Renovation of the

Existing Storm Drainage


System Along the Left
Side of Abanao Street
OBJECTIVES
• To assess the existing drainage system along the left
side of the Abanao Street.
• To propose supplementary designs that will improve
the condition of the existing drainage system.
Project Locale
FINDINGS
• MEASUREMENT OF THE EXISTING INLET AND GUTTERS
Inlets Length Width Height thickness of Steel gratings Width of gutter

1st 80 cm 40 cm 10 cm 2.54 cm diameter 60 cm

2nd 100 cm 45 cm 12 cm 5cm x 1cm 65 cm

3rd 100cm 45 cm 12 cm 5cm x 1cm 65 cm

4th 160 cm 30 cm 12 cm 5cm x 1cm 50 cm

5th 110 cm 70 cm 10 cm 2.54 cm diameter 90 cm

6th 100 cm 40 cm 10 cm 5cm x 1cm 60 cm

7th 100 cm 50 cm 15 cm 5cm x 1cm 70 cm

• SOME GUTTER’S HEIGHT ARE ALMOST LEVELED TO THE HEIGHT OF THE


SIDEWALK
• THERE IS NO INLET FROM THE POLICE STATION TO THE BAGUIO OFFICE,
DISTANCE = 100 METERS.
ANALYSIS
• DESIGN RAINFALL INTENSITY
FROM THE PAG-ASA RAINFALL DATA
I = 4,064 millimeters annually
• CALCULATED NUMBER OF INLETS
ALONG THE LENGTH OF 7TH INLET ; 5 ADDITIONAL INLETS
ALONG THE LENGTH OF 6TH INLET ; 1 ADDITIONAL INLETS
CONCLUSIONS
• THE GUTTER FROM POLICE STATION TO THE BAGUIO OFFICE IS NOT
CAPABLE OF CARRYING THE DESIGN STORM QUANTITY.

• THE EXISTING STORM DRAINAGE SYSTEM HAS INADEQUATE


NUMBER OF INLETS
RECOMMENDATIONS
• ADDITIONAL NUMBER OF INLETS IN THE SAID LOCATIONS OF
LACKING INLETS.
• IMPLEMENT PROPOSED DIAMETERS OF SEWER PIPES
Proposed Design Plan
PERT-CPM
Avtivity
Activity Denotion Predecessor Duration ES EF LS LF FLOAT
Survey of the road
A - 2 days 0 2 0 2 0
Permit Gathering
B A 2 days 2 4 2 4 0
Drilling of the road pavement

C B 5 days 4 9 4 9 0
Excavation of the road pavement

D B 5 days 4 9 1 6 -3
Excavation of the soil above the pipe

E D 5 days 9 14 6 11 -3
Transferring of the Excavated Portions

F E,C 8 days 14 22 11 19 -3
Extruding of the Old Pipes
G F 7 days 22 29 19 26 -3
Purchasing of the RC Pipes

H G 11 days 29 40 26 37 -3
Putting of Subbase course
I G 5 days 29 34 35 40 6
Placing of RC Pipes
J I 8 days 40 48 40 48 0
Connecting the pipes
K J 8 days 48 56 48 56 0
Backfilling of soil
l K 3 days 56 59 56 59 0
Putting of concrete and bituminous
pavement
M L 3 days 59 62 59 62 0