Dipak Shrestha , DOR

 Insert pile photo from bagmati.


 INTRODUCTION OF SITE
 1.Three bridges of span 20 - 25 m length up to
75 m. were build with pile foundations.
 2. The site geology was clay and sand layers.
The pile depth varied from 17.5 m to 28 m.
diameter was 600 mm.
 3. The design loads were 37, 42 and 54 tons.
 4. The production were 1 piles a day.
Pile Capacity (600 dia)
JUDI (BH1)

Pile Capacity (kN)


0 100 200 300 400 500 600 700 800 900
100

95

90

85
Elevation (m)

80

75

70

65

60
Pile Capacity (600 dia)
CHESANG (BH7)

Pile Capacity (kN)

0 100 200 300 400 500 600 700


100

95

90

85
Elevation (m)

80

75

70

65

60
 Enhancing Pile capacity
 Shaft grouting
 End grouting
Diameter 600 mm 1500 mm 1500 mm
length 24 m. 30 – 50 m shaft grouted
30 – 50 m.

Geology clay & sand clay & sand clay & sand

Design capacity
420 KN 8 MN 12 MN
(42t) (800t) (1200t)
 Summary of Rate Analysis (BUMP)
 Bored Cast in Situ Concrete Pile (600 mm diameter)

 The following rate analysis is based on a 600 mm diameter bored cast in


place pile length 20m constructed at Chesang river on Biratnagar Rangeli
Road.

 The rate (cost) of boring is based on boring through firm to stiff clays and
silty fine to medium to coarse sand. The rate will vary in different type of
geology.

 The entire piling operation was performed by bringing skilled to


semiskilled experienced people from Calcutta. Thus higher rates for man
days have been taken.

 The rates are excluding VAT and Contractor’s profit. Details of the rate
analysis is enclosed.
SN JOB ITEM UNIT RATE REMARK

1 Mobilisation / Demob of piling plant L.S./1 bridge


50,000

2 Construction of Mud tank L.S./1bridge 77,271

3 Preparation Piling platform L. S. /1 cap 10,000

4 Preparation for Boring L. S. /1pile 833.65

5 Boring (by wash boring method) M 853.73

6 Concreting M 1,789.33

7 Reinforcement Ton 28,612.00

8 Obstruction Hour 982.00

9 Pile head preparation 1 pile 600.00


Piles Well
15 no.x 20 m. x 600 mm dia 12 m. x 6 m. dia
scour depth 6m Scour depth 6 m
unit skin friction 40 kpa unit skin friction 40 kpa
unit end bearing 1500 kpa unit end bearing 1500 kpa

Total capacity : Total capacity :


(Shaft + Base) *15 (Shaft + Base)
(14*1.88*40 + 0.28 * 1500)*15 (6*15.7*40+19.62*1500)
15792 + 6300 KN 3768 + 29430
22,000 kN 33,000 KN

Allowable capacity 12,000 KN Allowable capacity 11,000 KN

FOS = 2 FOS = 3

Capacity can be handled with grouting


 Vertical Capacity
 Horizontal Capacity
 Group pile analysis
 Settlement
 Batter piles
 Negative skin friction
 Fixity of piles
 Construction time (as short a possible)
 Enhnacing the bearing by grouting