Falls
• Mechanical failures
How Do Accidents
Occur?
• Instability – unsecured load, load capacity
exceeded, or ground not level or too soft
• Lack of training
• Operators
• Persons at Crane
Site
Improper Load
Stay clear
Stay clear
from power
lines at least
10 feet
power lines
at least 10
feet
Hand Signals
An illustration of
the signals must
be posted at the
job site
Swing Radius
Broken Window
Ladder
Inspection of the
hoisting machinery
must be made by a
competent person
The employer must
maintain a record of
these inspections Crane wasn’t inspected
and tipped over
What to Inspect
Correct air pressure and no
leaks
Tires properly inflated
Clearance for tail swing
Wire rope wear
Physical damage to crane
Loose or missing hardware,
nuts, or bolts
Fluid leaks
Remove From Service
Crushed Rope
Broken Strands
Worn Part
Summary