Professional Documents
Culture Documents
Gas Desigh
Gas Desigh
Gas Desigh
Construction of
Gas Distribution Network
GSPC Gas Company Limited
December, 2009
Gandhinagar
City Gas Distribution – An
Overview
WHAT IS CITY GAS
DISTRIBUTION?
Distribution Zone
HP Network
CITY GATE
MPB Network
MPA Network
Domestic and
Commercial
LP Network
Users
CGD PRESSURE REGIMES
Outlet
Sr. No. Network Component Inlet from Inlet Pressure Outlet to
Pressure
4 Service Regulators (SR) MP MDPE Pipeline 4 – 1 Barg 110 mBarg LP MDPE Pipeline
Industrial MRS &
5 MP MDPE pipeline DRS 4 barg 4 – 1 barg Commercial
Connections
Regulator of Domestic /
6 LP MDPE Pipeline SR 110 mBarg 110 – 50 mBarg Commercial
Connections
1.5 barg or
MP MDPE pipeline 4 – 1.5 barg customer specific Industrial internal
7 Industrial MRS
Steel pipeline 26 – 14 barg pressure within pipeline
the supply range
Online / Mother CNG
8 Steel Pipeline 26 - 14 barg 250 Barg Vehicle at 200 Barg
Station
9 Domestic Connections LP MDPE Pipeline 110 – 50 mBarg 21 mBarg Meter & Gas Stove
75 mBarg or
LP MDPE Pipeline 110 – 75 mBarg customer specific
10 Commercial Connections Meter & Gas Stove
MP MDPE Pipeline 4 – 1 Barg pressure within
the supply range
City Gas Distribution –
Applicable Codes &
Standards
European Standard
S. No. STANDARD NO. DESCRIPTION
ASME Boiler and Pressure Vessel Part C- Specifications for welding Rods, Electrodes, and Filler
7
Code- II Metals
1 OISD-226 Natural Gas Transmission Pipelines & City Gas Distribution Networks
4 OISD- Standard- 141 Design and Construction requirements for cross country hydrocarbon pipelines
7 API Standard 1102 Specification for steel pipeline crossing & highways.
AMERICAN GAS ASSOCIATION
(AGA)
6 AGA Report No.3 Orifice metering of Natural Gas and other related Hydrocarbon fluids
Diaphragm
Rotary Positive Displacement (RPD)
Turbine
Diaphragm Gas Meters (Domestic)
Tech Spec: EN 1359
Capacity: 2.5 m3/hr
Rangeability or TD ratio: 1:150 or
better
Nominal Working Pressure: 21 mbar
(g)
End Connections: ¾”, as per BS 746
(Male)
Center to Center distance: 110 mm
between inlet and outlet connections
Diaphragm Gas Meters (Commercial)
Expensive
Industrial Metering Station (IMS)
IMS are used to measure gas supplied to
Industrial consumers
Main component in IMS is filter, Isolation
Valves, RPD Meters with EVC & Modem,
Regulators (If low pressure requirement) and
Non return Valve
Inlet pressure range – 1.5 Barg to 4 Barg
Outlet pressure – As required by customer
MRS components
Inlet & Outlet
isolation valves
Filter
Pressure regulator
with a built in slam –
shut device
Relief valve
Strainer
Flow Meter (RPD,
Turbine, etc.)
GI ERW Pipes
t = PD / 20fs
Steel Pipelines
Above Ground Mains
Polyethylene being forbidden for above
ground crossings, if any, steel mains sections
are needed at the crossing with PE/steel
transition fitting to be buried with the
adjacent PE mains.
Steel Pipelines
Process Design
Wey-mouth Formulae
Q = 0.0813 * (d)2.6667 * {(p12-p22)1/2 /
(S * L)1/2 }
Velocity
V = Q / A
Velocity for filtered gas to be 40 m/s
& unfiltered gas to be 20 m/s
maximum.
Example
1 2
Example
Q = 2,00,000 SCMD i.e. 9,166.66 SCMH
Using Wey Mouth Formulae: Q = 0.0813 * (d) 2.6667 * {(p12-
p22)1/2 / (S * L)1/2}
9166.66 = 0.0816 x (d)2.6667 * {(16.0132-10.0132)1/2/(S* L)1/2}
d = 198.52 mm : Calculated Diameter.
We have to select diameter from the available range e.g.
200.1 mm from API 5 L
Now, P1V1 = P2V2
1.013 * 9,166.66 = (9.32+1.013) * V 2
V2 = 898.8 M3 / Hr = 0.2497 M3 / Sec.
Now, for Velocity, Q = A * v
0.2497 = (3.14/4) * (200.1 * 10 -3)2 * v
V = 7.94 m/s
Now, for Wall Thickness, t = (P*D) / 20fs
t= (16.013 * 219.1) / (20 * 0.29 * 241)
t = 2.5099 mm
Example
1 2 3
2
1
Polyethylene Pipelines
MRS (Minimum Required Strength)
The MRS value represents the long-term
circumferential stress in the pipe under which the
break may occur after 50 years at the earliest.
