Honda-Goa, 06th May 2009 1

SAP PP MODULE

Presented By :
D.Avinash
Honda-Goa, 06th May 2009 2
Process Flow Integration

Sales Order Material Availability Check


Customer Shipment Sales & Transfer of Requirements
Credit Limit Distribution Goods Issue to SO

Sales Order / Forecast / Plan Invoice

Material Requirements
Production Material Procurement Materials
Planning Management
Production Cost Accounting Document

Purchase Order

Invoice Receipt

Goods Receipt
Finance & Vendor
Receivable Accounts / Cash Receipt Controlling Accounts Payable

Honda-Goa, 06th May 2009 3


SAP R/3 PP Module overview

Sales and Operations Planning


Org. Structure
SAP R/3 Integration
Long Term Planning

Demand Management

PP Basic Data : MRP

Material Master Planned order


Bill of Material
Work Center Production Order

Routing Back flushing

Production Order
Confirmation &
Settlement

Honda-Goa, 06th May 2009 4


Navigation

5
6
7
Organizational Structure

Company Company Code

Plants Plant 1 Plant 2 Plant 3

PC1 PC 2 PC 3 Storage Location SL 1 SL 2 SL 3

Profit Center

CC1 CC2 CC3


Cost Center

Work Center WC1 WC2 WC3

Honda-Goa, 06th May 2009 8


Company Code:

1
PLANT

 A Plant is a organization unit that subdivides an


enterprise according to production, procurement
,maintenance or material planning.
 It is a place where material are produced or goods and
services are provided

1
Storage Location

11
Master Data

Honda-Goa, 06th May 2009 12


Master Data
 Master data used for manufacturing planning and
execution includes:
 MATERIAL MASTER
 BILL OF MATERIAL
 WORK CENTER
 ROUTING
 COST CENTER

1
Material Master
Views of the Material Master

Purchasing

 Basic Data The material master is a Sales


central data object for all
MRP material types:
 Work
• raw materials scheduling 
Stocks in plant/
storage location • semi-finished products Quality
management
• finished products
Accounting
• P.R.T. Forecasting 
Storage
Classification

Costing Each user function has its own view of the material master which
permits easy access and maintenance of data.

Honda-Goa, 06th May 2009 15


Basic Data view

Honda-Goa, 06th May 2009 16


MRP View

Honda-Goa, 06th May 2009 17


Work Scheduling View

Shop Floor
Engineering
Production
 Which departments use this view?

? 


Engineering
Shop Floor Production
Materials  Materials Management
Management

 Why is this view used?


 To record data related to

? production such as:


 Units of issue
 Issue Storage Location
 In-house production
time
Honda-Goa, 06th May 2009 18
Plant Data / Storage Views

Shop Floor  Which departments use this view?


Production
 Shop Floor
?  Materials Management

Materials
Management

View is used to record following


data
? 


Shelf life data
Stock Determination
 Profit Center

Honda-Goa, 06th May 2009 19


Bill of Material

Honda-Goa, 06th May 2009 20


Bill of Material

BOM

A bill of material is a complete, formally structured


list of the components of a product or assembly.
A bill of material contains the description and
object number of each component, the quantity
and unit of measure.

Honda-Goa, 06th May 2009 21


Multi Level - Bill of Material

Machine

Assembly 1 Assembly 2

Motor Gear Exhaust Fly wheel Chain Frame Shaft

Combining single-level BOMs


creates a complete multi-level
structure.

Honda-Goa, 06th May 2009 22


Bill of Material Usage

Engineering Production Different types of BOM usage;


Data Data
 Engineering
 Production
 Costing
BOM  Sales
Costing BOM Item Status
Data
• Released
• Blocked

Sales Data

Honda-Goa, 06th May 2009 23


Bill of Material Structure

• BOM header maintained with structure of assembly components & sub assembly items with respective

base quantity and unit of measure.


• BOM status governs, whether the BOM is active or inactive.

Honda-Goa, 06th May 2009 24


ECM

Honda-Goa, 06th May 2009 25


BOM Validity Period

 The validity period is the time period during


which the bill of material is valid. The time period
is defined by the "valid-from" date and the "valid-
to" date.
 BOM creation and changes are handled by
Engineering Change Management by giving
SAP AG

Valid-from date
1993
Change Numbers
 ECN numbers are required for BOM creation &
changes.
 ECN’s will be inactive when Designer is working
on that BOM.
 ECN’s will be active when they are released to
SAP AG
production.
Valid-to date
1993

Honda-Goa, 06th May 2009 26


Work Center

Honda-Goa, 06th May 2009 27


Work center

Definition A work center is an organizational unit where


a work step (operation) is performed.

Usage Work centers are used in routings. They can also be used
as capacity collectors for statistical evaluations.

Examples
Type of work center Example
 Individual work center Automatic lathe 17

 Work center group Machine shop

 Assembly line Line 9

 Individual person John Doe


 Group of people Group 12

Honda-Goa, 06th May 2009 28


Work center Data

General data Basic data Name and description


Standard value key

Standard values Default values Control key


for routing
Standard text key

Capacity data Capacity


Available capacity
Formula key

Scheduling data Scheduling Scheduling basis


Queue and move times
Formula key
Costing data Cost center
and Assignment
HR data Activity types

Honda-Goa, 06th May 2009 29


Routing

Honda-Goa, 06th May 2009 30


Routings

 A routing describes the processing steps that must be performed to produce a


material.

