30-08-2019-CHP Construction Weekly PRM PPT R1
30-08-2019-CHP Construction Weekly PRM PPT R1
Financial Progress
Sl.NO Description Contract Value in Cr % Comp.
in Cr
1 Contract I 150.13 38.8
88 %
47.5%
Engineering Status
99.9 %
Engineering Progress Plan Vs Actual
100%
Plan-CUM
90% 97.0%
Actual-CUM
80% CU PLAN-CUM
70%
% Progress
60%
50%
40%
30%
20%
10%
0%
Nov/ Dec/ Jan/1 Feb/ Mar/ Apr/ May/ Jun/ Jul/1 Aug/ Sep/ Oct/ Nov/ Dec/ Jan/1 Feb/ Mar/ Apr/ May/ Jun/ Jul/1 Aug/ Sep/
17 17 8 18 18 18 18 18 8 18 18 18 18 18 9 19 19 19 19 19 9 19 19
Plan-CUM 0% 1% 5% 8% 19% 33% 44% 57% 64% 71% 77% 82% 85% 88% 94% 97% 98% 98% 98% 98.8%98.8%99.9%100%
Actual-CUM 0% 1% 4% 6% 13% 22% 28% 35% 39% 42% 44% 48% 51% 58% 64% 68% 71.3%78.4%86.2%93.1%95.4%97.00
CU PLAN-CUM 97.00 100%
NTP Month
Ordering Status
90%
Plan-CUM 97.5%
Actual-CUM
80% CU PLAN-CUM
70%
% Progress
60%
50%
40%
30%
20%
10%
0%
Nov/ Dec/ Jan/1 Feb/ Mar/ Apr/ May/ Jun/1 Jul/1 Aug/ Sep/ Oct/ Nov/ Dec/ Jan/1 Feb/ Mar/ Apr/ May/ Jun/1 Jul/1 Aug/ Sep/
17 17 8 18 18 18 18 8 8 18 18 18 18 18 9 19 19 19 19 9 9 19 19
Plan-CUM 0% 0% 0% 0% 0% 5% 13% 21% 29% 35% 46% 62% 74% 90% 98% 99% 99.8% 100% 100% 100% 100% 100% 100%
Actual-CUM 0.0% 0.0% 0.0% 0.0% 0.0% 4.6% 12.6%19.4%26.4%29.6%34.7%41.3%66.8% 80% 81% 84% 85% 89.2%89.8% 93% 96% 97.5%
CU PLAN-CUM 97.5% 100%
NTP Month
Delivery Status
60%
50%
40%
30%
31 %
20%
10%
0%
Nov Dec/ Jan/ Feb/ Mar/ Apr/ May Jun/ Jul/1 Aug Sep/ Oct/ Nov Dec/ Jan/ Feb/ Mar/ Apr/ May Jun/ Jul/1 Aug Sep/ Oct/ Nov Dec/
/17 17 18 18 18 18 /18 18 8 /18 18 18 /18 18 19 19 19 19 /19 19 9 /19 19 19 /19 19
Plan-CUM 0% 0% 0% 0% 0% 0% 1% 1% 3% 4% 7% 9% 13% 19% 26% 34% 45% 57% 69% 79% 88% 94% 98% 99% 100%100%
Actual-CUM 0.0% 0.0% 0.0% 0.1% 0.3% 0.5% 0.7% 1.0% 1.5% 2.0% 2.4% 2.9% 3.7% 6.2% 11.5 16% 18.5 20.8 21.2 24.8 28.5 31%
CU PLAN-CUM 31% 61% 86% 96% 100%
NTP Month
Note :- Actual Progress % showing supply of structural steel, Equipment manufacturing clearance and manufacturing
Construction Status
Construction Status
100%
90%
Plan-CUM 83 %
80% Actual-CUM
CU PLAN-CUM
70%
% Progress
60%
50%
40% 40.3%
30%
20%
10%
0%
Nov Dec/ Jan/ Feb/ Mar/ Apr/ May Jun/ Jul/1 Aug/ Sep/ Oct/ Nov Dec/ Jan/ Feb/ Mar/ Apr/ May Jun/ Jul/1 Aug/ Sep/ Oct/ Nov Dec/ Jan/ Feb/ Mar
/17 17 18 18 18 18 /18 18 8 18 18 18 /18 18 19 19 19 19 /19 19 9 19 19 19 /19 19 20 20 20
Plan-CUM 0% 0% 0% 1% 2% 3% 4% 5% 6% 8% 10% 13% 17% 23% 29% 35% 43% 51% 59% 67% 76% 83% 89% 94% 97% 98% 100%100%100%
Actual-CUM 0% 0% 0% 1% 1% 2% 3% 4% 4% 5% 6% 6% 8% 10% 12.4 15.3 16.8 22.1 24.8 31.9 37% 40.3
CU PLAN-CUM 40.3 48% 57% 67% 78% 87% 95% 100%
NTP Month
Construction Discipline wise Status
Plan
Construction Status Str.Erection, 7%
Str.Erection 7% 1%
Mechanical 9% Actual
Str.Erection, 1%
Ele.&Inst. 6%
Str.Fabrication,
6%
No Load Trial 3%
Commissioning 3% Civil Work,
33%
General
o Area Grading - 63% completed.
