BASE LINE SCHEDULE REVIEW- AACEI RP78R-13

Schedule Base Line establish the activity dates and possibly the budgeted cost.

Typical Baseline submittal consists of


- Narrative describes the general workplan.
- Electronic copy of the baseline native files
- Printed copy of the schedule as per the specification
- Graphics, as required includes ( Bar chart, Histograms, S-Curve)
Base line schedule review

Focuses on the following issues: To ensure the following issues

- Inclusion of entire scope.


- Sequence and work flow
- Constructability - Completeness.
- Timing and Phasing - Delineation of responsibility
- Legal and contractual requirement - Enforceability
- Unambiguous and clear description of the
work
- Resources usage and balance
- Level of detail
- Design and coding of Activities, project
organization and WBS
- Critical path analysis
Schedule baseline review

Evaluates: By check
- Scheduling requirement as per the - Critical activities, procurement and long lead items
contract - Activity durations
- Scope of the project as defined by the - Concurrent activities of similar work and the resource
contract availability
- The contractor execution plan - Activities relationships
- Resources availability - Project mile stones
- Area access restriction and site logistics plan
- Identifiable and reasonable critical path
Pre-Analysis Checks Analysis

- Proper identification of the schedule Project analysis


- Calculate the schedule
- Imposed project finish date Activity analysis
- Contract performance period
Activity description check
- Correct Data date
- Minimum duration measurement Activity Code analysis
- Currency designation
- Week start day WBS Code analysis
- Calendar check
- Internal operating rules Relationship analysis
- Out of Sequence
- Total Float Lag and Lead check
- Critical Path identification setting
Constraint analysis

Cost analysis

Notebook or log review

Other checks
Analysis

Project analysis

Activity analysis

Activity description check

Activity Code analysis


TO BE CONTINUED
WBS Code analysis m.nada@novsta.com.au
0426 149 527
Relationship analysis

Lag and Lead check

Constraint analysis

Cost analysis

Notebook or log review

Other checks