Material

Routing group

Operation 20

Operation 10
 Work center Material components
 Texts
 Control data Production Resources
 Times and Tools

Honda-Goa, 06th May 2009 31


Routings

 Each individual routing is referred to as a group counter within the group

Routing Group

Group Group Group


Counter 01 Counter 03 Counter 04

Honda-Goa, 06th May 2009 32


Routings

Routings contain:

 Manufacturing In-house components & finished goods.


 The work centres where the operations are to be performed

Material allocation
 The manufacturing material is allocated to the group counter.
 Component are allocated to operations and standard values for
• Setup time,
• Processing time
• Tear-down time

Honda-Goa, 06th May 2009 33


SOP

Honda-Goa, 06th May 2009 34


SALES AND OPERATION
PLANNING
 Sales and operation planning is a planning and
forecasting module within the logistics area of R/3.
 We can use SOP to help us forecast future sales,
develop production plans and perform feasibility
studies
 A production plan could be developed based on the
sales plan.

1
SOP Process Flow

1
To Create a sales plan
 We can enter manually
 We can enter from forecast
 By transferring data from COPA and also SIS
 By transferring data from another product group

1
To Create a Production Plan
 1.Synchronous to sales
 2.Target Stock level
 3.Target Stock days

1
Disaggregation
 Creating a sales plan or a production plan at one level
of the product structure hierarchy does not creat lower
level plans. So we must disaggregation
 Many options exists when disaggregation

1
Demand Management

Honda-Goa, 06th May 2009 40


Demand Management

Sales Plan Prodn Plan Forecast Plan

Manual Planned Sales


Independent Demand Management Demand from
Requirements “Demand Program” Sales Orders

MRP/MPS

Demand mgmt will have product, qty & Rqd. Date

Honda-Goa, 06th May 2009 41


Demand Management Process

Demand Management
 Customer or sales requirements ( Export or Domestic).
 Planned independent requirements.
Planning strategies
 Methods of production for planning & manufacturing or procuring a
product.
Different planning strategies used are;
 Make to stock
 Make to order
 Planning with final assembly
 Planning for project

Honda-Goa, 06th May 2009 42


MRP

Honda-Goa, 06th May 2009 43


MRP Overview

Complete MRP Overview

MRP
Sales orders
Planned ind reqmts
Dep. reqmts

Reservations Planned Only for


materials procured
order
externally

Convert
Purchase Schedule
Production requisitions lines
order
Purchase
order
Stores
Warehouse Stock
Stores Stock

 SAP AG 1999

44
MRP- Stock Requirement List

45
Production Control

Honda-Goa, 06th May 2009 46


Production Methods

Honda-Goa, 06th May 2009 47


Production Methods

Discrete manufacturing:
 Frequently changing products
 MFG restricted production lots
 Varying sequence of work centers over which a product can run

Repetitive Manufacturing:
 Same product is produced over a longer period of time in one
production line
 Total quantity of the product is manufactured over a specific period of
time with a specific production rate per partial period

Honda-Goa, 06th May 2009 48


Batch Management
Batch Management

Batch Management:

Batch Number Assignment


You use this function to assign a batch with a number that uniquely
identifies it.

Batch Specification
You use this function to describe each batch uniquely using
characteristics and characteristic values. You specify the permitted
value range in the allocated material master record.

Batch Status Management


You use this function to indicate whether a batch is usable or
unusable. You set this status:
Manually in the batch master record or at goods receipt
Automatically in the usage decision in quality management
Production Orders

Honda-Goa, 06th May 2009 51


Production Order Overview

7 - Print Shop
Confirmation Slip
1 - Select 2 - Select 3 – Schedule Dates Floor Papers
BOM Routing (Fwd / Backward)
Release
Order 6 - Calculate
Planned Costs
Actual
Create Labor Confirm
Order 4 - Check Completion
Availability 8 - Issue
Cost Release Materials to
5 - Calculate Order 10 - Calculate
Capacity Actual Costs

9 - Receive complete
Goods
Issue goods into stock
Goods
Receipt

Honda-Goa, 06th May 2009 52


Production Order Settlement

 A Production Order collects all costs associated with making an inventorial item and
the order “picks up” the cost from Material master.
 Production cost analysis carried out after Final Confirmation & Order Settlement.

Production Order STATUS:


Created, Released,
Bill Order: 73 Confirmed, Delivered,
of Type: PP01 Settled
Material Plant: LR001
Sys Status:
CRT REL CNF DLV SETC

Quantities:
Total Produced: 100 Tons
Scrap: .001
Routing Confirmed: 100 Tons
Dates:
Schedule 09/15/95
Confirmed 09/16/95

Honda-Goa, 06th May 2009 53


Repetitive Manufacturing Process

REM MFG Process:


 Produce the same or similar products over a lengthy period of time.
 Total quantity is produced over a certain period at a certain rate per part-period.
 products always follow the same sequence through the machines and work
centers in production.
 Production confirmation against product cost collector.
REM Process mandatory field:
 Production Version.
 REM Profile
 Product cost collector.

Honda-Goa, 06th May 2009 54


Backflushing

Honda-Goa, 06th May 2009 55


Backflushing Process

 GR/GI will happen simultaneously at the time of Posting.

Honda-Goa, 06th May 2009 56


THANK YOU