o Over Ground Bunker - 100% Table Slab work at 3.75 mtr completed. First lift of Hopper walls
completed & beam work in progress-Overall Progress- 51%
o Dumper unloading station and receiving pit – Civil work 76% completed
o CEO Office Building, Training Centre, Canteen Building, Fire station building, security room near main
gate complex rood of slabs completed. Finishing work in progress.
o CHP Office Building – Ground floor and First Floor slab casting 100% completed.
o Rapid Loading System (RLS) - Concrete Foundations completed. Erection planned on 07/09/2019.
o Mine Weigh Bridge – Weigh Bridge installation and Control Room building commissioning completed.
o Rail Over Bridge 2 – Start of Girder Erection planned on 10/09/2019.
Contd.
Transfer Houses
o All Civil foundation works completed
Conveyors:
o BC 2A/2B – All 22 RCC Column completed
Cum Cum
Plan for Achieved Cum.
Sl. No. Activity Unit Scope Plan as Catch Up
Aug'19 in Aug'19 Achieved
per L3 Plan
40000 39685
36102
33805
30970 31126
30000 29465
25647
25445
22393
19104
20000 18889
14918 15229
10493 11914
10000 6784 8480
3969 5763
1477 2375
508 9461326
3743
7 23 150 185 1014 1733 2185 2771
0
Apr/1 May/1 Aug/1 Sep/1 Oct/1 Nov/1 Dec/1 Feb/1 Mar/1 Apr/1 May/1 Aug/1 Sep/1 Oct/1 Nov/1 Dec/1 Feb/2
Jun/18 Jul/18 Jan/19 Jun/19 Jul/19 Jan/20
8 8 8 8 8 8 8 9 9 9 9 9 9 9 9 9 0
CUM Plan 7 150 508 946 1477 2375 3969 6784 10493 14918 19104 25647 30970 36102 41607 45039 48364 51690 54223 56155 57098 57657
CUM CU
33805 39685 45985 52085 55585 57085 57754
Plan
CUM
23 185 1014 1326 1733 2185 2771 3743 5763 8480 11914 15229 18889 22393 25445 29465 31126
Actual NTP Month
Cumulative Structural Fabrication Plan Vs Actual
6300 6026
Metric Ton
5903
5551
5400 4937 5188
4500 4454
3649 3752
3600
2700 2749
2000
1800 1745
763 9…
900
238 505
0 0 1 31 19 54 79 102 204
0
Jul/18 Aug/18 Sep/18 Oct/18 Nov/18 Dec/18 Jan/19 Feb/19 Mar/19 Apr/19 May/19 Jun/19 Jul/19 Aug/19 Sep/19 Oct/19 Nov/19 Dec/19
CUM Plan 0 1 19 238 763 2000 3649 4937 6026 6699 7333 7906 8249 8377 8478 8537 8537
CU PLAN (CUM) 5903 6853 7553 7878 8000
CUM Actual 0 31 54 79 102 204 505 962 1745 2749 3752 4454 5188 5551
NTP Month
Cumulative Structural Erection Plan Vs Actual
NTP Month
Receiving Pit Area
Transfer House (TH-2) - Structural Erection
Transfer House (TH-3) - Structural Erection
Transfer House (TH-4) - Structural Erection
Transfer House (TH-5) & TC-1A/1B - Structural Erection
Over ground Bunker
Transfer House (TH-6) & BC-6A/6B- Structural Erection
Belt Conveyor (BC-7A/7B) - Structural Erection
Transfer House (TH-7) & BC-8A/8B - Structural Erection
Transfer House (TH-8) - Structural Erection
RLS Building
Admin & CEO Office Building
CHP Office building
CHP Main Sub-station Building
CHP Store Shed - Structural Erection
Fire Fighting Pump House Building
Road from Mines to Garia Nalah
Thank You