22.4.18 Monitoring and Control-Omm

You might also like

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 27

Centre for

Continuing Education

Session conducted by

Dr Rajesh Gupta
B Tech, PGDOM, PhD

Area of interest
• Operations management
• Project Management
• Quantitative Techniques
• Quality Management
UPES – The Nation Builders University

PROJECT MANAGEMENT AND CONTRACT


ADMINISTRATION

22nd April, 2018

Centre for
Continuing Education
UPES – The Nation Builders University
Alpha solutions private limited – client’s concern about project progress
Alpha solutions private limited was established in 2012. The company started undertaking
projects for developing internet security software from corporates. By the year 2016, the
company was already doing business with more than 30 corporates and had developed the
reputation of its expertise in the field. The company was headed by Mr. Mehra as the Managing
Director and Anil assisted him as chief project manager. Anil was responsible to allot the new
projects to one of eight project managers working for the company.
Anuj was the project manager for a project with Mohit Industries, one of the most important
clients of Alpha Solutions. Project started on January 1, 2016 and was expected to be handed
over to the client by 30th June, 2016. Anil received a call from CEO of Mohit industries on 24th
March, expressing his concerns over progress of the project. Just two days back, Anuj had also
requested Anil to talk about some unavoidable constraints that cropped up unexpectedly and
also to request for an enhancement of project budget.
Anil discussed the matter with Mr Mehra and both agreed to have a joint meeting with MD of
client’s company and Anuj to resolve the issue. Anil instructed Anuj to come to the MD’s office on
26th March at 10 PM with a report of projects progress. Anuj immediately started collecting
relevant data for the meeting. He instructed all his team to provide data of work completion and
expenses made so far.
On the night of 25th March, Anuj was busy with the data collected and provided by his team
members and to prepare a project progress report.

Centre for
Continuing Education
UPES – The Nation Builders University
The summarized data is as below.

Time Budgeted cost Scheduled completion Actual Completion status Actual cost
Activity Code
(Weeks) (Thousands) status on 26th March on 26th March incurred

Study of Client’s processes A 2 20 100% 100% 24

Security audit of the system B 4 25 100% 100% 22

Development of design for security


C 7 10 100% 90% 10
software

Procurement of hardware D 3 70 100% 70% 55

Trial run of the software E 2 25 50% 0% -

Modification and validation F 5 40 0% 0% -

Software testing G 3 15 0% 0% -

Installation H 4 12 0% 0% -

Training on software I 4 22 0% 0% -

Centre for
Continuing Education
UPES – The Nation Builders University

PROJECT MONITORING AND CONTROL

Centre for
Continuing Education
UPES – The Nation Builders University

Project control process

Process of comparing actual performance against plan to


identify deviations, evaluate possible alternative courses of
action and take appropriate corrective action

Centre for
Continuing Education
UPES – The Nation Builders University

Project control process Steps

• Setting a baseline plan


• Derived from cost and duration information in WBS
• Measuring progress and performance
• Comparing plan against actuals
• Taking action

Centre for
Continuing Education
UPES – The Nation Builders University

Define project objectives

Develop base plan Develop monitoring plan

Compare performance with


Collect data as per monitoring plan
plan

Identify deviation Establish need for action

Apply action

Verify effectiveness of action


taken

Centre for
Continuing Education
UPES – The Nation Builders University

Resources that need to be controlled include

• Physical resources

• Human resources

• Financial resources

Centre for
Continuing Education
UPES – The Nation Builders University

Earned value

•Comparison of cost incurred for an accurately


identified amount of work with the cost budgeted for
the same amount of work

•Requires a detailed work breakdown structure

Centre for
Continuing Education
UPES – The Nation Builders University

BCWS Budgeted cost of work scheduled

BCWP Budgeted cost of work performed

ACWP Actual cost of work performed

CPI Cost performance index

SPI Schedule performance index

Centre for
Continuing Education
UPES – The Nation Builders University

Cost variance = BCWP – ACWP

Schedule variance = BCWP - BCWS

Centre for
Continuing Education
UPES – The Nation Builders University

Cost performance indicators

CPI = BCWP / ACWP

SPI = BCWP / BCWS

Centre for
Continuing Education
UPES – The Nation Builders University

Index CPI SPI

> 1.00 Under cost Ahead of schedule

= 1.00 On cost On schedule

< 1.00 Over cost Behind schedule

Centre for
Continuing Education
UPES – The Nation Builders University

A project was reviewed during its execution. It was

observed that 50% of work scheduled was completed

against a target of 60% on that day. The cost of project

was Rs 10,000,00/- and was distributed over the project

span uniformly. A total of Rs. 5,50,000/- was already spent

on the project. Calculate CPI and SPI and comment on the

project performance.

