Weekly Construction Progress Report NO. 31: Period Covered: June 09 To June 15, 2018
Weekly Construction Progress Report NO. 31: Period Covered: June 09 To June 15, 2018
2. WEEKLY DASHBOARD
3. PROGRESS S-CURVE
NOA 02-November-17
NTP 04-December-17
Original Contract Period 540 Calendar Days
Original Contract Project Start 21-November-17
Proposed Start Date 18-December-17
Actual Start Date 15-October-17
Original Contract Completion Date 14-May-19
Proposed Completion Date 10-June-19
Projected Completion Date 30-December-18
Percentage Time Elapsed 33%
Percentage Time Remaining 67%
Schedule Slippage _
REASONS OF DELAY
Consultant Concluded Delay Events: Ongoing delay events
TVA&P - NO MAJOR DELAY - NONE
% remaining
64.43%
QUALITY PROJECT HEALTH CHECK
Issued Closed in time Closed-late Overdue Timely % Trend
NCR's 0 0 0 0
*** Timely % represents total NCR's closed on time. Upward trending represents improvement in timely closure
SCHEDULE SAFETY
HSE STATISTICS
Item Last Period This Week Total to date
No. of LTI(s) 0 0 0
LTIFR 0 0 0
COST QUALITY
LTISR 0 0 0
PROGRESS
S-CURVE
STATEMENT OF WORK ACCOMPLISHMENT
Planned Actual GAIN SPI
SWA 18.02%
18.82% 35.57% 17.56%
16.75% 1.97
1. Fabrication of rebars for footing tie beams and ties for columns
2. Column ties installation
3. Continuous dewatering
4. Backfilling
5. Removal of eroded soils
6. Deshuttering works
Concreted FTB
On-hold
Zone 3
Rebar installed
Zone 2
Zone 4
PROJECT RELATED
ISSUES/ CONCERNS
PROJECT RELATED CONCERNS
NONE
QA/QC, SAFETY &
SECURITY CONCERNS
QA/QC CONCERNS
LOAD ALLOWANCE
SAFETY & SECURITY CONCERNS
WEATHER REPORT
Period Covered: June 09 to June 15, 2018
WEATHER
DATE REMARKKS UNWORKABLE DAYS
AM PM
June 9, 2018 HR HR /
June 14, 2018 RS RS Working areas were fully saturated. All major works are suspended. /