DPR For Widening of Bridge Over Narmada Canal On NH-8C
DPR For Widening of Bridge Over Narmada Canal On NH-8C
Scope of Work:-
To carry out a Detailed Project Report, approval of proposed alignment and GAD from Irrigation Dept/SSNNL, for
widening of existing 4 lane bridge & its approaches to 6 lane bridge and approaches.
Page 1
Location Map
Page 2
Details of Existing Bridge
Page 3
Current Status of Project
Initial scope was to widen from 4 lane to 6 lanes by adding 1-1 lane on both side of
existing bridge.
Thereafter, Additional 4-lane bridge with footpath proposal was finalized. Span
arrangement of 3x21.6m+2x38m with 17.275 m overall width has been proposed.
In the Meeting held at MoRTH on 04/07/2017 it was suggested to consider Longer
span in the central Canal,
This being a revision in scope the Consultant, submitted a revised offer of
Consultancy on 14/07/2017,
Based on negotiations, a final revised offer submitted by Consultant on 30/08/2017,
CE (NH) has written a letter to CE (Bridge) MoRTH for approval of additional fees on
08/09/2017,
Meanwhile block cost for Larger Spans (1x38m+1x64.8m+1x38m) submitted by
Consultant on 10/11/2017.
In the last meeting held at MoRTH on 16/08/2018, it was informed that Alignment
Option recommended was found in order and Span arrangement will be finalised
separately.
Page 4
29/06/2017 (Consultant is open to modification as per width of 19.250m. To clear any ambiguity, the sketch is appended as below.
Further we believe, that the breakup of width indicated is as per IRC:05, 2015 & not as per IRC:84-2015)
Alignment Plan showing Long Span
Page 6
Cross Section of Existing & Proposed Bridge with Existing ROW
Page 7
Cost Comparison of Various Options
Sr. Description Amount (in Rs.) Amount (in Rs.) Long Amount (in Rs.) Long Amount (in Rs.) Long
N Submitted with span Option span Option span Option
o. old proposal* (Bow string Steel (Composite Steel (Steel Through Truss
3 x 21.6 + 2x38m Girder) Girder) Girder)
with 19.25 m 1x38m+64.8m+1x38 1x38m+64.8m+1x38m 1x38m+64.8m+1x38m
width m with 19.25 m with 19.25 m width with 19.25 m width
width
1 2 3 3 4 5
1 Cost of Canal 948,64,000 203,280,000 184,307,200 196,504,000
Bridge
Page 8
Land Acquisition & Forest Clearance
(a) Stretches under DPR where Land Acquisition (Adequate ROW) and Forest Clearance Not Required
Sr. Chainage Tentative Length of Existing Right Of Way
Name of Work Name of Consultant Remarks
No. From To Road (In Km.) (In Mt.)
N/A
Page 9
Land Acquisition & Forest Clearance
Page 10