SHDP Tizon
SHDP Tizon
BAKOD
Constructing School Perimeter Fence
Made of Steel with Concrete Post
APPLICATION PROJECT
PROJECT BAKOD
Constructing School Perimeter
Fence Made of Steel with
Concrete Post
NEAP PROGRAM
SCHOOLHEADS DEVELOPMENT
PROGRAMFOUNDATION COURSE
Tizon Elementary
School
Has 83 learners from kinder to Grade 6,
5 Teachers and school head. It is located
at Tizon, Tarangnan, Samar along the
national highway. With the location of
the school it is necessary to secure the
school with fence to avoid illegal entry
to the school.
INTRODUCTION
88 Learners
5 Teachers
1 School Head
Project Objectives:
1. Instructional Leadership
a. Development or Adapting the
existing program
b. Implementing program for
instructional Improvement
Project Targets:
Expected Output :
• Perimeter fence with concrete post.
• Safe and motivating learning
environment.
• No unauthorized entry to the school and
promote security.
Strategies
Milestone 1 :
Construction of school
perimeter fence made of
cyclone wire with concrete
post.
Strategies
Action 1
Conduct of Assembly Meeting
Responsible Person
School Head, School Planning Team
Support Needed From :
MOOE Fund (Php. 1000.00)
Target Date
February 1, 2019
Strategies
Action 2
Proper planning and formulating of Program of
Work
Responsible Person
School Head, Teachers, SPT, SGC, STWG, SBAC
Support Needed From :
MOOE Fund (Php. 500.00)
Target Date
February 8, 2019
Strategies
Action 3
Canvas an procurement of materials
Responsible Person
Procurement personnel, TWG
Support Needed From :
MOOE Fund (Php. 30,000.00)
Target Date
February 15, 2019
Strategies
Action 4
Implementation of the Project
Responsible Person
Skilled Worker, Laborer, Inspector
Support Needed From :
MOOE Fund (Php. 10, 5000.00)
Target Date
February – May , 2019
Strategies
Action 5
Monitoring and Inspection
Responsible Person
Division and District Supervisor, School Head, SPT,
SGC, TWG
Support Needed From :
MOOE Fund (Php. 500.00)
Target Date
Last week of May , 2019
Impact