PROJECT MANAGEMENT
FrauMonaRe
Project Management
2
Success Failure
+ Costs Costs
+ Increased because of the design planned costs were $876 million
+ The final construction was 100 dollars
meters higher than the original final cost were $1.5 billion dollar
design Time
+ Changes in interior design planning Originally the duration of the
+ Quality project was set for 47 months
+ Engineers did practice tests several Was completed nine months later
times to raise safety of the
construction