Professional Documents
Culture Documents
(Cost Management) - Report On Cost Control
(Cost Management) - Report On Cost Control
16
What’s More Important?
17
Some New Terms
PV – Planned Value
AC - Actual Cost
EV – Earned Value
18
Earned Value Management
Planned Value
PV or BCWS = Hourly Rate × Total
Hours Planned or Scheduled
Actual Cost
AC or ACWP = Hourly Rate × Total
Hours Spent
Earned Value
EV or BCWP = Baselined Cost × %
Complete Actual
Note: All these three elements can be derived from Work Breakdown Structure by
associating the costs to each of the tasks.
Earned Value Management
% COMPLETED PLANNED
It is calculated using the following formula:
% Completed Planned = PV / BAC
% COMPLETED ACTUAL
% Completed Actual = AC / EAC
Earned Value Management
COST VARIANCE
CV can be calculated using the
following formula:
Cost Variance (CV) = Earned
Value (EV) − Actual Cost (AC)
Cost Variance (CV) = BCWP −
ACWP
Note: Positive CV indicates the project is under-budget; negative
CV indicates the project is over-budget.
Earned Value Management
COST PERFORMANCE INDICATOR
CPI can be calculated using the
following formula:
CPI = Earned Value (EV) ⁄ Actual
Cost (AC)
CPI = BCWP ⁄ ACWP
Note:
A CPI value above 1 indicates the efficiency of utilizing
the resources allocated to the project is good.
A CPI value below 1 indicates the efficiency of utilizing
the resources allocated to the project is not good
Earned Value Management
SCHEDULE VARIANCE
It can be calculated using the following
formula:
Schedule Variance (SV) = Earned
Value (EV) − Planned Value (PV)
Schedule Variance (SV) = BCWP −
BCWS
Note:
A positive SV indicates we are ahead of schedule.
A negative SV indicates we are behind schedule.
Earned Value Management
SCHEDULE PERFORMANCE INDICATOR
SPI can be calculated using the following
formula:
SPI = Earned Value (EV) ⁄ Planned
Value (PV)
SPI = BCWP ⁄ BCWS
Note:
An SPI value above 1 indicates the project team is very
efficient in utilizing the time allocated to the project.
An SPI value below 1 indicates the project team is less
efficient in utilizing the time allocated to the project.
Earned Value Management
BUDGET AT COMPLETION
is the total budget allocated to the project
generally plotted over time.
is used to compute the Estimate at
Completion (EAC)
It can be calculated using the following
formula:
BAC = Baselined Effort − hours ×
Hourly Rate
Earned Value Management
ESTIMATE AT COMPLETION
There are four methods to calculate
EAC:
BAC / CPI
AC + (BAC − EV)
AC + ETC (Estimate To Complete)
AC + (BAC − EV) ⁄ (CPI*SPI)
Earned Value Management
VARIANCE AT COMPLETION
is the total budget allocated to the project
generally plotted over time.
is used to compute the Estimate at
Completion (EAC)
SPI can be calculated using the following
formula:
BAC = Baselined Effort − hours ×
Hourly Rate
But How Do I Do All This Stuff?
Trend Cyclical
Seasonal Random
Time series: simple moving average
Month Bottles
Jan 1,325
Feb 1,353 What will
the sales
Mar 1,305 be for
Apr 1,275 July?
May 1,210
Jun 1,195
Jul ?
What if we use a 3-month simple moving average?
What do we observe?
wt + wt-1 + … + wt-n = 1
For a 6-month
SMA, attributing
equal weights to
all past data we
miss the
Time
Jan Feb Mar Apr May Jun Jul Aug downward trend
Example: Kroger sales of bottled water
Month Bottles
Jan 1,325
What will
Feb 1,353 be the
sales for
Mar 1,305 July?
Apr 1,275
May 1,210
Jun 1,195
Jul ?
6-month simple moving average…
Make the weights for the last three months more than
the first three months…
Over budget
TCPI = (BAC – EV) / (EAC – AC)
To-Complete Performance Index
CPI is the past cost performance of the project; on the
other hand, TCPI is the future cost performance of the
project.
Since the cost performance index is 0.67, which is less than one, you
are over budget. Therefore, in this case you will use the TCPI formula
based on the EAC.
Estimate at Completion (EAC) = BAC / CPI
= 100,000 / 0.67
= 149,253.73 USD
Variance analysis
Trend analysis.
Earned value performance.
To-Complete Performance Index
Variance analysis, as used in EVM, is the
explanation (cause, impact, and corrective
actions) for cost (CV = EV – AC),
schedule (SV = EV – PV), and
variance at completion (VAC = BAC – EAC)
Client Server
- the software is installed on a company’s
server and allows multiple users to be logged into
the application at once. This software type allows
for centralized data storage to make collaboration
easier.
Types of Project Management Software:
Web-based
- uses software that is accessed through the
internet, allowing access from any computer and any
location. The software is updated and maintained by
the provider, which is often less expensive the outright
purchasing software. Web-based software allows
easier collaboration and central data storage.
Integrated
- combines project management functions with
other aspects of a company’s business, such as
invoicing. Integrated software applications are either
installed on the company’s server or are accessed
through the internet.
Example:
mpower is a project cost control and
performance management system for
engineering, construction, maintenance and
operations environments. mpower's powerful
cost control software and management features
allow it to work seamlessly alongside other
project management software products like
Primavera.
EcoSys Projects is a web-based project cost
management solution which combines the
usability of Excel-like spreadsheets, with the
power and control of an enterprise database
application. It provides visibility into project
costs, efficiency in cost management, and
greater accuracy and accountability. EcoSys
Projects is designed to provide robust cost
management capabilities that span the planning
cycle, from estimating, to budgeting and
forecasting, through all stages of project
execution.
Reserve Analysis
Is used to monitor the status of contingency and
management reserves for the project to
determine if these reserves are still needed or if
additional reserves need to be requested.
Causes of Variances