Stress = MRS / C, where C is overall service coefficient
The minimum value of C for the material to be used
for Gas application is 2.
MAOP (Max. allowable Operating Pressure)
MAOP = (20 * MRS) / [C * (SDR-1)].
Standard Dimension Ratio
SDR = Dn / En
SDR used in GSPC Gas is SDR 9, SDR 11 & SDR 17.6
Standard followed by GSPC Gas
IS 14885: 2001
Polyethylene Pipelines
Base resin
The PE resins of “Third Generation” (PE 100 or MRS
10) in full compliance with detailed specification is
being used. First Generation is PE 63, second PE 80
& Third generation is PE 100.
Wall thickness
The MDPE network designed and qualified for a MOP
of 4 bar.
The “Network analysis” and resulting structure and
behaviors are based on such design. PE line pipes
wall thickness shall be in accordance with the
following SDR
Gas mains (ND ≥ 90 mm): SDR 17.6
Gas mains and Service lines (ND ≤ 90 mm): SDR 11.
Service lines (ND = 20 mm): SDR 9
Polyethylene Pipelines
Different Material used for PE Pipes
The following materials have been approved to date:
Solvay Eltex TUB 121(Black) or Eltex TUB 125(Orange) PE
100
Borealis HE 2490 PE 100
Fina Finathene XS 10 B PE 100
Dow BG 10050 PE 100
Elenac Hostalen CRP 100 PE 100
Codes:
Manufacturer Commercial Brand Name Code(*)
SOLVAY ELTEX TUB 121/125 E3
BOREALIS HE 2490 N3
FINA FINATHENE XS 10 B F3
DOW BG 10050 D3
ELENAC HOSTALEN CRP 100 H7
Polyethylene Pipelines
Process Design
Wey-mouth Formulae
Q = 0.11672 * (d)2.664 * {(p12-p22)0.544 / (S *
L)1/2}
Velocity
V = Q / A
Velocity for filtered gas to be 40 m/s &
unfiltered gas to be 20 m/s.
Being a complex network, required
specialized tools for Planning & Designing
the network. GSPC Gas use SynerGEE
software for designing the PE Network.
PNG Domestic & Commercial
Connection
Process Design
Polyflow Formulae
Q = 1.522786 * 10-3 * (d)2.623 * {(h/L)0.541}
Peak Gas flow is assumed @ 0.5 SCMH
for one house
Being a standard PNG Connection, we
have standardize the design of PNG
Network as follows;
½” GI pipes up to G + 4 apartments OR 5 connections
in case of raw house.
1” GI Pipe above 5th Floor apartment OR above five
connections in raw house.
PNG Domestic & Commercial
Connection
Route Selection for GI / Copper Pipe Installation
Route selection for GI pipe installation shall be carried out as per
the guideline given below;
Pipe shall not be installed on un-plastered wall or in the house under
construction.
Pipe shall not be installed in an unventilated void space.
Route shall be selected that maximum length of the pipeline shall be
installed outside.
Route of the pipeline shall be planned for the shortest possible length.
The gas pipeline shall be away (minimum distance of 200mm) from
the electrical line.
There shall be minimum change of directions and minimum no of
threaded joints.
Maximum two Point in the kitchen for gas stove only.
Compound gate or doors and windows inside the house shall not hit
the Gas pipeline.
Copper installation should be a minimum 300mm away from heat
source and Electrical installations. If it is not possible for copper
installation then suitable protection should be given.
If the copper pipe installation is carried out inside cupboards, there
should be a provision for adequate ventilation like louvers/holes in
cupboard doors.
PNG Domestic & Commercial
Connection
Positioning of Valves, Regulator & Meter
Riser Isolation Valve:
For apartments, one riser isolation valve shall be provided at
a height of 2 meter
From the ground and individual meter control valve shall be
installed for each connection.
The riser isolation valve shall be installed at a convenient
height so that it is easy to operate the valve in emergency.
Meter Regulator:
Regulator shall be installed in such a way that it reduces the
length of H.P. Line (Max. pressure 0.1 Bar) to minimum
possible.
Wherever possible meter Regulator shall always be installed
outside residence and at a convenient height.
PNG Domestic & Commercial
Connection
Gas Meter:
Gas Meter shall be installed in such a way that it shall be
protected from direct rain or waterfall on the meter. Location
of the Gas meter shall be decided during the route selection.
Meter shall be installed at convenient height so that it is easy
for the meter reader to take correct readings.
The meter shall never be positioned very near to Electric
Line. A minimum distance of 200 mm shall be maintained.
Appliance Valve:
The position of the appliance valve shall be convenient to
operate and it shall keep the rubber tube at a safe distance
from the heat source.
The orientation and distance from cooking platform/ground
shall be maintained in such a way that the Bending Radius of
the Rubber Tube shall be more than 100mm.
Appliance valve shall be installed in ventilated space and the
lever of appliance valve shall not foul with the wall during the
on-off operation.
Clamping
GI Pipe cutting &
Threading
After site and route clearance, the measurements for pipe cutting
shall be taken and pipes shall be cut accurately as per the
required lengths.
