Professional Documents
Culture Documents
Earned Value Analysis-1
Earned Value Analysis-1
BY: -
Hakeem–Ur–Rehman
IQTM–PU
1
Budget
Variance
C On Critical Path
A
E Schedule
Variance
Behind Ahead
2
EARNED VALUE ANALYSIS
“Earned Value Analysis” is:
• an industry standard way to:
• measure a project’s progress,
• forecast its completion date and final cost, and
• provide schedule and budget variances along the
way.
3
WHAT’S MORE IMPORTANT?
4
EARNED VALUE ANALYSIS
BCWS: “Budgeted Cost of Work Scheduled”
“Also Know as Planned budget value of the work
scheduled (PV).”
5
EARNED VALUE ANALYSIS
ACWP: “Actual Cost of Work Performed”
Actual cost required to complete all or some portion of
the tasks, up to the status date.
6
EARNED VALUE ANALYSIS
BCWP: Budgeted Cost of Work Performed
EV (EARNED VALUE)
7
SOME DERIVED METRICS
SV: Schedule Variance (BCWP-BCWS) = (EV – PV)
A comparison of amount of work performed during a
given period of time to what was scheduled to be
performed.
If it is 0, you are right on schedule.
If it is negative, you are behind schedule.
If it is positive, you area ahead of schedule.
9
EXAMPLE:
EARNED VALUE ANALYSIS
Suppose you are making cookies for a large party to be held
tomorrow.
Suppose the following are your plans:
Plans:
Therefore:
SV = BCWP - BCWS = -$2.50 (you are behind schedule)
over budget)
CPI = BCWP / ACWP = 0.833 (you are running over budget by
about 17%)
11
Estimate At Completion (EAC) The expected TOTAL cost required to finish
complete work. ACWP + ETC = EAC
Estimate to complete (ETC) The expected cost required to finish all the
REMAINING work. ETC= (BAC-EV)/CPI
12
WORK SHOP
A project has a budget of £10M and schedule for 10 months.
It is assumed that the total budget will be spent equally each
month until the 10th month is reached.
After 2 months the project manager finds that only 5% of the
work is finished and a total of £1M spent.
Find the following:
Variances: CV, SV
Indices: CPI, SPI
Forecasting: EAC, ETC, Time to completion
13
WORK SHOP
Solution:
PV = £2M
EV = £10M * 0.05 = £0.5M
AC = £1M
CV = EV-AC = 0.5-1 = -0.5M
SV = EV-PV = 0.5-2 = -1.5 months
Questions/Discussion
15