Centre for
Continuing Education
UPES – The Nation Builders University

Time Budgeted cost Scheduled completion Actual Completion status Actual cost
Activity Code
(Weeks) (Thousands) status on 26th March on 26th March incurred

Study of Client’s processes A 2 20 100% 100% 24

Security audit of the system B 4 25 100% 100% 22

Development of design for security


C 7 10 100% 90% 10
software

Procurement of hardware D 3 70 100% 70% 55

Trial run of the software E 2 25 50% 0% -

Modification and validation F 5 40 0% 0% -

Software testing G 3 15 0% 0% -

Installation H 4 12 0% 0% -

Training on software I 4 22 0% 0% -

Centre for
Continuing Education
UPES – The Nation Builders University

S CURVE – A TOOL FOR

PROJECT MONITORING AND CONTROL

Centre for
Continuing Education
UPES – The Nation Builders University
S Curve as a tool of project monitoring and control

Actual cost at completion


Cost Over run
Budgeted cost at completion

BCWS

Schedule variance

ACWP

Cost Variance

BCWP Schedule slippage

Centre for
Continuing Education
UPES – The Nation Builders University
CPI < 1 SPI < 1

BCWS

ACWP

BCWP

Centre for
Continuing Education
UPES – The Nation Builders University
CPI < 1 SPI = 1

BCWS

ACWP

BCWP

Centre for
Continuing Education
UPES – The Nation Builders University
CPI = 1 SPI = 1

BCWS

ACWP

BCWP

Centre for
Continuing Education
UPES – The Nation Builders University

Determine
2000
• Budgeted cost of completion
BCWS
• Projected cost of completion
1800
• Projected cost variance
1640 • Scheduled time of
1600
completion
1450 • Projected time of completion
1400
• Projected schedule slippage
ACWP
AFTER 12.5 WEEKS
1200
• CPI
1100
• SPI
1000
• CR
• CV
800
• SV
PROJECTED AT COMPLETION
400
• CPI
• SPI
200 BCWP • CR
• CV
• SV
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

Centre for
Continuing Education
UPES – The Nation Builders University

Activity % Scheduled Completion Budgeted cost % Actual Completion

A 100 2000 100

B 100 3500 90

C 100 1500 90

D 60 3000 35

E 40 1000 0

For the above data, calculate SPI and cost variance of all activities and for
project in totality.

Centre for
Continuing Education
UPES – The Nation Builders University

A project was evaluated at different milestones for performance. The data collected at
different milestones is as under.

If the total budgeted cost for project was Rs 5, 00,000, comment on the performance of
project.

Milestone 1 2 3 4 5

Actual cost incurred 1,02,000 1,65,000 2,75,000 2,98,000 3,79,000

Work completed 20% 35% 54% 60% 75%

Work scheduled 24% 39% 52% 64% 73%

Centre for
Continuing Education
UPES – The Nation Builders University

Milestone 1 2 3 4 5

Actual cost incurred 1,02,000 1,65,000 2,75,000 2,98,000 3,79,000

Work completed 20% 35% 54% 60% 75%

Work scheduled 24% 39% 52% 64% 73%

ACWP 1,02,000 1,65,000 2,75,000 2,98,000 3,79,000

BCWP 1,00,000 1,75,000 2,70,000 3,00,000 3,75,000

BCWS 1,20,000 1,95,000 2,60,000 3,20,000 3,65,000

CPI 0.98 1.06 0.98 1.01 0.99

SPI 0.83 0.90 1.03 0.94 1.03

Centre for
Continuing Education
UPES – The Nation Builders University

TEST YOUR UNDERSTANDING

Centre for
Continuing Education
UPES – The Nation Builders University

10000
80000
ACWP

Cost 6000
BCWS
5000

BCWP

Week
15 22

At 15th week on completion


Question Determine Answer
Question Determine Answer
number
number
1 CPI 4 CPI

2 SPI 5 SPI

6 Cost to complete remaining


3 Critical ratio work after 15th week

Centre for
Continuing Education

You might also like