EXAMPLE OF BUILDINGS

CONSTRUCTED USING IBS AND


EXPLANATION ON THE SYSTEM USED
INDUSTRIALISED BUILDING SYSTEM
BRIEF HISTORY OF IBS
IN MALAYSIA
BRIEF HISTORY OF
IBS IN MALAYSIA
• Pilot project started using IBS system during
1966 namely
• Pekeliling Flat, Kuala Lumpur
• The Rifle Range Flat, Penang
• In 1981 – 1993, PKNS acquired pre-cast
concrete technology from Praton Haus
International, Germany for built housing
project.

Add a footer 3
EXAMPLES OF IBS IN
MALAYSIA
FR

Project Detail
• Project site : 2.1 hectars
• Possession of site : 1 Feb
2001
• Completion : 31 July
2001
• Construction Period : 5 ½
months
FR

System Used
• Beams, floor slabs (half slabs with
concrete topping) and staircases
were prefabricated in the factory,
and wall panel are hollow blocks.
• Column and toilets were cast in-
situ
FR
Project constructed
FR
Project constructed
FR
Finished project
FR
Quarters for Immigration
Department of Malaysia,
Bandar Baru Uda, Johor.
• Start Project : April 2015
• Handing Over : 25th July
2018
• Located in Bandar Baru
Uda.
• Main contractor : Gerbang
Nusajaya Sdn Bhd.
• Precast concrete
components supplier :
MTD ACPI Engineering
Berhad.
• IBS installer : Triple Consult
& Resources Sdn Bhd
FR
• A 16-Storey tower.
• Prefabricated components : Precast
concrete columns, beams, half
slabs and hollow core slabs.
FR
FR

Project Akademi Audit


Negara, Nilai, Negeri
Sembilan
• Start Project : 15 August
2002
• Start operation : September
2005
• Located in Bandar Enstek,
Nilai, Negeri Sembilan.
FR

System Used
• A five-storey hostel was
constructed using precast
technology.
• The precast structural elements
were beam, column, wall, slab,
staircase and balcony.

14
FR

PROJECT BALAI
POLIS
SENAWANG,
NEGERI
SEMBILAN
System used : cast-in-situ column and
beam, precast infill wall and slab