Sewerage System of Abanao Road
Sewerage System of Abanao Road
C B 5 days 4 9 4 9 0
Excavation of the road pavement
D B 5 days 4 9 1 6 -3
Excavation of the soil above the pipe
E D 5 days 9 14 6 11 -3
Transferring of the Excavated Portions
F E,C 8 days 14 22 11 19 -3
Extruding of the Old Pipes
G F 7 days 22 29 19 26 -3
Purchasing of the RC Pipes
H G 11 days 29 40 26 37 -3
Putting of Subbase course
I G 5 days 29 34 35 40 6
Placing of RC Pipes
J I 8 days 40 48 40 48 0
Connecting the pipes
K J 8 days 48 56 48 56 0
Backfilling of soil
l K 3 days 56 59 56 59 0
Putting of concrete and bituminous
pavement
M L 3 days 59 62 59 62 0
PERT-CPM