Evacuation, Dehydration and Leak-Checking Procedures
Evacuation, Dehydration and Leak-Checking Procedures
procedures
1. Introduce dry air to the system and
apply pipe insulation
2. Check pressure switches and control
valves
3. Operate air or motor operated valves
and other components
4. Get rid of excess water in the system
5. Set ambient temperature to 5°C
6. Break vacuum seal using dry
nitrogen
7. Shut off vacuum pump
8. Break vacuum seal using gaseous
ammonia