– Formwork costs including labor, equipment, and materials – Cost of reinforcing steel and placement – Concrete materials, equipment, and labor for placing, curing, and finishing – F11-1 Cast in Place • Traditional method – Allows concrete to be formed to site conditions – Used on most construction sites for structural members • Concrete placed in forms to cure • Forms removed after enough strength in concrete to support self and additional construction loads Cast in Place • Walls and wall footings – Need to avoid voids and separation of materials due to large fall • Special care for areas under windows , pipe chases and other formwork installed inside wall forms • Can pump concrete from bottom of form to get rid of voids Cast in Place • Floors and roofs – One way slab – only supported in one direction F 11-3 • Slab and beam • Slab, beam & girder • Outside beam is called spandrel beam • Columns poured before slabs – shrinkage – If poured same time could stress floors and beams due to shrinkage Cast in Place • Floors and roofs – One way slab – only supported in one direction F 11-3 • Slab and beam • Slab, beam & girder • Outside beam is called spandrel beam – Two directional slabs (waffles) provide support in two perpendicular directions – supported by columns Cast in Place • 2 way – Basically joists in both directions • Flat slabs – Supported directly by columns – Uses column capitals to distribute load over larger area – More reinforcement needed to carry loads to columns – F 11-6 Precast concrete • Cast into desired shape at plant and moved to site – Controlled environment -> better finish and quality – All prestressed and pretensioned members are precast – F 11-7, 11-8 Precast concrete • Types – Joists and purlins F 11-7 – Roof and floor panels • Flat 1-4” thick, 15 – 32” wide, 4-10’ long • hollow core 4 – 12” thick, 4-8’ wide, 15 – 50’ long • tee, double tee 4-12’ wide span 12 – 100 feet • channel slabs 2 – 5 ‘ wide, 15-50 ‘ long – F11-8 Precast concrete • Types – Walls • Usually curtain wall construction panels fit between structural components to form wall • But used in tilt up construction – Panels cast horizontally on existing slab and tilted upright – F 11-9 Prestressed Concrete • Initial compression load applied to concrete – Places entire beam in compression • Makes beam stronger since more force is required to induce a tension component • Reduces deflection • F11-10 Prestressed Concrete • 2 ways to do – Pretension – place prestressing material in tension in the form while concrete is poured • Once concrete hardened remove tension • Bond between steel and concrete keeps steel in place – Post tensioning – steel is placed inside a plastic tube during concrete pouring • Upon placement steel is tensioned and the steel is mechanically anchored to the concrete at each end • Load is removed and steel cut flush Architectural Concrete • Appearance effects – Shape, size, texture, and color – F 11-12 & 11-13 Concrete Construction Practices • Transporting and Hauling – Need to avoid segregation of materials in concrete – Wheelbarrows, buggies, chutes, pumps, conveyors, buckets, trucks • Placing and consolidating – Need to make sure form surfaces and bracing is right before placing concrete Placing – Forms must be coated in oil to allow removal – If placing concrete on ground – must moisten ground – If pouring on top of cured concrete must place bonding agent between pours – Shotcrete (gunite) – concrete placed pneumatically – Consolidation – removing air voids • vibration Finishing & Curing • Finishing – bring surface of concrete to its final position and surface texture – Screeding – striking off excess concrete – Floating – smoothes and compacts concrete imbeds aggregates – Troweling – compacts surface F 11-16 – Brooming – surface texture Curing • To get good concrete must cure properly – Moisture and temperature are key – Moisture – wet straw or burlap, curing compounds – Vacuum dewatering – mat placed on concrete • Vacuum applied to mat – takes out excess water • Lower W/C ratio -> denser mix Hot weather Concreting • Curing accelerates when concrete temp above 50 – 60 F – How to lower temp • Use cold water in mix • Cool aggregates before mixing • Use Type IV (low heat cement) • Add a retarder • Decrease max time to discharge to 1 hour Cold weather Concreting • Concrete should not freeze for 1st 24 hours – Min temp for placement is 50F – Use type III (hi early strength) – Use accelerator – Heat water and aggregates before mixing – Use vented heaters to keep concrete warm