Professional Documents
Culture Documents
Construction Project Delays
Construction Project Delays
Project Delays
• If Owner causes a delay and there is no EoT clause, time may become ‘at
large’ and LD clause fails.
Project Delays
Time is the essence
• Not only is the contractor bound by it to perform in time, but owner is also
required to review and approve drawings and payments at contractual
terms.
Project Delays
Provisions in Contracts
• No-Damages-for-Delay-Clauses
• Contractor waives his right to any cost adjustment for any delay whatsoever, even if
owner caused delay
• Only an extension of time allowed for proven delays
• Classic example of an ‘exculpatory clause’
Project Delays
Contracts with No Provisions for Delays
• Only way to recover costs is through a lawsuit proving breach of contract on part
of the owner
Project Delays
Notice Requirements
• Without such a notice, owner may not know that some act or failure to
act is delaying the contractor
Project Delays
Constructive Notice
• E.g. An act of god shuts down work or the owner has issued a
notice to suspend work.
Project Delays
Compensable
Types of Delays Delays
Excusable delays
According to Non-Compensable
liability Non-excusable Delays
delays
Delays
Independent
According to Delays
occurrence
Concurrent Delays
Critical Delays
According to
effect and impact Non-Critical
Delays
Project Delays
Compensable vs Excusable Delays
Excusable Delays
Project Delays
Compensable vs Excusable Delays
Compensable Delays
Project Delays
Consecutive and Concurrent Events
• Consecutive Events
• Concurrent Events
Project Delays
Types of Delay events
NN Delay: Events for which the contractor
Non-excusable assumes the risks of the costs and time
Non Compensable
Delay Events
consequences involved. (Contractor Caused
Delays – CDR)
Project Delays
Responsibility
Related
External
Delay Resource
Causes Related
Causes
Contract
Condition
Related
Project Delays
• Lack of on time finance and • Subcontractors related problems
payments • Poor site management and
• Interference on execution of work performance
• Slowness in decision making • Ineffective project planning and
• Late in site delivery for construction scheduling
work and design • Inappropriate construction methods
• Improper project feasibility study • Poor communication and
• Poor communication and Client related Contractor coordination
coordination causes related causes • Inadequate contractor experience
• Late in supply of owner scope • Rework for correcting unsatisfactory
materials work
• Late/Limited Notice to proceed
Project Delays
• Lack of quality materials • Problem of process of financial
claims
• Slow delivery of material
• Government funding processes
• Changes in material types and
specifications • Late release budget/ funds
• Damage of materials • Global financial crisis
Construction Finance
• Inflation/price increases in
materials Material related
related causes causes
Project Delays
Contract Absence of alternative dispute resolution (ADR)
condition
Mistakes & ambiguities in contract document
related
causes Unrealistic contract durations and cost
Project Delays
External Adverse weather condition
Causes
Force majeure (acts of God)
Corruption
Effect of social and cultural factors
Policy and commitment of government
Unavailability of utilities at site
Project Delays
Construction Contracts and Project Delays
• But most (if not all) Contracts are silent as to how to demonstrate delay
and prove entitlement.
Project Delays
Delay Analysis
Project Delays
Prospective Analysis
• This is performed in REAL time prior to delay even or in real time
contemporaneous with the delay event.
• Based on Foresight.
Retrospective Analysis
• This is performed in after the delaying event(s) or change work has been
performed, such that the actual sequence, timing, and resources of the
work related to the subject event(s) is known.
• The timing may be soon after the delay events or prior to the completion
of the overall project or after the completion of the entire project.
• Based on Hindsight
Project Delays
A Case Study – As Planned Schedule
Activity Name Start Finish Original Duration(d)
Project Delays
Primavera Network Diagram
Project Delays
As Built Schedule
Activity Name Start Finish Original Duration(d)
Project Delays
As-Built Network Diagram
Project Delays
Delay Events
Activity As Chronolog Delay information Type Start (day) End (day) Delay
planned y of Duration
Duration delays (days)
Pedestal for
5 8 Holding of works by Owner EC 38 42 4
transformer
Project Delays
Model Project Delay Analysis using various
techniques
Project Delays
As Planned vs. As-Built
Project Delays
As Planned vs. As-Built
Project Delays
As Planned vs. As-Built
• The difference between the as-planned and as built completion dates is
the amount of time for which the claimant will request for
compensation.
