The document outlines a 3-month production plan and activity plan for Tata Steel. It provides production targets of 43KT in June from seams V and IX, 45KT in July from seams IX and VIII, and 41KT in August from seams IX, VIII, and X. The activity plan details preparations of various seams and panels, extension of overhead arrangements, and maintenance activities to achieve the production targets over June, July, and August.
The document outlines a 3-month production plan and activity plan for Tata Steel. It provides production targets of 43KT in June from seams V and IX, 45KT in July from seams IX and VIII, and 41KT in August from seams IX, VIII, and X. The activity plan details preparations of various seams and panels, extension of overhead arrangements, and maintenance activities to achieve the production targets over June, July, and August.
The document outlines a 3-month production plan and activity plan for Tata Steel. It provides production targets of 43KT in June from seams V and IX, 45KT in July from seams IX and VIII, and 41KT in August from seams IX, VIII, and X. The activity plan details preparations of various seams and panels, extension of overhead arrangements, and maintenance activities to achieve the production targets over June, July, and August.
The document outlines a 3-month production plan and activity plan for Tata Steel. It provides production targets of 43KT in June from seams V and IX, 45KT in July from seams IX and VIII, and 41KT in August from seams IX, VIII, and X. The activity plan details preparations of various seams and panels, extension of overhead arrangements, and maintenance activities to achieve the production targets over June, July, and August.
01.04.19 01.06.19 Panel – A 6.78 LT 5.47 LT Panel – B 0.50 LT 0.50 LT Panel – C 1.36 LT 1.36 LT 3 Month Production Plan
Month Production Remarks
Jun’19 43 KT V Seam – 40KT , IX seam – 3KT Jul’19 45 KT IX Seam – 13 KT, VIII – 32 KT Aug’19 41 KT IX Seam – 5 KT, VIII – 28 KT, X Seam – 8 KT
Activity Plan:
# Activity Timeline
1 i. IX Seam pad preparation at Panel – C. Jun’19
ii. Extension of overhead and power arrangement at Panel – C. iii. Marching of Highwall miner to IX seam Panel – C. 2 i. VIII Seam pad and IX seam preparation at Panel – C. Jul’19 ii. Providing Platform of Hose reel maintenance job (Maint. Job may take up to 7 Days). iii. Thin Cutter Head installation for mining of X Seam Panel – C. iv. X Seam pad preparation at Panel – C. 3 i. VIII Seam preparation for remaining area of Panel – C. Aug’19 ii. VII Seam Pad preparation for Panel – A.