Professional Documents
Culture Documents
Case 2 AIC Netbooks
Case 2 AIC Netbooks
Presented by:
Sakshi Jain
Sadhana Kharol
Prerna Sharma
Background Of Case
Advanced Integrated Circuitry
Founded in Taichung, Taiwan in 1992
Producer of Printed circuit boards, Motherboards &
Graphic cards
Supplier are Dell, Compaq &Hewlett-Packard
2000: Evolved Original Design Manufacturing
2001: Shifted all production in china
2007: Enters Consumer Electronic Market
Factory Setup
• Total 4 Assembly lines
• 1 Assembly line = 16 mtr.
• 1 Shift = 8 hrs(excluding 1 hr. beak)
• A day =16 hrs, a week =96 hrs
• Each line produced 700 units per shift
• A day =1400 units, a week =8400 units
Good Practices
High Focus on Cost Management
Avoided “me to” product & encouraged them to
introduce an “atom processor” based netbooks
Giving ownership over all steps
Shifted Unit to China which gave lower labour cost
Burn in test before packaging to shipment
Double check process
Encourages Kaizen Approach
POKA-YOKE Process
Strategically Delayed the Production so as to have
technological edge
Bad Practices
Some non-standard operations crept into the assembly
process. E.g.: Webcam cable requirement
The pressure to maintain output levels led supervisors
in addressing the immediate problems without fixing
the root cause
Unsanctioned buffer inventories were accumulated
between stations
No new hiring despite requirement
Supervisors were often engaged in “FireFighting”
Problems
Unsanctioned buffer inventories
Inconsistent Demand
How to improve productivity of existing capacity
Increasing shifts to 10 or 12 hours was not sustainable
CSO unwilling to invest on 3rd shift workers
Pressure from corporate office to improve current
performance and boost Gross Margin
Variance in labour efficiency
kaizen meetings led to supervisors fire-fighting to look
for quick fixes to maintain output levels
Solutions
Should hire more workers to increase the shift from
two to three.
Shifts should be of 8 hrs each(including 1 hr of lunch
break)
-Number of units in 1 hour = 3600/50 * 4 = 288
- Number of units per shift = 288 * 7 = 2,016
-Number of Units per day = 2,016 * 3 = 6,048
-Number of Units per week = 6,048 * 6 = 36,288
-Number of Units per month = 1,45,152
-Thus, even with the three 7 working hour shifts, we can
produce well above the expected demand of 1,30,000
Netbooks per month.
THANK YOU