• Net Delay= 51 – 40 = 11 days
Project Delays
Impacted As-Planned (Impact of first delay)
Project Delays
Impacted As-Planned (Impact of first delay)
Project Delays
Impacted As-Planned (Impact of second delay)
Project Delays
Impacted As-Planned (Impact of second delay)
Project Delays
Impacted As-Planned (Impact of third delay)
Project Delays
Impacted As-Planned (Impact of third delay)
Project Delays
Impacted As-Planned (Impact of fourth delay)
Project Delays
Impacted As-Planned (Impact of fourth delay)
Project Delays
Impacted As-Planned (Impact of fifth delay)
Project Delays
Impacted As-Planned (Impact of fifth delay)
Project Delays
Impacted As-Planned (Impact of sixth delay)
Project Delays
Impacted As-Planned (Impact of sixth delay)
Project Delays
Impacted As-Planned (Impact of seventh delay)
Project Delays
Impacted As-Planned (Impact of seventh delay)
Project Delays
Impacted As-Planned (Impact of eighth delay)
Project Delays
Impacted As-Planned (Impact of eight delay)
Project Delays
Impacted As-Planned (Impact of ninth & tenth delay)
Project Delays
Impacted As-Planned (Impact of ninth & tenth delay)
Project Delays
Impacted As-Planned
Duration Impact
Chronology of delays Type
(days) (days)
1 NN 3 3
Owner responsible delays = 6
2 EC 7 0
Contractor responsible delays = 8
3 NN 1 1
4 EC 1 0
5 EC 4 1
6 EC 2 1
7 NN 5 4
8 EC 4 4
9 NN 3 0
10 EC 3 0
Project Delays
Impacted As-Planned
• The sum of the delays (6+8=14 days) is greater than 11 days of actual
project delays.
• Limitations of this technique:
Maintaining the original finished-start relationship as per the as plan schedule.
Project Delays
As-Planned But for
Project Delays
As-Planned But for (with contractor’s delays only)
Project Delays
As-Planned But for (with contractor’s delays only)
Project Delays
As-Planned But for (with contractor’s delays only)
Project Delays
As-Planned But for (with owner’s delays only)
Project Delays
As-Planned But for (with owner’s delays only)
Project Delays
As-Planned But for (with owner’s delays only)
Project Delays
Collapsed As-Built
Project Delays
Collapsed As-Built (with owner’s delay subtracted)
Project Delays
Collapsed As-Built (with owner’s delay subtracted)
Project Delays
Collapsed As-Built (with owner’s delay subtracted)
Project Delays
Collapsed As-Built (with contractor’s delay subtracted)
Project Delays
Collapsed As-Built (with contractor’s delay subtracted)
Project Delays
Collapsed As-Built (with contractor’s delay subtracted)
Project Delays
Window Analysis
Project Delays
Window Analysis
Project Delays
Window Analysis (update schedule on day10)
Project Delays
Window Analysis (update schedule day 10)
Project Delays
Window Analysis (update schedule on day 21)
Project Delays
Window Analysis (update schedule on day 21)
Project Delays
Window Analysis (update schedule on day 32)
Project Delays
Window Analysis (update schedule on day 32)
Project Delays
Window Analysis (update schedule on day 40)
Project Delays
Window Analysis (update schedule on day 40)
Project Delays
Window Analysis (update schedule on day 51)
Project Delays
Window Analysis (update schedule on day 51)
Project Delays
Window Analysis
Delay in window
Schedule Update Completion date
Window Number
(day No) (day No) EC NN
0 (start) 0 40 0 0
1 10 41 0 1
2 21 42 0 1
3 31 44 2 0
4 39 49 3 2
5 (completion) 51 51 2 0
Total 7 4
Project Delays
Summary of delay analysis results for the case study
Delay in window
Delay analysis methodology
EC NN
As planned vs. As-Built 9 2
Impacted As-Planned 6 8
As planned but-for
Contractor’s point of view 4 7
Owner’s point of view 9 2
Collapsed As-Built
Contractor’s point of view 6 5
Owner’s point of view 7 2
Window Analysis 7 4
Project Delays
Summary of delay analysis results for the case study
Delay Analysis Methodology
10
9 9
9
8
8
7 7 7
7
6 6
6
5
5
4 4
4
3
2 2 2
2
0
As planned vs. As- Impacted As- As planned but-for As planned but-for Collapsed As-Built Collapsed As-Built Window Analysis
Built Planned (Contractor’s POV) (Owner’s POV) (Contractor's POV) (Owner’s POV)
EC NN
Project Delays
Concurrent Delays
Option One:
Option Two:
Option Three:
• Causes of delay are apportioned between the parties and the Contractor receives an
extension of time equal to the apportionment (for example, if the concurrent causes
of a 10-day delay are apportioned 60:40 Owner: Contractor, the Contractor would
receive a six-day extension of time).
Project Delays
Option One: Contractor not entitled to an extension of
time for concurrent delays
Project Delays
Delay Event Concurrent with Net Effect
Non-excusable to contractor,
Contractor Delay Another Contractor Delay or nothing
compensable to owner
Project Delays