CONSTRUCTION OF PASIG CITY SPORTS ARENA

(Phase II-Structural Works)

WEEKLY CONSTRUCTION PROGRESS REPORT


NO. 31

Period Covered: June 09 to June 15, 2018


CONTENTS
1. PROJECT PARTICULARS

2. WEEKLY DASHBOARD

3. PROGRESS S-CURVE

4. MANPOWER HISTOGRAM & EQUIPMENT HISTROGRAM

5. CONSTRUCTION (LOOK- AHEAD )

6. ARENA PROGRESS LAYOUT

7. WEATHER REPORT & WEATHER FORECAST

8. PROJECT SITE PHOTOS


Client Pasig City Local Government
Contractor Phesco Incorporated
Consultant TVA&P
BID Contract Amount 339,015,973.60
Contract Budgetary Amount 205,976,000.00

NOA 02-November-17
NTP 04-December-17
Original Contract Period 540 Calendar Days
Original Contract Project Start 21-November-17
Proposed Start Date 18-December-17
Actual Start Date 15-October-17
Original Contract Completion Date 14-May-19
Proposed Completion Date 10-June-19
Projected Completion Date 30-December-18
Percentage Time Elapsed 33%
Percentage Time Remaining 67%
Schedule Slippage _

Amount Accomplished this Period ₱ 4,389,908.83


Previous Amount Accomplished ₱ 116,207,351.21
Amount Accomplished to Date ₱ 120,597,260.04
Schedule Percent Accomplishment 18.82%
Percent Accomplished to Date 35.57%
Gain % 16.75%
Maximum Allowed Negative Slippage - 30%
Retention % 10%
CONSTRUCTION OF PASIG CITY SPORTS ARENA (Phase 2-Structural Works)
WEEKLY DASHBOARD Status as of 08-Jun-18
PROJECT DETAILS PROJECT MILESTONE STATEMENT OF WORK ACCOMPLISHMENT STATUS
Original Revised/ Actual/
Project Manager MILESTONE Planned Actual GAIN Current SPI Previous SPI
Contract Proposed* Forecast *
ENGR. ROBERT C. BULAN NOA 2-Nov-17 n/a 2-Nov-17
Contractor NTP 4-Dec-17 n/a 4-Dec-17
PHESCO INCORPORATED PROJECT START 21-Nov-17 18-Dec-17 15-Oct-17 SWA 18.02%
18.8 35.57% 17.56%
16.75 1.97  1.95 
2% %
PROJECT COMPLETION 14-May-19 10-Jun-19 30-Dec-18

TIME METER SWA- (PROGRESS S-CURVE)


Commencement Date 18-Dec-17 Elapsed Remaining
Client Contract Completion Date 10-Jun-19
PASIG LOCAL GOVERNMENT Total Project Duration 540 days 32% 68%
Time Elapsed 173 days
Time Remaining 367 days 0% 20% 40% 60% 80% 100%

REASONS OF DELAY
Consultant Concluded Delay Events: Ongoing delay events
TVA&P - NO MAJOR DELAY - NONE

PROGRESS HIGHLIGHTS (CONSTRUCTION MILESTONES) Progress Chart


Previous week This Week Projected Next Week % complete
35.57%
Substructure Works 67% Substructure Works 76.00% Substructure Works 80%
Superstructure Works0% Superstructure Works 0% Superstructure Works 0%
MEP Works 0% MEP Works 0% MEP Works 0%

% remaining
64.43%
QUALITY PROJECT HEALTH CHECK
Issued Closed in time Closed-late Overdue Timely % Trend
NCR's 0 0 0 0 
*** Timely % represents total NCR's closed on time. Upward trending represents improvement in timely closure
SCHEDULE SAFETY
HSE STATISTICS
Item Last Period This Week Total to date
No. of LTI(s) 0 0 0
LTIFR 0 0 0
COST QUALITY
LTISR 0 0 0
PROGRESS
S-CURVE
STATEMENT OF WORK ACCOMPLISHMENT
Planned Actual GAIN SPI

SWA 18.02%
18.82% 35.57% 17.56%
16.75% 1.97

Reasons for positive variance:

1. Bending & cutting of rebars, rebar fixing/installation and concreting of footing


tie beams contributed this period that causes positive variance.
MANPOWER HISTOGRAM
MANPOWER HISTOGRAM
EQUIPMENT HISTOGRAM
EQUIPMENT HISTOGRAM
CONSTRUCTION
(LOOK- AHEAD)
ACTIVITIES THIS PERIOD

1. Fabrication of rebars for footing tie beams and ties for columns
2. Column ties installation
3. Continuous dewatering
4. Backfilling
5. Removal of eroded soils
6. Deshuttering works

PLAN NED ACTIVITIES FOR NEXT PERIOD

1. Rear installation for pile caps


2. Continue installation of column ties
3. Continue formworks installation for FTB at zone 3
4. Concrete pouring
ARENA PROGRESS LAYOUT
Zone 1 Legend:

Concreted pile cap

Concreted FTB

On-hold
Zone 3

Rebar installed

Zone 2
Zone 4
PROJECT RELATED
ISSUES/ CONCERNS
PROJECT RELATED CONCERNS

NONE
QA/QC, SAFETY &
SECURITY CONCERNS
QA/QC CONCERNS

 LOAD ALLOWANCE
SAFETY & SECURITY CONCERNS

1. ABSENCE OF ENVIRONMENTAL OFFICER (PCO) ASSIGN TO


MONITOR WASTE MANAGEMENT OF PROJECT SITE.

2. NO PROPER SEGREGATION OF WASTE MATERIALS.

3. ABSENCE OF HEALTH AND SAFETY COMMITTEE.

4. POOR PERMIT TO WORK SYSTEM.

5. ABSENCE OF ORIENTATION ROOM.

6. LACK OF MEDICINE/ MEDICAL SUPPLIES.


WEATHER REPORT &
FORECAST
Phase II- Structural Works

PASIG LOCAL GOVERNMENT

CONSTRUCTION OF PASIG CITY SPORTS ARENA

Phase II- Structural Works

Rosario, Pasig City

WEATHER REPORT
Period Covered: June 09 to June 15, 2018

WEATHER
DATE REMARKKS UNWORKABLE DAYS
AM PM

June 9, 2018 HR HR /

June 10, 2018 SUNDAY

June 11, 2018 NO WORK

June 12, 2018 NO WORK

June 13, 2018 RS HR NO WORK

June 14, 2018 RS RS Working areas were fully saturated. All major works are suspended. /

June 15, 2018 HR RS All Earthworks suspended. /

Legend: F-Fair C-Cloudy R-Rain Shower HR-Heavy Rain I-Intense Rain


PROJECT SITE PHOTOS
CONSTRUCTION TOOL BOX

ONGOING TOOL BOX


MEETING.
Ongoing fabrication of rebars for footing tie beams and columns.
REBAR WORKS

Ongoing installation of lateral ties for columns.


Ongoing Bed prepation for
Dewatering
pile cap foundations
Site condition after heavy rain.
Ongoing restoration of eroded areas caused by heavy rain.