If the length of pipes is not correct, the threaded joints come
under heavy stresses, which may ultimately cause gas leakage.
Installed piping threaded connections / joints shall be tightened in
such a way that all the joints shall be free from heavy stresses
and misalignments due to incorrect pipe length.
The condition of thread die and pipe vice jaws shall be checked
regularly and shall be free from defects.
Cutting fluids (oils) shall be used while thread cutting.
Threaded pipes shall be handled carefully so that the threaded
oily portion shall be free from dust, mud, water and any damage
due to impact of any object.
Cutting burrs on the pipe shall be removed from the edges. The
edges shall be straight and free from Knife-edge formation.
G.I. Pipe Installation &
Clamping
Teflon tapes shall be wrapped on threaded portion of the pipe with
minimum three overlaps. The Teflon tap should be of approved make
and gauge.
The no of clamps shall be adequate. The pipeline portion containing
the Regulator and Meter, either horizontal or vertical, shall have
clamps on both side of the regulator and meter. Clamps shall be
fitted in such a way that they do not create misalignment of pipes.
The clamp shall be installed by drilling 6 mm hole in plastered wall
and screwed using rowel plug.
Distance between two clamps shall not be more than 2 meter; the
gap between riser and wall shall be minimum 25 mm.
Clamps shall be installed in a straight line and shall be parallel to
each other.
The clamps shall be fixed properly on the walls and should grip pipe
in position.
For wall crossing, drill the hole with the help of electrical drilling
machine in such a way that plaster and tiles shall not be damaged. It
shall be ensured that there is no concealed wiring or any other fitting
on the opposite side of the wall for a particular location of drilling.
G.I. Pipe Installation &
Clamping
Self-adhesive anticorrosive tape shall be wrapped on the
pipe with 50% overlap.
Casing sleeve shall be installed in wall for wall crossing.
Alignment of the pipeline shall be maintained.
Whenever compound gate, house door or window hits the
G.I. pipe protection clamp shall be installed to protect the
pipe.
Concealed piping shall not be done.
All the pipes shall run on walls with clamps. Pipe should not
be overhung and shall not be installed without pipe clamp.
Wherever powder coating is peeled off during fitting and
tightening of the pipe, touch up shall be done after the
installation is completed by two coats of approved paint.
Prior to installation all pipes and fittings shall be checked
internally to ensure that they are free from any obstruction.
PE to GI (transition fitting) joint shall be provided above
ground.
Installation of Valves,
Regulator & Meter
Union and testing T shall be installed before riser
isolation valve.
Meter control valves, Meter regulator and Gas meter
shall be protected from the over tightening of the thread.
Valves, Meter regulator and Gas meter shall be installed
with the clamps on both sides. As far as possible hex
nipple shall not be used for connecting. Both side
threaded 3” to 8” long pipe nipple shall be used.
Gas meter, regulator and installed piping shall be aligned
properly.
Flow direction of the gas meter shall be checked before
installation.
Flat rubber washer shall be checked and ensure at inlet
and out let of the adaptor joint to the meter.
Pipe nipple shall be installed between elbow and
regulator to avoid direct load of line or riser on regulator
and a clamp must be provided on the pipe nipple.
Testing of Installed Piping
Connection
Before carrying out the pneumatic test of the whole installation;
testing assembly, air foot pump with pressure gauge / manometer
shall be checked its calibration and proper functioning.
Before pneumatic testing of the installed connection spacing
between two clamps, tightening of the clamps thread joints,
alignments of the whole piping shall be checked. Valve shall be
kept in open position and the appliance valve shall be kept in
close position.
Calibrated pressure gauge shall be used having the range of 0 – 1
Bar.
Position of the pointer of the pressure gauge shall not be marked
with the marker pen on the glass. It should be recorded in the test
records. Pneumatic testing pressure shall be kept 1.5 times of the
working pressure and should be maintained for 30 minutes.
After pressurization of the whole piping section shall be checked
for the leakage with the help of soap solution.
During the testing, air should reach up to the appliance valve.
After completion of testing, pressurized air shall be released from
appliance valve only.
Conversion of Burner
All the appliance valve and riser isolation valve shall be kept in closed
position.
Ensure that meter and regulator adaptor shall be leak proof.
Open the burner knob and remove the plug from the hot plate.
Clean the simmer hole.
Make the simmer hole of 0.6 mm with the help of simmer drill.
At the time of drilling the hole, ensure that it should not be inclined.
Remove the dust from plug.
After greasing, plug and knob should be properly positioned at their original
position.
Remove the burner from hot plate and clean it.
Open the existing jet (LPG) and replace it by 125 no jet if it is big burner or
110 no jet if it is small burner.
Place the burner on its original position and connect the nozzle with appliance
valve using flexible and braided rubber hose.
The length of rubber hose shall not exceed 1.5 mtr.
Both the ends of the rubber hose shall be clamped by metallic clamps on the
nozzle.
Check all the joints with soap solution and ensure that the flame color should
be blue.
All the Best