PROJECT PROGRESS REPORT

Room Cooling
Pristine Energy Transfer Corporation Weekly Report No. 19
Date Cover: December 22, 2018 – December 28, 2018
Production Area
6OO BPM

Machine Room Area

Production Area
6-8 Liters
AREA OF CONCENTRATION

Production Area
6-8 Liters

Production Area
6OO BPM

Machine Room
DUCTING INSTALLED
IN 6OO BPM PRODUCTION AREA
600 BPM
FABRICATED DUCTING IN
6-8 LITERS PRODUCTION AREA
6-8 LITERS
INSTALLED EQUIPMENT
IN MACHINE ROOM MACHINE ROOM AREA
SAFETY REPORT
(Cumulative Progress)
Week Ending: 27 December 2018

SAFETY PERFORMANCE BOARD


TOTAL SAFE MANHOURS 14,307
LOSS TIME ACCIDENT NONE
LAST REPORTED ACCIDENT NONE
TOTAL SAFE MAN DAYS 126 DAYS
ACCOMPLISHMENT REPORT
(Cumulative Progress %)
Week Ending: 20 December 2018
WEEKLY PLAN WEEKLY ACTUAL VARIANCE THIS WEEK
ACCOMPLISHMENT

WEEK 1 4.9% 4.9% 0.0%


WEEK 2 5.8% 5.8% 0.0%
WEEK 3 8.5% 8.5% 0.0%
WEEK 4 10.6% 10.6% 0.0%
WEEK 5 12.5% 12.5% 0.0%
WEEK 6 13.5% 13.5% 0.0.%
WEEK 7 15.3% 15.0% -0.3%

WEEK 8 16.7% 16.0% -0.7%


WEEK 9 18.0% 17.1% -0.9%
WEEK 10 19.4% 18.1% -1.3%
ACCOMPLISHMENT REPORT
(Cumulative Progress %)
Week Ending: 20 December 2018
WEEKLY PLAN WEEKLY ACTUAL VARIANCE THIS WEEK
ACCOMPLISHMENT

WEEK 11 20.9% 24.2% 3.3%


WEEK 12 28.0% 26.3% -1.7%
WEEK 13 40.4% 37.7% -2.7%
WEEK 14 57.0% 56.7% -.3%
WEEK 15 63.8% 68.4% 4.6%
WEEK 16 80.1% 69.1% -11%
WEEK 17 84.6% 72.6% -12%
PROGRESS PHOTOS
Area: 600BPM
Main Activities: Installation of Grilles and Diffuser
Area: Machine Room
Main Activities: Derusting and Painting of Pipe Support
Area: Fabrication Area
Main Activities: Fabrication of Ducting
Area: Machine Room
Main Activities: Moving and Positioning of Chilled Water
Pumps
LOOK AHEAD SCHEDULE FOR NEXT WEEK
Date Cover: 14 December – 20 December 2018

Insulation wrapping of Ducting for 6-8 Liters


Installation of Ducting in 6-8 Liters
Insulation Wrapping of Ducting Joint for 600BPM
Installation of Remaining Ducting Joints in 600BPM
Moving and Positioning of Equipments
S-CURVE
ITEMS/WORKS WITH DELAYS,
CAUSES/REASONS OF DELAYS AND CATCH UP
PLAN

ITEMS WITH DELAYS CAUSES / REASONS OF DELAYS CATCH UP PLAN

1. Installation of Ducting in Late Delivery of Insulations Divert to Other Activities


6-8Liters
2 Piping and Positioning of
Equipments Late Turn-over of Machine Coordination to ABI and BEC
Room

3. Installation of Ducting Joints Late Delivery of Insulations Divert to Other Activities


ISSUES AND CONCERNS
Complete Turn over of Machine Room
THANK YOU!